Legal Q&A: Sub ‘Volume' Discounts And Extras

PA
Peckar & Abramson PC

Contributor

For over four decades, Peckar & Abramson has been a leader and innovator in construction law, providing tailored results for its clients – delivered with a commitment to efficiency, value and client service. With over 100 attorneys in nine offices in the United States and affiliations around the globe, P&A is the recipient of many accolades that reflect the firm’s stature as the premier construction law firm in the industry. Firmly rooted in its history, P&A maintains an unmatched national presence while providing its local clients with highly sophisticated legal insights.
A subcontractor gave us a reduced price for a package of several projects, but there are separate contracts for each project.
United States Real Estate and Construction
Levi W. Barrett’s articles from Peckar & Abramson PC are most popular:
  • with readers working within the Property industries

Levi W. Barrett, co-managing partner of P&A's New Jersey office and chair of the firm's Contracts, Project Documentation, and Risk Management practice was recently featured in The Construction Broadsheet's latest "Legal Q and A" to answer questions about sub 'volume' discounts and extras.

The questions included:

  1. A subcontractor gave us a reduced price for a package of several projects, but there are separate contracts for each project. We are underway with two of them. Are we allowed to take bids on the remainder of the projects?
  2. We received design input from one of our subcontractors, and the company submitted a change order for the work they did related to that. The input was related to the sub's scope of work but did change the scope slightly. Is this really an extra? Put another way, where is the line between work "incidental" to the contract scope and work that warrants an additive change order?
  3. We made a small change to the scope of work for one of our subs, but the anticipated dollar amount is very small. At what point is a change enough to warrant additional money for the sub-performing the work?

To read Levi's responses, click HERE.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.