Modernization Of The CCDC Contracts: A Retrospective On The Recent Updates And What They Mean For Ontario Owners And Contractors

Over the years, the Canadian Construction Documents Committee (CCDC)1 has built out a suite of standardized documents for procurement and delivery...
Canada Ontario Real Estate and Construction

Over the years, the Canadian Construction Documents Committee (CCDC)1 has built out a suite of standardized documents for procurement and delivery of construction projects in Canada, including:

  • Fixed price contracts (e.g., CCDC 2 – Stipulated Price, CCDC 2MA – 2023 Master Agreement between Owner and Contractor, CCDC 3 – Cost Plus, CCA 1 – Stipulated Price Subcontract);
  • Construction management (CCDC 5A/5B) and trade contractor forms (CCDC 17);
  • Design-build and civil works contracts;
  • Insurance and bonds (e.g., CCDC 41 insurance requirements; CCDC 220/221/222 surety bond forms); and
  • Practice guides (e.g., Division 00/01 master specs; contract administration and insurance guides).

As the market and legal landscape shift, the CCDC continues to improve the contract forms to reflect the legal and practical realities of our markets. This article rounds up the series of recent changes to the CCDC forms over the past half-a-decade.

The big pivot in 2020: CCDC 2 gets modernized

After a 12-year run of CCDC 2 (2008), the Committee issued CCDC 2 (2020). The 2020 edition introduced several structural changes aimed at reducing supplementary conditions and aligning with provincial prompt-payment regimes, including Ontario's Construction Act reforms. Notable additions are:

  • Ready-for-Takeover (RFT) as a defined completion milestone has now replaced Substantial Performance of the Work as the key contractual milestone (although Substantial Performance of the Work remains a key milestone under the Act);
  • Early Occupancy rules allowing an owner to occupy all/part of the work before RFT (subject to approval of authorities having jurisdiction and contractor agreement), with responsibility for insurance and warranty start dates shifting for any owner-occupied portion;
  • Cross-references to provincial payment legislation, including interim adjudication and prompt payment stipulations; and
  • Related insurance updates coordinated through CCDC 41 (2020).

At the time of issuing the CCDC 2-2020, the CCDC Master Specification for Division 01 – General Requirements was also published by the CCDC. Chiefly, certain items (such as cutting, cleanup and remedial work) which were previously in the general conditions of the former CCDC 2 – 2008 have been moved into the new Division 01 – General Requirements form. Further, with the CCDC 41 (2020) refresh, higher insurance limits, contractors' pollution liability coverage and UAV liability were introduced to the broader non-P3 segment of the market.

For vertical alignment with the standard form stipulated price subcontract, the Canadian Construction Association (CCA)2 released an updated version of the CCA 1- 2021: Stipulated Price Subcontract in December 2021 to align more closely with the CCDC 2-2020 – Stipulated Price Contract, being the standard prime contract.

The newest wave (June–July 2025): Construction Management and IPD refresh

In June–July 2025 CCDC released significant updates to the construction management (CM) and integrated project delivery (IPD) suites, with outreach through industry associations and seminars:

  • CCDC 5A (2025) – Construction Management for Services
  • CCDC 5B (2025) – Construction Management for Services and Construction
  • CCDC 17 (2025) – Stipulated Price Contract for Trade Contractors on CM projects
  • CCDC 30 (2025) – Integrated Project Delivery Contract (and CCDC 30-G (2025) Guide)

Key 2025 themes to know:

  • Pre-construction services are clearly delineated: CCDC 5A/5B now let parties separately define fee for pre-construction (and, in CCDC 5A, even post-construction) services, as opposed to blending them into one CM fee structure.
  • Owner suspension/termination for convenience: CCDC 5A/5B now created new entitlement. Specifically, CCDC 5B introduces a break fee (which is tied to the agreed cost estimate class) if termination for convenience happens during the pre-construction phase.
  • Early occupancy mechanics extend beyond CCDC 2: CCDC 5A/5B and CCDC 17 forms now expressly allow early occupancy of part/all of the project before RFT, with corresponding shifts in health and safety responsibility, as well as insurance and warranties liabilities for owner-occupied areas/phases.
  • Availability and transition: The new documents went live at the end of June 2025 and are being distributed electronically, with a one-year transition window.
Recent changes to CCDC 30: Clarification of definitions and roles

