Damage Control: Supreme Court Clarity On Liquidated Damages

WB
Wedlake Bell

Contributor

We are a contemporary London law firm, rooted in tradition with a lasting legacy of client service. Founded in 1780, we recognise the long-standing relationships we have with our clients and how they have helped shape our past and provide a platform for our future. With 76 partners supported by over 300 lawyers and support staff, we operate on a four practice group model: private client, business services, real estate and dispute resolution. Our driving force is to empower our clients by providing quality legal advice, insight and intelligence that enables them to achieve their goals whether personal or business. We are large enough to advise on the most complex matters, but small enough to ensure that our people and our work remain exceptional and dynamic. Building relationships is at the heart of everything we do.
In 2019 the construction industry was thrown into a state of confusion (before COVID or BREXIT had a chance to try) by a Court of Appeal ("COA'")...
United Kingdom Real Estate and Construction

In 2019 the construction industry was thrown into a state of confusion (before COVID or BREXIT had a chance to try) by a Court of Appeal ("COA'") decision turning on its head the long held "orthodox" view that liquidated damages ("LDs") for incomplete works would only accrue until contract termination, not to completion of the works.

On appeal of this decision in Triple Point Technology Inc (Triple Point) v PTT Public Company Ltd (PTT) [2021] UKSC 29  the UK Supreme Court ("UKSC"), in its eagerly awaited judgment, has provided some much needed clarity to the industry on the applicability of LDs until termination. The UKSC unanimously held that LDs would indeed only apply up to termination of a contract, irrespective of whether the works were completed by the Contractor or accepted by the Employer. The UKSC held that to accept otherwise was "inconsistent with commercial reality and the accepted function of liquidated damages".

This decision provides certainty in this respect for Employers and Contractors moving forward (and not to mention a sigh of relief for Employers under current contracts which under the COA ruling may have had LD regimes of questionable enforceability in the event of termination).  Despite this newfound clarity it will be interesting to see if parties or industry groups, out of an abundance of caution, also seek to address this in drafting as we have seen the NEC4 suite, to include amendments making it clear that delay damages will cease at termination. 