Appeal Panel decision delivered on Biowood
On 15 November 2019, the NSW Civil and Administrative Tribunal (Tribunal) determined that a treated wooden cladding product called "Biowood" was combustible, not sufficiently fire retardant and was in breach of the requirements of the Building Code of Australia (BCA) and awarded an owners corporation the cost of removing and replacing it from the façade of a residential apartment building.1
The decision was significant as it was the first decision of any court or tribunal in Australia after the Melbourne Lacrosse fire, where damages were awarded for the cost of replacing combustible cladding, other than for aluminium composite cladding (ACP), which is the subject of bans in NSW and other states.
The defendant builder and developer both appealed the decision. The Appeal Panel of the Tribunal has now delivered its determination on the appeal, which upholds the original decision.2
Being an appeal, the Appeal Panel did not hear new evidence but was required to determine whether the Tribunal below had sufficient grounds for making its original decision and whether there had been any errors in making that decision.
The Appeal Panel determined that there was a reasonable basis for and no error in the original decision and that the owners corporation had sufficiently demonstrated the combustibility and risk of fire spread created by the product through its expert evidence, to establish that the product was not BCA compliant, imposed an undue risk on the occupants and users of the building, was accordingly not fit for purpose and amounted to a breach of the statutory warranties in section 18B of the Home Building Act 1989 (NSW) (Act).
Some likely consequences of the decision are below:
- the owners of other residential buildings with Biowood on their facades are likely to be lining up to seek expert opinion on whether the installation of the product on their buildings also comprises a risk of fire spread in breach of the BCA, with a view to bringing proceedings against those responsible for its design and installation
- now that the Design and Building Practitioners Act 2020 (NSW) (DBPA) has commenced, the class of buildings the owners of which are likely to claim may be broader, having regard to the retroactive statutory duty of care to avoid economic loss as a result of defects, applying alongside the statutory warranties under the Act. The defendants in such claims may also extend to include the design team now that the existence of a duty of care has been established by statute
- the Biowood product and similar products may well be the subject of review by the NSW Government's recently formed Cladding Product Safety Panel to determine whether it and other products, such as steel composite cladding and foam based cladding products, should be the subject of a product safety ban, alongside ACP.
Footnotes
1 https://www.caselaw.nsw.gov.au/decision/5df0887ce4b0ab0bf60748b1
2 https://www.caselaw.nsw.gov.au/decision/173a260197982c9039cce483
In the media
Australia's build-to-rent is coming of age and
it's green
Australia's emerging build-to-rent sector is starting
to look like an attractive asset class and stimulus option,
especially now. With Covid the sector benefits by being closer to
"shovel ready" than traditional build to sell models (20
August 2020).
More...
Master Plumbers group urges caution with national
licencing
Master Plumbers Australia and New Zealand
(MPANZ), the collective voice for the Australian
and New Zealand plumbing industry, is warning that a national
occupational licensing scheme announced by Treasurer the Hon. Josh
Frydenberg comes with potential risks for community safety and
consumer protection (18 August 2020).
More...
Researchers develop spray-on clear coatings for cheaper
smart windows
A simple method for making clear coatings that can block
heat and conduct electricity could slash the cost of energy-saving
smart windows and heat-repelling glass. Developed by researchers at
RMIT University, the spray-on coatings are ultra-thin,
cost-effective and rival the performance of current industry
standards for transparent electrodes (14 August 2020).
More...
Gosford scaffolding collapse prompts calls for workplace
safety reform
NSW passed amendments to the Work Health and Safety Act
last month, but WorkSafe says almost half of all scaffolds have
"missing parts" (21 August 2020).
More...
Why NSW's BASIX tool needs some love
While BASIX, the NSW-specific planning controls that
override National Construction Code requirements on emissions and
other sustainability criteria, started life as a market-leading
tool, some say it's now losing its edge and stymying progress
towards next generation technologies such as heat pumps (20 August
2020).
More...
Expert panel to accelerate removal of high-risk
cladding
The NSW Government has established an expert panel of
building and construction specialists to help support the removal
of unsafe cladding across the state (10 August 2020). More...
HIA: Update on COVID-19: ACT & NSW
In the wake of the Victorian lock-down the NSW Premier has
this week reinforced the importance of all businesses embracing and
adhering to the COVID-19 safety measures. Businesses found to be in
breach of the public health orders could face a penalty of up to
$55,000 or an on the spot fine of $5,000 (10 August 2020).
More...