The updated CCDC 30 provides clearer definitions of key terms and roles within the IPD framework. This includes more precise descriptions of the responsibilities and expectations for each party, which helps to reduce ambiguities and potential disputes. For example, the roles of the Core Group (the decision-making body) and the Project Team are more clearly delineated, ensuring all parties understand their authority and obligations.

Enhanced "Ready-for-Takeover" provisions

The "Ready-for-Takeover" concept, first introduced in CCDC 2-2020, has now been incorporated into CCDC 30. This addition establishes a clear milestone for project completion and handover, providing all parties with a well-defined point at which the owner can take possession and the warranty period commences. This clarity benefits owners, contractors and suppliers by reducing uncertainty around project closeout.

Early occupancy provisions

The new version of CCDC 30 introduces provisions for early occupancy, allowing owners to occupy and use portions of the project before full completion. This flexibility can be particularly valuable for phased projects or where operational needs require partial handover. The contract now sets out the process, conditions, and implications for early occupancy, including how it affects warranties, insurance, and responsibilities for those portions of the work.

Editable schedules and customization

CCDC 30 now includes editable schedules, making it easier for parties to tailor the contract to the specific needs of their project. This customization can cover project milestones, deliverables, payment terms, and other key elements, allowing for a more flexible and project-specific approach to contract administration.

Electronic format availability

The latest CCDC 30 is now available in electronic format, which streamlines document management, distribution, and execution. This change enhances accessibility and efficiency, making it easier for all parties to collaborate and maintain up-to-date records.

Improved change management processes

The updated CCDC 30 contract refines the procedures for managing changes, including how changes are proposed, evaluated, and approved within the collaborative IPD environment. This includes clearer processes for documenting and agreeing on changes to scope, cost, and schedule, which is essential for maintaining trust and transparency among all parties.

In addition to the foregoing, the CCDC 30 also received other updates in its 2025 edition, including the introduction of an IPD Advisor, formalizing the 'Big Room' concept for collaboration, providing greater detail on the validation phase, enhancing termination rights, and introducing new clauses for curing default. The 2025 CCDC 30 also updates the profit pool terminology to reflect the intent of the funds and expands the list of reimbursable costs.

Ontario-specific impacts of these changes

Ontario's prompt payment and adjudication regime (in force since October 1, 2019) sets statutory clocks (often described as the "28-7-7" cadence) and obliges parties to adjudicate quickly if payment is disputed. CCDC 2 (2020) explicitly acknowledges such provincial payment legislation, and the newer CCDC 5A/5B and CCDC 30 forms are updated to align with the statutory framework. For Ontario projects, this means:

  • Payment timelines are statutorily monthly unless a contract structure shifts the "proper invoice" trigger from monthly issuance to a milestone structure; owners must pay within 28 days of a proper invoice or issue a notice of non-payment (with downstream timing obligations).
  • If a payer withholds payment because they weren't paid by the owner, they must commence adjudication promptly to justify their own inevitable non-payment down the chain.
  • Contracts should now line up their invoice timing, certification steps (if any), and milestones with Ontario's rules to avoid accidental breaches.

