The President has finally issued a long-awaited regulation that maps out the road towards cleaner power generation in Indonesia, in line with the country's international climate-change commitments.

The new regulation, Presidential Regulation No. 112 of 2022 on Accelerated Development of Renewable Energy for Electricity Supply ("PR 112"),1 was issued and entered into force on 13 September 2022.

The key features of PR 112 may be summarized as follows:

A. Accelerated Energy Transition

To support the transition to greener energy in Indonesia, the Government has stepped in to restrict the development and operation of coal-fired power plants ("CFPPs") by means of the following measures:

  1. Decommissioning Roadmap
    In coordination with the Ministry of Finance ("MOF") and the Ministry of State Owned Enterprises ("MSOE"), the MEMR is required to prepare a roadmap to accelerate the decommissioning of CFPPs. The roadmap should, at minimum, address the following issues:
  1. reduction of greenhouse gas emissions from CFPPs;
  2. strategies for accelerating the decommissioning of CFPPs; and
  3. ensuring policy alignment
  1. Restrictions on New CFPPs
    The development of new CFPPs is prohibited, except for:
  1. CFPPs that were identified in state power utility PLN's Electricity Supply Business Plan (Rencana Usaha Penyediaan Tenaga Listrik  / RUPTL) prior to the issuance of PR 122; or
  2. CFPPs that satisfy the following requirements:
    1. integration with industries that are being developed in order to increase the added value of natural resources, or which are designated as national strategic projects and which provide a major contribution to job creation and/or national economic growth;
    2. Commitment given to reducing greenhouse gas emissions at the CFPP by at least 35% within 10 years from the coming on-stream of the CFPP, compared with average CFPP emissions in Indonesia in 2021. Such commitment may be realized through the application of new technology, carbon offsetting, and/or a renewable energy mix; and
    3. To be operational until 2050 at the latest (in other words, they cannot operate beyond 2050).
  1. Accelerated Decommissioning of CFPPs
    In an effort to increase the proportion of renewable energy in the electrical energy mix, PLN is required to accelerate:
    1. the decommissioning of its own CFPPs; and/or
    2. the termination of power purchase agreements ("CFPP PPA") with independent power producers (IPP) for the supply of power by CFPPs, while taking into account power supply and demand conditions.

Should the accelerated decommissioning of CFPPs require the sourcing of replacement power, this may be done from renewable energy generators, having regard once again to power supply and demand conditions.

The accelerated decommissioning process should take into account the following criteria: (i) capacity; (ii) generator age; (iii) utilization; (iv) greenhouse gas emissions; (v) economic added value; (vi) availability of domestic and overseas financing; and (vii) availability of domestic and foreign technology.

  1. Fiscal Support for Accelerated Energy Transition
    In order to accelerate the decommissioning of CFPPs and early termination of CFPP PPA contracts with IPPs, the Government may provide fiscal support through a funding and financing framework that includes blended finance sourced from the state budget and/or other sources aimed at accelerating energy transition in Indonesia.

B. Renewable Energy Purchase Price

  1. Relevant provisions of PR 112
    Prior to PR 112, the ceiling price for power sourced from renewable energy generators was determined using PLN's base electricity generating cost (biaya pokok pembangkit tenaga listrik /  BPP), By contrast, PR 112 establishes two different purchase price mechanisms: the ceiling-price mechanism and the agreed price mechanism (taking into account, or not, a location factor (F), as the case may be). Agreed purchase prices are to be evaluated on an annual basis following the coming into force of PR 112 on 13 September 2022, having regard to the latest average contract price with PLN.

    PR 112 further provides that payments for electricity purchases by IPPs should be made in IDR at the Jakarta Interbank Spot Dollar Rate (JISDOR) at the time agreed upon in the power purchase agreement.

    The following table sets out the details of the power purchase price models under PR 112.

Purchase Price Model

Applicable To

Notes

Power purchase based on ceiling price

  1. hydro power plants
  2. solar power plants or wind power plants
  3. biomass power plants or biogas power plants
  4. hydro power plants that utilize hydropower from government-owned multi-purpose reservoirs/dams and irrigation channels;
  5. additional capacity (expansion) from hydro power plants, solar power plants and wind power plants
  6. additional capacity (expansion) from biomass or biogas power plants
  7. additional capacity (expansion) from geothermal power plants
  8. excess power from geothermal power plants, hydro power plants, biomass power plants and biogas power plants

(applies to all capacities).

  1. price is determined by negotiation, with upper limit based on ceiling price, as stipulated in Annex to PR 112
  2. no escalation during PPA period; and
  3. operates as price approval from MEMR
  1. solar power plants and wind power plants of all capacities equipped with battery or other power storage facilities
  1. price is determined based on a ceiling price of 60% of the electricity purchase price.
  2. price for battery or other electrical energy storage facilities operates as price approval from MEMR.
  3. Should the price of battery or other electrical energy storage facilities amount to more than 60% of the power purchase price, price approval must be obtained from MEMR.
  1. Where a direct selection or repeat direct selection has been conducted and there is only one business entity involved in respect of the development of a (i) hydro power plant; (ii) solar power plant or wind power plant equipped or not equipped with battery facilities or other electrical energy storage facilities, whether the land is provided by government or using their own land; (iii) biomass power plant or biogas power plant; or (iv) hydro peaking power plant, biofuel power plant, or tidal/ocean thermal energy conversion power plant

Purchase price to be determined by negotiation, with upper limit based on ceiling price

  1. geothermal power plant (applies to all capacities)
  1. purchase price to be determined by negotiation, with upper limit based on ceiling price, as listed in Annex to PR 112;
  2. applies as base price;
  3. escalation applies during the PPA or the steam purchase agreement; and
  4. Operates as price approval from MEMR.