Practice and courts
Standards Australia: Drafts open for public
comment
Standards Australia are seeking your feedback on a range
of standards concerning the plumbing and drainage trade. On this
page you will find a complete list of drafts currently open
for public comment from August to October 2020. For more
information, please consult the Standards Australia
Public Commenting Guide(17 August 2020).
More...
AS/NZS 5131:2016 Amd 1:2020
Structural steelwork - Fabrication and erection Standards
Australia.
More...
Build Australia discussion paper: Draft National
Registration Framework for Building Practitioners
A discussion paper on a draft National Registration
Framework (NRF) for Building Practitioners has
been developed in response to BCR recommendations 1 and 2. The
discussion paper seeks stakeholder feedback on the draft NRF
outlined in the consultation form, until 23 August 2020. Only
comments submitted using the online form will be
considered.
More...
ABCB: Consultation on minimum accessibility standards
for housing closes 31 August
This is your opportunity to provide feedback (17 August
2020).
More...
ABCB: Proposal to include minimum accessibility
standards for housing in the NCC
Consultation RIS open for public consultation, closing 31
August 2020. It examines regulatory options that are based on
the
Livable Housing Design Guidelines
(LHDG) Silver-level and Gold-level
specifications, as well as a 'Gold-plus' specification
developed through stakeholder consultation. The ABCB has also
released a
project overview and RIS explainer document that explain
the project, its timelines and the RIS process.
More...
GBCA: draft Green Star Homes Standard for
consultation
Part of the Green Building Council of
Australia's
Future Homes Strategy, the Standard is a key tool to help drive
transformation in the residential sector to create a market for
healthier, more resilient, energy efficient homes. Consultation on
the draft standard will run until 30 October 2020.
More...
2020 National Housing Research Program commences
Research is underway for the suite of projects funded by
AHURI as part of the 2020 National Housing Research Program
(NHRP). The research will be undertaken by
collaborative teams from AHURI's eight national university
research partners. For more details of the 2020 NHRP
projects
please click here.
More...
NSW Revenue: HomeBuilder program
HomeBuilder will provide eligible owner-occupiers
(including first home buyers) with a grant of $25,000 to build a
new home or substantially renovate an existing home where the
contract is signed between 4 June 2020 and 31 December 2020.
Construction must commence within three months of the contract
date.
More...
Cases
CaseNote: High court clarifies personal leave accrual
On 13 August the High Court
handed down a decision that clarified the accrual of
personal leave. The decision and what it means: The Court declared
that the expression '10 days' in the Fair Work
Act in regards to personal leave accrual refers to 10
'notional days' rather than 10 'working days'. The
full decision of the High Court is available at
In the matter
of Vista Del Mare Pty Ltd [2020] NSWSC
938
CORPORATIONS — Winding up — Statutory demand
— Whether statutory demand should be set aside by reason of
offsetting claim — Where Plaintiff makes offsetting claim for
defective construction works — Where expert evidence provides
opinion on rectification cost.
Decision
restricted [2020] NSWCATAP 163
BUILDING AND CONSTRUCTION — Home Building Act 1989
(NSW) — Statutory warranty — In accordance with the law
- Building Code of Australia – Whether issue of interim
occupation certificate creates an irrebuttable presumption that the
building is BCA compliant – Whether attachment of
"Biowood" to the exterior walls constituted an
"undue risk of fire spread via the façade of the
building" – Words and phrases – "undue
risk"
Price v Commissioner for Fair
Trading [2020] NSWCATOD
93
ADMINISTRATIVE LAW – administrative review –
licensing – whether Applicant meets requirements for Issue of
builders licence - application of Instrument as policy –
experience requirements not met – not unfair or unjust to
apply policy - Administrative Decisions Review Act 1997; Civil and
Administrative Tribunal Act 2013; Evidence Act 1995; Home Building
Act 1989
Florida Kitchens Pty Ltd v Number One Cutting Service
Pty Ltd trading as Number One Marble and
Granite [2020]
Summons seeking leave to appeal dismissed, with costs.