How specific CCDC changes play out in Ontario: Considerations for supplementary conditions

a) Ready-for-Takeover vs. lien milestones

It is important to note that RFT (which is a contractual milestone) doesn't change Ontario's lien triggers (e.g., substantial performance under the Act); however, it does influence warranty start, care of the work responsibilities, and liability for liquidated damages within the contract. Parties should coordinate RFT with certificate of substantial performance dates to manage holdback release and lien enforcement deadlines, subject to the Construction Act (Ontario).

b) Early occupancy

If an Ontario owner takes early occupancy, the occupied portion is deemed taken over. Accordingly, care responsibilities shift to the owner; warranty periods start for that portion of the work; and insurance responsibilities may change. Parties should coordinate this with municipal occupancy permissions and ensure partial occupancy doesn't unintentionally trigger lien/posting issues or alter site safety controls.

c) Construction management (CCDC 5A/5B) fee architecture

The 2025 separate pre-construction fee structure clarifies budgeting and makes it easier to terminate pre-construction without wading into full CM at-risk exposure. This is helpful for Ontario public and private owners navigating financing options or moving through staged approvals. The termination-for-convenience addition plus a defined break fee (in CCDC 5B) bring transparency to off-ramps; contractors should price and document pre-con value carefully to account for true Division 01 costs and any related "fast-tracked" services or early works performed during the preconstruction phase of the project.

d) Trade contractor alignment (CCDC 17 – 2025)

Updated trade contract forms for CCDC 5A arrangements help align flow-down of early occupancy, insurance and takeover concepts from the new CCDC 5A, reducing the need for bespoke supplementary conditions and avoiding gaps that could complicate prompt payment timing down the chain.

e) Insurance posture (CCDC 41)

With CCDC 41 (2020) as the market reference, expect higher and more explicit coverages (e.g., liability limits; environmental/UAV where applicable). Owners should confirm program capacity; contractors should price and coordinate endorsements across tiers to avoid uninsured exposures at early occupancy or RFT milestone.

Practical takeaways

For Ontario owners
  • Map dates: Converge RFT, substantial performance and occupancy permits into a single milestone to be reflected in the contract schedule; link the milestones to prompt payment and holdback release steps, subject to the Construction Act (Ontario) as may be amended.
  • Benefit from the bifurcation of services and fees: In CCDC 5A/5B, clearly ring-fence pre-construction scope of services and fees. In the case of CCDC 5B, negotiate a pre-determined break fee, such that if the off-ramp mechanism is deployed, the break fee will be a pre-budgeted amount absorbable by the project economics.
  • Plan early occupancy: Parties should have an occupancy plan that accounts for circumstances where the owner takes early occupancy under the contract. The parties should properly allocate risks and responsibilities in such plans for insurance, warranties, site safety interfaces, as well as utilities and security for occupied zones/phases.
For Ontario contractors/construction managers
  • Cash-flow discipline: Align proper invoice mechanics and certification steps with the Act; calendar the 28-7-7 deadlines and be ready to adjudicate on short notice.
  • Price the new risks: Consider the cost of higher insurance, pre-con deliverables, potential termination for convenience and the operational impacts of early occupancy on productivity and warranties.
  • Flow-down: Ensure use of updated CCDC 17 (2025) to keep terms consistent with the new CCDC 5A, rather than the older version of the CCDC 5A.

Footnotes

1. Formed in 1974, the CCDC is a national, industry-balanced body that develops and publishes standard contracts, guides and forms used across Canada. Its mandate is to create fair, widely adopted templates that reduce transaction costs and promote predictable risk allocation.

2.The CCA is the national association that represents the construction industry and is a key member organization of the CCDC. The CCA is a major user and endorser of the CCDC documents.

About Dentons

Dentons is the world's first polycentric global law firm. A top 20 firm on the Acritas 2015 Global Elite Brand Index, the Firm is committed to challenging the status quo in delivering consistent and uncompromising quality and value in new and inventive ways. Driven to provide clients a competitive edge, and connected to the communities where its clients want to do business, Dentons knows that understanding local cultures is crucial to successfully completing a deal, resolving a dispute or solving a business challenge. Now the world's largest law firm, Dentons' global team builds agile, tailored solutions to meet the local, national and global needs of private and public clients of any size in more than 125 locations serving 50-plus countries. www.dentons.com

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances. Specific Questions relating to this article should be addressed directly to the author.

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More