We are a contemporary London law firm, rooted in tradition with a lasting legacy of client service. Founded in 1780, we recognise the long-standing relationships we have with our clients and how they have helped shape our past and provide a platform for our future. With 76 partners supported by over 300 lawyers and support staff, we operate on a four practice group model: private client, business services, real estate and dispute resolution. Our driving force is to empower our clients by providing quality legal advice, insight and intelligence that enables them to achieve their goals whether personal or business. We are large enough to advise on the most complex matters, but small enough to ensure that our people and our work remain exceptional and dynamic. Building relationships is at the heart of everything we do.
RMP Construction Services Ltd was a ground works sub-contractor which carried out works for Chalcroft ("the Main Contractor") relating to the construction of a Shell petrol station.
United Kingdom Real Estate and Construction

RMP Construction Services Ltd v Chalcroft [2015] EWHC 3737 (TCC)

RMP Construction Services Ltd was a ground works sub-contractor ("the Sub-Contractor") which carried out works for Chalcroft ("the Main Contractor") relating to the construction of a Shell petrol station.

The Main Contractor served a pay less notice under the Construction Act which, under the Main Contractor's version of the terms of the contract (the sub-contract order), was arguably served in time. Under the Sub-Contractor's version of the terms (a series of emails), the Scheme for Construction Contracts applied and the pay less notice was served late, entitling the Sub-Contractor to the full amount applied for.

The Sub-Contractor referred the matter to adjudication and the Adjudicator found in favour of the Sub-Contractor.

The Main Contractor's version of the sub-contract order was unsigned and certain terms rejected by the Sub-Contractor in writing.

The decision illustrates the dangers of relying on conversations and unsigned draft agreements, as this can ultimately lead to the parties spending time and money in proceedings to establish what the terms of the agreement were. It is essential to ensure that key contractual provisions are always documented, especially those as fundamental as payment provisions.

Practical Tip:

No worthwhile legal update is complete without a case stressing the importance of clearly documenting agreed contractual provisions in writing.

Due to the quick nature of an adjudication, adjudicators are often inadequately placed to investigate the terms of an oral contract. It is therefore, all the more important to ensure that the terms of a construction contract are clearly recorded in writing (or depending on your perspective – those not agreed clearly set out).