ARTICLE
28 January 2026

Supreme Court Upholds APTEL Judgment On Interim Relief Under Section 11 Of The Electricity Act

SKV Law Offices

Contributor

SKV Law Offices, a New Delhi-based full-service law firm, is recognized for its solution-oriented approach and consistency in delivering high-quality outcomes. With a focus on entrepreneurship and client-centric service, SKV provides comprehensive legal advisory and representation across diverse sectors, including shareholder disputes, service law, environmental issues, tax advisory, competition law, consumer issues, corporate insolvency, restructuring, and regulatory matters.

The firm’s expertise extends to advising corporations, infrastructure and power companies, associations, high-net-worth individuals, and regulatory stakeholders, particularly in the energy sector. SKV’s commitment to understanding client needs and leveraging deep sectoral insights ensures tailored, effective solutions that align with the prevailing commercial climate. This focus on exceptional service and value has driven the firm’s reputation and growth.

The Supreme Court of India has dismissed the Civil Appeals filed by Gujarat Urja Vikas Nigam Limited (GUVNL) and Punjab State Power Corporation Limited...
India Energy and Natural Resources
Shri Venkatesh’s articles from SKV Law Offices are most popular:
  • within Energy and Natural Resources topic(s)
  • with readers working within the Retail & Leisure industries
SKV Law Offices are most popular:
  • within Government, Public Sector, Environment and Corporate/Commercial Law topic(s)

The Supreme Court of India has dismissed the Civil Appeals filed by Gujarat Urja Vikas Nigam Limited (GUVNL) and Punjab State Power Corporation Limited (PSPCL), thereby refusing to interfere with the Judgment dated 31.10.2025 passed by the Appellate Tribunal for Electricity (APTEL). Tata Power Company Limited (TPCL), represented by SKV Law Offices, successfully defended the interim relief granted by CERC.

By dismissing the Appeals, the Supreme Court has affirmed the APTEL Judgment upholding the interim relief granted by the Central Electricity Regulatory Commission (CERC) in proceedings arising from the Section 11 directions issued during the coal shortage period, subject to safeguards and final adjudication.

Background

The dispute arose from directions issued under Section 11(1) of the Electricity Act, 2003, whereby generating stations, including Tata Power Company Limited's Mundra Ultra Mega Power Project (formerly Coastal Gujarat Power Limited), were mandated in public interest to generate and supply electricity using imported coal due to acute domestic coal shortages and high demand.

The Energy Charge Rate (ECR) notified under the Section 11 directions was substantially lower than the actual cost of generation using imported coal, resulting in sustained adverse financial impact on generators operating under statutory compulsion. Consequently, the generator approached CERC under Section 11(2) seeking adjudication of the adverse financial impact, along with interim financial relief pending final determination.

Orders of CERC and APTEL

By its Interim Order dated 10.03.2025, CERC exercised its powers under Section 94(2) of the Electricity Act and permitted limited interim recovery, allowing 50% of the differential energy charge between benchmark rates, strictly as a provisional measure and subject to final adjustment upon adjudication of the Section 11(2) petition.

The interim order was challenged by multiple procurers, including GUVNL and PSPCL, before APTEL. By its Judgment dated 31.10.2025, APTEL:

  • Declined to set aside the interim relief granted by CERC;
  • Directed a limited remand to CERC solely for arithmetical re-computation, without reopening the merits;
  • Recorded that even on the procurers' own computations, the interim benchmark adopted by CERC was conservative and non-prejudicial;
  • Directed the generator to furnish unconditional bank guarantees for the entire recomputed amount and to provide an undertaking to pay carrying cost in the event of an adverse final determination; and
  • Requested CERC to finally decide the Section 11(2) petition within a specified timeframe.

Supreme Court's Decision

The Supreme Court, after hearing the parties, dismissed the Civil Appeals and declined to interfere with the APTEL Judgment. In doing so, the Court allowed the following to stand:

  • The competence of CERC to grant interim relief under Section 94(2) in proceedings under Section 11(2);
  • The balanced interim arrangement crafted by APTEL, which protected procurers through bank guarantees, restitution safeguards, and carrying cost; and
  • The provisional and adjustable nature of the interim relief, pending final adjudication by the regulatory commission.

As a result, the interim recovery mechanism, together with the safeguards directed by APTEL, continues to operate pending final determination by CERC.

Significance

The decision reinforces key principles of regulatory jurisprudence under the Electricity Act, 2003, including that:

  • Statutory directions under Section 11(1) do not oust or dilute the adjudicatory powers of regulatory commissions under Section 11(2);
  • Regulatory commissions retain full authority to grant interim financial protection under Section 94(2) where generators are compelled to operate in public interest at regulated rates; and
  • Appellate courts will ordinarily not interfere with well-balanced interim regulatory orders, particularly where complete restitution and consumer protection mechanisms are in place.

The ruling secured by SKV Law Offices is significant for the evolving jurisprudence on emergency powers, fuel cost recovery, and interim regulatory reliefs in the power sector.

Click here to read the order.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

[View Source]

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More