At RDJ, we combine legal insight and human intelligence to deliver long-lasting business impact. As one of Ireland’s leading corporate law firms, we’re as ambitious for your business as you are. With offices in Cork, Dublin, Galway and London, we represent clients from scaling and established Irish companies to multinationals, financial institutions and global insurance companies with unique cross-sectoral expertise. We build meaningful relationships with clients and counsel to deliver tangible value for more sustainable businesses, becoming our client’s most trusted advisors and the number one employer of choice for legal talent in Ireland. And, by investing in the progress of our people and harnessing new technologies, we power agile decision-making that adds long-term value every step of the way. Legal Insights. Human Intelligence. Business Impact
On 24 November 2021, the Office of Government Procurement ("OGP") issued general guidance for Contracting Authorities whose public works tenders were impacted by the marked price inflation...
Ireland Real Estate and Construction

On 24 November 2021, the Office of Government Procurement (“OGP”) issued general guidance for Contracting Authorities whose public works tenders were impacted by the marked price inflation in the construction industry and stated that broader amendments to the price variation provisions in the public works contracts would be introduced by it in Q1 2022. For further information on this general guidance please see our Insight published on 1 December 2021 here. These interim amendments were released by the OGP on 7 January 2022 which saw the introduction of the following new provisions into the public works contracts:

  1. an indexed price adjustment mechanism to address the risk of inflation to materials prior to the award of a contract for PW-CF1 – PW-CF6 (inclusive). Two formulas have been developed and introduced to the Instruction to Tenderers documents to determine what increases may apply by relative movements in the CSO Wholesale Price Index (the “Index”) relating to building and construction materials;
  2. in forms PW-CF1 – PW-CF5 inclusive, the Base Date for PV1 and PV2 has been reduced from 30 months to 24 months from the Tender Inflation Indexation Date (being the last day of the month in which the latest available Index is published as at the Contract Date); and
  3. in forms PW-CF1 – PW-CF5 inclusive, the sub-clauses in PV1 and PV2 dealing with exceptional material price increases have been amended to adjust the threshold from 50% to 15%.

For Contracting Authorities currently conducting a live tender process, the amendments are to be used in tenders due to be received from 18 January 2022 onwards.

Co author by Teniola Ayeni

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More