Power purchase based on agreed price between the parties

  1. hydro peaking power plant
  2. biofuel power plant or tidal/ ocean thermal energy conversion power plant,

(applies to all capacities)

Price to be determined by negotiation and price approval of MEMR required.

Note: An earlier draft of PR 112 included a feed-in-tariff pricing mechanism. However, this has been omitted from the definitive version of PR 112 as the government appears to believe that current market conditions no longer require subsidization of this kind.

The purchase price of electricity under PR 112 does not include the price for the use of transmission networks. This price is determined based on the agreement of the parties, up to a maximum of 30% of the power purchase price. An agreed price that does not exceed the 30% cap does not require a further price approval from the MEMR.

In the event that the price for the use of a transmission network amounts to more than 30% of the power purchase price, approval must be obtained from the MEMR.

C. Renewable Energy Procurement

PR 112 provides that the procurement of all forms of renewable energy should be conducted through direct selection, save in certain circumstances where the direct-appointment mechanism may be employed. The criteria and requirements for each type of procurement are as follows:

Direct Selection

Direct Appointment

  1. Employed for power procurements from the following types of power plant (all generating capacities):

  1. Hydro power plants;
  2. solar power plants or wind power plants, whether or not equipped with battery or other electrical energy storage facilities, including those standing on government-provided land and those standing on their own land;
  3. biomass power plants or biogas power plants; and
  4. hydro peaking power plants, biofuel power plants, and tidal/ ocean thermal energy conversion power plants.
  1. Employed for power procurements from the following types of power plant (all generating capacities):
  1. hydro power plants that utilize hydropower from government-owned multi-purpose reservoirs/dams and irrigation channels;
  2. geothermal power plants in the case of a geothermal license holder, a geothermal resources utilization concessionaire, or the holder of a joint operation contract for the exploitation of geothermal resources;
  3. additional capacity from (expanded) hydro power plants, photovoltaic solar power plants, wind power plants, biomass power plants, geothermal power plants, and biogas power plants;
  4. excess power from hydro power plants, biomass power plants, geothermal power plants and biogas power plants; and
  5. Where a direct selection or repeat direct selection has been conducted and there is only one business entity involved in respect of the development of a (i) hydro power plant; (ii) solar power plant or wind power plant equipped or not equipped with battery facilities or other electrical energy storage facilities, whether the land is provided by government or using their own land; (iii) biomass power plant or biogas power plant; or (iv) hydro peaking power plant, biofuel power plant, or tidal/ocean thermal energy conversion power plant

PR 112 sets out additional procurement requirements for the purchase of power by PLN where it is generated by the following types of power plant:

Type of Power Plant

Procurement Requirement

Hydro peaking power plant, biofuel power plant, or tidal/ocean thermal energy conversion power plant

The purchase by PLN is carried out by way of a capacity-quota offer

Biomass power plant or biogas power plant

IPP must have access to a sufficient supply of feedstock to ensure the continuity of the power plant's operation during the PPA period;

Geothermal power plant in the case of a geothermal license holder, a geothermal resources utilization concessionaire, or the holder of a joint operation contract for the exploitation of geothermal resources

IPP must have completed exploratory work and have proven geothermal reserves that are sufficient to ensure the continuity of the power plant's operation during the period of the PPA or steam sale & purchase contract;

Geothermal power plant in the case of an electricity supply business license holder (IPP) for a geothermal power plant.

The electricity supply business license holder (IPP) must have secured a commitment for the supply of geothermal steam to ensure the continuity of the power plant's operation during the PPA period (this would arise if the electricity supply business license holder / IPP is different from the geothermal license holder)

D. Other Provisions

  1. Cooperation with the holder of IUPTLS
    As one of the purposes of PR 112 is to strengthen the power supply system, PLN may purchase excess power from holders of own-use power-supply business licenses (IUPTLS) that utilize renewable energy resources.
  2. Government Support
    PR 122 mandates the Government to provide incentives in the form of (i) fiscal facilities (i.e. income tax facilities, exemptions from import duties and/or taxes, land and building tax facilities, support for geothermal development, support for financing facilities and/or the provision of guarantees by state-owned enterprises designated by the government); and (ii) non-fiscal facilities – these may be provided by the MEMR and by other sectoral ministries, and include the prioritization of renewable-energy power plants in the national spatial planning process, ease of licensing, and setting targets in the form of PLN performance indicators on the use of renewable energy so as to encourage PLN to source power from renewable energy power plants.
  3. Compensation for PLN
    PR 112 provides that if a purchase of electricity from a renewable-energy power plant results in an increase in PLN's base electricity generating cost (biaya pokok pembangkit tenaga listrik), PLN must be compensated for all additional costs incurred, within payment to be made having regard to the state's financial capacity and the provisions of laws and regulations.

ABNR commentary:

PR 112 solidifies the government's expressed commitment to energy transition by incorporating a road map for the accelerated decommissioning of existing CFPPs and a prohibition on the development of new CFPPs (subject to a number of exceptions). Further, the procurement process for new renewable-energy power plants by PLN under PR 112 is simpler and more straightforward than that for other types of power plant under the prevailing regulations at ministerial level.

However, it remains to be seen if these changes will be effective in practice, given that PR 112 ties the development of new renewable-energy power plants to the financial capacity of the state, which indirectly relates to the financial capacity of PLN to purchase power from renewable energy power plants at a price that is relatively higher than the price of power from CFPPs.

Footnote

Peraturan Presiden Republik Indonesia Nomor 112 Tahun 2022 tentang Percepatan Pengembangan Energi Terbarukan untuk Penyediaan Tenaga Listrik

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.