ARTICLE
16 March 2023

Louisiana Strikes A Blow Against Judicial Review Of Arbitral Error

PD
Phelps Dunbar LLP

Contributor

Phelps is a full-service Am Law 200 law firm, blending valuable traditions and progressive ideas to foster a culture of collaboration among our lawyers in Alabama, Florida, Louisiana, Mississippi, North Carolina, Tennessee, Texas, and London. The firm’s lawyers handle a broad range of sophisticated business needs regionally, nationally, and internationally.
Continuing with the theme of last week's post, in a recent decision, the Louisiana First Circuit Court of Appeals upheld a trial court's confirmation of an arbitration...
United States Louisiana Litigation, Mediation & Arbitration

This article was written for The Dispute Resolver and was published February 28, 2023.

Continuing with the theme of last week's post, in a recent decision, the Louisiana First Circuit Court of Appeals upheld a trial court's confirmation of an arbitration award of over $500,000, even though the award contained two errors of undisputed fact that the dissenting opinion argued, if corrected, would have resulted in an award in favor of the non-prevailing party. Coastal Indus., LLC v. Arkel Constructors, LLC, 2021-0906 (La.App. 1 Cir. 9/1/22); 350 So.3d 912, writ denied sub nom. Coastal Indus., LLC v. Arkle Constructors, LLC, 2022-01489 (La. 11/22/22); 350 So.3d 500

The case involved an arbitration between a subcontractor and the general contractor on a project to construct a building at a petroleum refinery. The subcontractor brought a claim to recover for amounts it contended it was due under its subcontract. The general contractor asserted a counterclaim seeking to recover for, among other things, the excess cost of completing the subcontract because of the subcontractor's alleged abandonment of the project prior to completion.

After a nine-day arbitration hearing, the arbitrator issued an award in favor of the general contractor. In rendering the award, the arbitrator found that the general contractor was entitled to recover $44,755.98 on its counterclaim.

The arbitrator calculated the award by taking the subcontract amount and subtracting therefrom the amounts the arbitrator determined the general contractor was due for excess completion costs and back charges, as well as the amounts previously paid to the subcontractor, resulting in what the arbitrator determined to be an overpayment of $44,755.98 to the subcontractor.

The arbitrator also awarded the general contractor its attorneys' fees of $408,772.46 and various costs, for a total award of $530,574.02. The trial court affirmed the arbitrator's award.

On appeal, the subcontractor contended that the award should have been vacated because the arbitrator improperly calculated the award on the counterclaim by including back charges that were withdrawn by the general contractor and excess completion costs that the general contractor acknowledged should not have been included in its claim.

In affirming the trial court's confirmation of the arbitration award, the majority opinion held that errors in factual or legal conclusions will not invalidate an otherwise fair and honest arbitration award:

This was a complicated case, with considerable evidence submitted by both parties. Upon review of that evidence, this Court may have reached different conclusions as to the interpretation of the Subcontract or the amount of damages. However, a court may not substitute its conclusions for those of the arbitrator.

The court then went on to quote the U.S. Supreme Court in Major League Players Assoc. v. Garvey, 532 U.S. 504, 509-10, 532 U.S. 1015, 121 S.Ct. 1724, 1728-29, 149 L.Ed.2d 740 (2001):"the arbitrator's 'improvident, even silly, factfinding' does not provide a basis for a reviewing court to refuse to enforce the award."

However, the dissent in the case agreed with the subcontractor and found the arbitrator had made two mistakes of undisputed fact in rendering the award by including:

  • $19,507.50 in excess completion costs, despite the fact that the general contractor acknowledged in its post-hearing brief that amount should not have been included in its claim
  • $44,906.67 in back charges that were withdrawn, as shown by the general contractor's damages summary

The dissent noted that had those two errors of undisputed fact not been part of the arbitrator's calculation, the subcontractor would have been the prevailing party and awarded $14,781.31. The dissent went on to note that the arbitrator's award of attorneys' fees to the general contractor was founded on the erroneous determination that the general contractor was the prevailing party.

The dissent found that based on state and federal case law, the arbitration award should have been vacated because of the errors of undisputed fact: "where the record that was before the arbitrator demonstrates an unambiguous and undisputed mistake of fact and the record demonstrates strong reliance on that mistake by the arbitrator in making his award, it can fairly be said that the arbitrator 'exceeded his powers, or so imperfectly executed them' that vacation may be proper." Coastal Indus., LLC v. Arkel Constructors, LLC, 350 So.912, 925 (citing Nat'l Post Office, Mailhandlers, Watchmen, Messengers & Grp. Leaders Div., Laborers Int'l Union of N. Am., AFL-CIO v. U.S. Postal Serv., 751 F.2d 834 (6th Cir.1985); and Cole v. Hiller, 30,397, p. 9 (La.App. 2 Cir. 4/8/98); 715 So.2d 451, 456, writ not considered, 98-1512 (La. 9/4/98); 723 So.2d 429).

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More