ARTICLE
18 September 2025

Contract Performance Disputes In India: Defending Against Termination, LD, And Risk-Purchase Claims

MC
MAHESHWARI & CO. Advocates & Legal Consultants

Contributor

MAHESHWARI & CO., a multi-speciality law firm, advice on a variety of practice areas including Corporate & Commercial Law, M&A, IPR, Real Estate, Litigation, Arbitration and more. With expertise across diverse sectors like Automotive, Healthcare, IT and emerging fields such as Green Hydrogen and Construction, we deliver legal solutions tailored to evolving industry needs.
Public and private sector contracts in India often end up in disputes not because contractors underperform, but because projects are delayed, disrupted, or changed mid-stream...
India Government, Public Sector
Maheshwari & Co.’s articles from MAHESHWARI & CO. Advocates & Legal Consultants are most popular:
  • within Government and Public Sector topic(s)
  • in India
  • with readers working within the Law Firm industries
MAHESHWARI & CO. Advocates & Legal Consultants are most popular:
  • within Government, Public Sector, Transport and Environment topic(s)

Public and private sector contracts in India often end up in disputes not because contractors underperform, but because projects are delayed, disrupted, or changed mid-stream in ways no party anticipated. Contractors are then penalised with liquidated damages (LD), threatened with wrongful termination, or saddled with inflated "risk-purchase" claims when the employer re-awards unfinished work. These disputes fall squarely within the arena of tender litigation in India, and contractors who do not contest such actions often lose not just margins but reputation and future opportunities.

The Indian tender litigation process recognises the need for balance between employer rights and contractor defences. Wrongful termination of a government contract, excessive liquidated damages, or exaggerated risk purchase claims can all be challenged before arbitral tribunals or courts. For contractors, the key is to frame a claims suite—extension of time (EOT), price escalation, disruption costs—and to marshal hard evidence like CPM schedules, site diaries, and correspondence.

Explore More: Arbitration Law Firm in India

Claim Heads That Win

In Indian contract disputes, the contractor's survival often depends on how well claims are framed. A defence that only reacts to LD or termination notices is not enough; tribunals expect contractors to establish affirmative claims. The strongest heads typically include:

  1. Extension of Time (EOT) Claims
    • When delays are attributable to the employer—late site handover, delayed drawings, approvals, or change orders—the contractor is entitled to time extensions. This defence not only negates liquidated damages but also preserves contractual rights against wrongful termination. Courts in India have consistently held that LD cannot be levied if the employer caused the delay.
  2. Price Escalation and Variation Claims
    • Government contracts often fix base prices, but prolonged delays inflate input costs. Where escalation clauses exist, they must be invoked. Even in their absence, claims may be pursued under Section 73 of the Indian Contract Act as compensation for prolonged performance beyond the agreed period.
  3. Disruption and Idle Cost Claims
    • Losses from under-utilised manpower, machinery idling, and work stoppages due to employer instructions can be significant. Contractors can press disruption claims with quantified site diaries, equipment logs, and correspondence showing who caused the stoppage.
  4. Set-Aside of Wrongful Termination
    • If an employer terminates without establishing contractor default, tribunals can declare the termination illegal. Reliefs often include damages for loss of profit on the unexecuted portion of the contract. This defence is particularly strong in cases of wrongful termination in government contracts, where procedural safeguards are mandatory.
  5. Rebuttal of Risk-Purchase Claims
    • Employers often inflate re-tender costs, claiming the difference from the terminated contractor. The contractor can argue (a) that the termination itself was invalid, (b) that the re-award price was commercially unreasonable, and (c) that no causal link exists between the contractor's alleged breach and the increased price.

Evidence That Sticks

Arbitration in India is evidence-driven. A contractor's defence against liquidated damages, wrongful termination of government contracts, or risk purchase claims will stand only if backed by a consistent documentary trail. Oral assertions rarely survive scrutiny. The following categories of proof typically make or break a case:

  1. Critical Path Method (CPM) Schedules
    • Delay analysis is best presented through CPM or Primavera schedules. They demonstrate which activities drove project delays, and whether they were employer-responsible or contractor-driven. Without such analysis, tribunals often default to the employer's version of events.
  2. Site Diaries and Progress Reports
    • Daily site logs showing manpower, equipment, weather, stoppages, and instructions record the lived reality of the project. When these align with correspondence, they provide contemporaneous evidence that delays were not of the contractor's making.
  3. Correspondence and Notices
    • Letters, emails, and minutes of meetings that document requests for drawings, approvals, or clarifications show that the contractor flagged issues in real time. Tribunals often ask: did the contractor protest employer-caused delay at the time, or only after LD was imposed?
  4. Engineer/PMC Instructions
    • Written directions from the Project Management Consultant (PMC) or Engineer-in-Charge—especially instructions to suspend or change work—become vital to show disruption costs or excusable delays.
  5. Financial Records
    • Idle machinery expenses, wage sheets for standby manpower, and vendor invoices establish the monetary impact of delay and disruption. Without these, quantum claims risk being struck down as speculative.

