More than 800 attorneys strong, Wilson Elser serves clients of all sizes across multiple industries. It maintains 38 domestic offices, another in London and enjoys more extensive international reach as a founding member of Legalign Global.  The firm is currently ranked 56th in the National Law Journal’s NLJ 500.
Christopher A. Priore (Partner-Albany) and Olivia Orlando (Associate-Albany) represented a subcontractor who supplied and placed aggregate materials and liquid asphalt for the construction...
United States Real Estate and Construction
To print this article, all you need is to be registered or login on Mondaq.com.

Christopher A. Priore (Partner-Albany) and Olivia Orlando (Associate-Albany) represented a subcontractor who supplied and placed aggregate materials and liquid asphalt for the construction of a federally funded municipal runway. The subcontract contained an "escalation clause" permitting the subcontractor to make payment requisitions for materials based upon a market index price at the time of placement, not the time of project bidding. Since the index price had drastically increased between the time of bidding and the time of placement, the client included the escalation costs in its applications for payment. The contractor refused to approve payment requisitions notwithstanding the fact that the Project Engineers certified the client's work and the contractor was paid the base contract price in full.

Chris and Olivia filed a Complaint against the contractor and the contractors' Surety seeking damages for breach of contract and breach of the Surety's payment bond, and asserting a cause of action under NY State Finance Law section 137. The contractor contended there was a clause prohibiting contract terms for material escalations that "flowed down" to the sub-contract and therefore precluded the client's claim for escalation of the asphalt materials. The Court rejected defendants' arguments and agreed with our argument that interest accrued as of the date of the breach of the subcontract and failure to pay a properly made bond claim. Accordingly, the court applied the statutory mandated rate of interest of 12% per annum, and the interest equated to more than $200,000 of the overall award. Ultimately the Court granted Chris and Olivia's Motion for Summary Judgment in full and rejected all of the defendant's defenses and justifications for nonpayment.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

ARTICLE
8 November 2022

Priore And Orlando Obtain Summary Judgment On Breach Of Contract Dispute And Secure $800,000 In Damages

United States Real Estate and Construction

Contributor

More than 800 attorneys strong, Wilson Elser serves clients of all sizes across multiple industries. It maintains 38 domestic offices, another in London and enjoys more extensive international reach as a founding member of Legalign Global.  The firm is currently ranked 56th in the National Law Journal’s NLJ 500.
See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More