APPEALS – leave – dismissal of appeal from order for
provision of security for costs – orders made against sole
director and shareholder – no question of principle –
leave refused - Civil and Administrative Tribunal Act 2013 (NSW), s
83; Civil Procedure Act 2005 (NSW), s 56; Home Building Act 1989
(NSW); Uniform Civil Procedure Rules 2005 (NSW), rr 49.4, 51.12,
51.18, 59.11
F.E. V Mono Constructions Pty Ltd v
Beattie [2020] NSWSC 1093
CIVIL PROCEDURE – stay of proceedings –
pending appeal – where there is no practical benefit of
imposing a stay CIVIL PROCEDURE – summary disposal –
dismissal of proceedings – where action may be
maintainable
The remaining plaintiff corporation, which is unrepresented, is
suing the law practice defendants for professional negligence in
the performance of legal work and the provision of legal advice in
a home building dispute brought against the plaintiff by former
customers, originally in the Consumer Trader and Tenancy Tribunal,
and continued in the Civil and Administrative Tribunal
(NCAT)
Calderwood v Department of Planning, Industry and
Environment; Calderwood
v Campbelltown City
Council; Department
of Planning, Industry & Environment v City of
Ryde [2020] NSWCATAD
200
GOVERNMENT INFORMATION- Combustible [Flammable] Cladding
Register- disclosure of addresses of buildings on Register- agency
can rely on additional factors in Table negative to disclosure
other than those referred to in access decision-denial of access
affirmed
Michael Kuehn & Jennifer Kuehn v Masterton Homes (NSW) Pty Ltd
t/as Masterton Homes (NSW) Pty Ltd
[2020] NSWSC 1049
CONTRACT – Whether parties compromised or
settled proceedings between them – One of the plaintiffs sued
the first defendant house builder in the NSW Civil &
Administrative Tribunal (NCAT) for damages,
alleging defective construction of their house – The first
defendant alleged that on 29 July 2019 when the proceedings were
before NCAT, a binding compromise or settlement of the claims of
both plaintiffs was entered into
HELD – No binding compromise or settlement was entered into
because the other plaintiff was not a party to any arrangement and,
in any event, the objective intention of the parties was that there
would be no binding arrangement until the terms of it were embodied
in a formal deed signed by all of them.
One Pro Baulkham Hills Pty Ltd v Ming Tian Real
Property Pty Ltd [2020] NSWSC
1043
CONTRACTS – building contract – construction
– conditions precedent – whether conditions precedent
were to formation of contract or parties' performance of their
obligations under the contract – whether defendant contractor
obliged to commence work under contract – whether failure by
defendant to provide bank guarantees and evidence of home warranty
insurance caused plaintiff to suffer damage
CONTRACTS – ambit of exclusion clause – whether
exclusion clause survived consensual termination of contract
CONTRACTS – remedies – damages – whether
plaintiff principal proved it had suffered damage by reason of
defendant's conduct
CONSUMER LAW – misleading or deceptive conduct – where
director of defendant represented guarantee was genuine –
where bank guarantee was not genuine – where plaintiff
general manager saw at once that bank guarantee was not genuine
– whether plaintiff has suffered any loss by director's
conduct
Loneragan v
The Owners - Strata Plan No 16519 [2020]
NSWCATAP 177
APPEAL — NCAT — questions of law —
leave to appeal from decision of Consumer and Commercial Division
of NCAT
LAND LAW — strata title — common property —
maintenance and repair of common property - relationship between ss
106 and 108 of the Strata Schemes Management Act 2015
EVIDENCE — expert evidence — whether Tribunal
permitted to consider whether witness was an expert in proceedings
in which NCAT Procedural Direction 3, Expert Evidence did not
apply
Crea v Bedrock
Construction and Development Pty Ltd; Bedrock Construction and
Development Pty Ltd v Crea & Anor [2020] sadc
124
CONTRACTS - Building, Engineering and related contracts -
performance of work
CONTRACTS - Building, engineering and related contracts - the
contract - construction of particular contracts and implied
conditions - variations
Legislation
Regulations and other miscellaneous instruments
Residential Apartment Buildings (Compliance and Enforcement Powers)
Regulation 2020
(2020-475) — published LW 14 August 2020
Road Transport Amendment (Miscellaneous) Regulation
2020
(2020-476) — published LW 14 August 2020
Western City and Aerotropolis Authority Amendment (Operational
Area) Regulation 2020
(2020-479) — published LW 14 August 2020
Administrative Arrangements (Administration of Acts—Amendment
No 5) Order 2020
(2020-389) — published LW 3 July 2020
Home Building Amendment (Fees) Regulation 2020
(2020-314) — published LW 26 June 2020
Building and Development Certifiers Amendment (Provision of
Information) Regulation 2020
(2020-300) — published LW 26 June 2020
Home Building Amendment (Miscellaneous) Regulation 2020
(2020-179)
published LW 1 May 2020
Environmental Planning Instruments
State Environmental Planning Policy Amendment (Western Gateway
Sub-precinct) 2020
(2020-480) — published LW 13 August 2020
Bills assented to
State Revenue Legislation Amendment (COVID-19 Housing Response) Act 2020 No 19 — Assented to 11 August 2020
For the full text of Bills, and details on the passage of Bills, see Bills.
This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.