Employers often argue that contractors failed to maintain proper records. Contractors who build a meticulous paper trail not only neutralise LD but also strengthen offensive claims. In Indian tender litigation, evidence that sticks is often evidence created contemporaneously, not reconstructed after the dispute arises.

Quantum Methods

Once liability is established, the next hurdle is quantification. Indian arbitral tribunals are wary of inflated claims. They expect a disciplined methodology, not broad assertions of loss. Contractors facing liquidated damages defence in India, wrongful termination government contracts, or risk purchase claims should adopt tested approaches to compute entitlements:

  1. Measured Mile Analysis
    • Compares productivity in an undisrupted period against a disrupted one to establish loss of efficiency. This is widely accepted in international arbitration and increasingly recognised in Indian disputes.
  2. Actual Cost Records
    • Payroll sheets, plant hire bills, and subcontractor invoices form the most persuasive evidence. Tribunals are far more inclined to accept actual financial records than hypothetical estimates.
  3. Formula-Based Calculations
    • In long-running infrastructure disputes, tribunals sometimes apply Hudson or Emden formulas to assess overheads and loss of profit. While courts in India caution against mechanical application, these formulas serve as fallback tools when actual cost records are patchy.
  4. Loss of Profit on Unexecuted Work
    • In cases of wrongful termination, contractors can claim the margin they would have earned on the balance contract value. The quantum often turns on past project margins or audited financial statements.
  5. Rebutting Risk-Purchase Inflation
    • Contractors can challenge employer calculations by producing market rates at the time of termination, showing that the re-award was overpriced. Evidence of comparable tenders helps reduce or nullify inflated demands.

The art lies in presenting numbers that are both defensible and consistent with the contract record. Tribunals are inclined to award only what they can verify. A claim that blends actual cost data with recognised quantum methodologies stands the best chance of success.

Enforcement and Settlement Levers

Even a well-won award means little if it cannot be enforced. Contractors in India facing LD disputes, wrongful termination claims, or risk purchase demands must plan their forum strategy and enforcement roadmap from the outset. The key levers include:

  1. Contractual Dispute Boards (if provided)
    • Many infrastructure contracts provide Dispute Adjudication Boards (DABs) or Dispute Review Boards (DRBs). Though often overlooked, timely reference to these forums can secure interim relief and create a favourable record for arbitration.
  2. Section 9 Relief (Interim Measures from Court)
    • Before or during arbitration, contractors can approach courts under Section 9 of the Arbitration and Conciliation Act to restrain encashment of bank guarantees, stop coercive recoveries, or preserve evidence. This is often the first line of defence when an employer invokes LD or threatens risk-purchase recovery.
  3. Section 17 Relief (By the Tribunal)
    • Once the arbitral tribunal is in place, Section 17 empowers it to grant interim measures. Tribunals can order release of withheld payments, stay of LD deductions, or security for counterclaims.
  4. Arbitration on the Merits
    • The full hearing allows contractors to seek declaration of wrongful termination, reduction or annulment of LD, and damages for delay/disruption. Proper sequencing of claim heads and evidence presentation often decides outcomes.
  5. Enforcement of Awards
    • Arbitral awards are enforceable as court decrees under Section 36. Government employers may resist, but Indian courts have shown increasing reluctance to grant unconditional stays. Interest awards, often significant, become leverage for negotiated settlements.
  6. Settlement Dynamics
    • Employers—especially PSUs and government departments—are often willing to settle once an award or interim order exposes their financial exposure. A contractor with a strong paper trail and favourable interim orders is in the best position to negotiate write-backs of LD or waiver of risk-purchase claims.

In short, success is not only about winning the arbitration but also about leveraging interim reliefs, shaping enforcement pressure, and driving settlement at the right stage.

Conclusion

Contract performance disputes in India rarely boil down to a single issue. A contractor penalised with liquidated damages, faced with wrongful termination of a government contract, or burdened with inflated risk purchase claims must approach the fight as a strategic litigation suite. The defensive side—negating employer penalties—must be balanced with offensive claims for EOT, disruption costs, escalation, and loss of profit.

The tender litigation process in India rewards those who build their case brick by brick: CPM schedules that demonstrate critical delays, site diaries and correspondence that pin responsibility on the employer, financial records that quantify costs, and carefully chosen quantum methods that withstand tribunal scrutiny. Interim reliefs under Sections 9 and 17 can buy time and breathing space, while strong awards backed by enforceable evidence often shift employers towards settlement.

For contractors, the key message is this: do not treat LD demands, termination notices, or risk purchase recoveries as fait accompli. Each of these can be challenged, reduced, or reversed. With the right evidence, claims strategy, and procedural moves, what begins as a penalty can end as a recovery.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More