ARTICLE
23 June 2025

GERC Grants First-of-its-Kind Extension For Power Evacuation Infrastructure

DL
Dentons Link Legal

Contributor

Established in 1999, Dentons Link Legal is a full service corporate and commercial law firm with over 50 partners and 250 lawyers across multiple practice areas. With offices across all major Indian cities and access to more than 160 offices in more than 80 countries of Dentons’ combination firms across the world, Dentons Link Legal is equipped to assist you in achieving your business objectives with the help of a team of experienced, well trained and qualified lawyers.
GERC, in one of the first of its kind matter, extended completion date of the power evacuation infrastructure recognising occurrence of the unforeseen events...
India Energy and Natural Resources

GERC, in one of the first of its kind matter, extended completion date of the power evacuation infrastructure recognising occurrence of the unforeseen events

In one of the first of its kind matter before Gujarat Electricity Regulatory Commission ("GERC"), it allowed extension of 465 days to a renewable energy developer for construction of evacuation infrastructure.

Cleanmax Vayu Urja Private Limited, a renewable energy developer ("Cleanmax") is setting up a 100MW renewable energy power plant at Devpur Ranuja, Gujarat ("Power Plant") got its right to get connected with the transmission asset of GETCO. As per the applicable laws, Cleanmax was required to complete the evacuation infrastructure within the timeline specified by the Commission, failing which its right to get connected with GETCO's transmission asset would be revoked. Connectivity is a major element of any power project and without connectivity, any power developer will not be able to supply its power to any off-taker.

However, Cleanmax, despite its best efforts and leaving no stone unturned, was in a genuine difficulty to complete the said evacuation infrastructure within the given timeline. Immense delay had occurred due to unforeseen reasons which included the following:

  1. Delay in clarity in status of lead generator
  2. Delay associated with vendor approval for GIS
  3. Delay connected with common drawing approval

Cleanmax appointed Dentons Link Legal ("DLL") to assist, advise and represent before GERC. DLL recognised importance of interim protection of the connectivity. Aditya K Singh, Partner, DLL (assisted by Anukriti Jain, Principal Associate) appeared before GERC and pressed for interim stay till the disposal of the petition. GERC after hearing issues at length, prima facie agreed with the merit of the matter and provided order of status quo on 11.02.2025.

Further, GERC issued final order on 17.06.2025 recognising difficulties being faced by Cleanmax recognising DLL's submission that Cleanmax's ability to complete the requisite evacuation infrastructure was impacted by occurrence of unforeseen events.

Various power developers are facing similar challenges in completing their evacuation infrastructure. GERC has shown path to other similarly situated developers that in cases of genuine difficulties, sectoral regulator will provide appropriate remedy.

Cleanmax was represented before GERC by Sr. Adv. Mr. Mihir Thakore and Mr. Aditya K. Singh (Partner, DLL) assisted by Ms. Anukriti Jain (Principal Associate, DLL).

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More