Ofgem's Demand Connection Queue Reform: What Data Centre Developers Need To Know
Great Britain's electricity demand connection queue has surged from 41 GW to 125 GW in just five months, driven largely by data centre applications accounting for 75 GW. Ofgem and NESO have launched consultations proposing significant reforms including a Data Centre Commitment Fee and new project progression milestones to eliminate speculative projects and ensure viable developments can progress efficiently.
Gowling WLG