ARTICLE
15 November 2024

Dispute Resolution & ADR Newsletter - November 2024

Fox & Mandal

Contributor

Our focus on responsive and collaborative engagement with our clients is motivated by a desire to seek alignment of values, purpose and ambition. Our extensive clientele extends across varied industry sectors, Fortune 500 companies, domestic conglomerates, startups, PSUs, MNCs, and non-profits. We have grown and expanded to keep pace with our clients and have a team of 20 partners and over 120 professionals across our offices in Kolkata, Mumbai and New Delhi. Even as our footprint continues to grow in India, F&M’s team supports our clients’ global operations and cross-jurisdictional requirements through a network of international law firms and advisors.
Welcome to the latest edition of the Fox & Mandal Dispute Resolution & ADR Newsletter. In this edition, we examine the impact of various judgments rendered by the Supreme Court of India, High Courts and tribunals on the dispute resolution and ADR ecosystem in the country.
India Delhi Litigation, Mediation & Arbitration

Dispute Resolution & ADR Newsletter - November 2024 (pdf)

Consent of a non-signatory not required for appointment of arbitral tribunal

Yves Saint Laurent v. Brompton Lifestyle Brands Pvt Ltd & Anr

Delhi High Court | September 18, 2024 OMP (T) (Comm) No. 29 of 2023

The Delhi High Court recently held that a non-signatory's consent is not required for the appointment of an arbitral tribunal. In coming to this conclusion, the Court's reasoning – that a 'party' under Section 2(1)(h) of the Arbitration and Conciliation Act, 1996 (Act) does not include a non-signatory – seems to be inconsistent with the Supreme Court's decision in Cox and Kings Ltd v. SAP India Pvt Ltd1 where it was held that 'parties' includes both signatories and nonsignatories, while leaving it to the arbitral tribunal to decide on the impleadment of the nonsignatory as a veritable party to the arbitration. In light of this, a claimant initiating arbitration cannot assume that such a non-signatory would indeed be made party to the arbitration and therefore, is not mandated under law to seek its participation in the appointment procedure prior to such determination by arbitral tribunal. However, in our view, it is in the interest of natural justice that a non-signatory that is made a 'party' is not bound by orders passed by an arbitral tribunal, the appointment of which it did not consent to (this issue was not addressed by the Supreme Court in Cox & Kings).

SUMMARY OF FACTS

Yves Saint Laurent (YSL), a leading fashion design house, entered into a Franchise Agreement (FA) with Beverly Luxury Brands Ltd (Beverly) in 2019. Subsequently, Beverly entered into a Sub-Franchise Agreement (SFA) with Brompton Lifestyle Brands Pvt Ltd (Brompton), without the consent or knowledge of YSL. While the FA did not contain any arbitration clause, the SFA provided for arbitration by a sole arbitrator.

YSL terminated the FA in 2021, and subsequently Beverly terminated the SFA. Brompton sent a notice to Beverly and YSL invoking arbitration under the SFA, and by mutual consent of Beverly and Brompton (without knowledge of YSL), an arbitrator was appointed.

YSL challenged the jurisdiction of the arbitrator under Section 16 of the Act (that empowers the arbitrator to adjudicate challenges to its jurisdiction), contending that the arbitrator was coram non judice vis-à-vis YSL since YSL, being a non-signatory, had neither consented to arbitration nor to the appointment of the arbitrator. The arbitrator dismissed YSL's Section 16 challenge.

Thereafter, YSL sought termination of the mandate of the arbitrator under Section 14 of the Act before the Delhi High Court, but without any alternate prayer for deletion of its name or substitution of the arbitrator (Section 14 Petition).

DECISION OF THE COURT

The key issues before the Court were whether the Section 14 Petition filed by YSL was maintainable and if so, whether the unilateral appointment of the arbitrator rendered him de jure incapable of performing his functions.

On the issue of maintainability, the Court observed that the right to seek termination of the arbitrator's mandate under Section 14 remains absolute, independent and una[ected by the outcome of a separate jurisdictional challenge under any other provision of the Act. Thus, the Section 14 Petition was maintainable despite dismissal of the Section 16 challenge by the arbitrator.

In respect of the arbitrator's appointment, the Court observed that the requirement for consensus in appointing an arbitrator envisaged under Section 21 of the Act, applies only to the 'parties' to the arbitration agreement as defined in Section 2(1)(h), and not to 'non-signatories'. The Court relied on an excerpt from the decision in Chloro Controls India Pvt Ltd v. Severn Trent Water Purification Inc2 wherein the Supreme Court stated that 'a non-signatory or third party could be subjected to arbitration without their prior consent, but this would only be in exceptional cases' As such, the Court held the arbitrator's appointment does not become unilateral simply because the consent of YSL, a non-signatory to the SFA, was not obtained.

The Court also observed that if YSL was improperly made a party to the arbitration, the appropriate remedy of its deletion from proceedings was never prayed for.

Buyback claim of shares constitutes 'financial debt' under the IBC framework

Spectrum Trimpex Pvt Ltd v. VPhrase Analytics Solutions Pvt Ltd

National Company Law Tribunal (NCLT), Mumbai Bench | October 4, 2024 Company Petition (Insolvency) No. 249 of 2024 (Mumbai)

The NCLT recently held that claims arising out of buyback clauses under Share Purchase Agreements constitute 'financial debt' under the insolvency framework if they imply an obligation that mirrors the commercial eTect of borrowing. The judgment helps clarify the scope of 'financial debt' under the Insolvency and Bankruptcy Code, 2016 (IBC) and underlines the importance of compliance with mutually agreed terms, particularly in valuation, to fulfil the IBC's financial thresholds. Even though NCLT has limited scope of adjudication before admitting a corporate debtor into insolvency, diligent scrutiny of shareholder claims will help prevent misuse of IBC provisions.

SUMMARY OF FACTS

Spectrum Trimpex Pvt Ltd (Spectrum) invested in VPhrase Analytics Solutions Pvt Ltd (VPhrase) under a Share Subscription and Shareholders Agreement (SSA). The SSA involved the allotment of 378 equity shares to Spectrum, with a clause for mandatory buyback to provide an exit at fair market value after 5 years. Spectrum invoked this buyback clause in January, 2023 calling upon VPhrase to pay INR 93,79,692 at the rate of INR 24,814 per equity share based on its audited financial statements. However, VPhrase did not respond.

A valuation report was then obtained unilaterally by Spectrum, setting a share price of INR 34,600 per equity share, resulting in a claim amount of more than INR 1 crore (unpaid buyback amount).

Consequently, Spectrum filed a petition under Section 7 of the IBC before the NCLT, Mumbai seeking initiation of Corporate Insolvency Resolution Process against VPhrase, claiming that the unpaid buyback amount constituted a 'financial debt' due to non-compliance by VPhrase.

DECISION OF THE TRIBUNAL

While deciding on whether the buyback claim of shares by Spectrum constituted 'financial debt', the NCLT referred to the decision in Kotak Mahindra Bank Ltd v. A Balakrishnan & Anr3 wherein the Supreme Court held that raising of an amount by a company through a Shareholders Agreement had the commercial e[ect of borrowing since the said transaction has direct e[ect with the business and the Company and the promoters were obliged to purchase all the shares held by non-defaulting shareholders at a price that provides an internal rate of return of 15% p.a. compounded annually or at the fair market value, whichever is higher.

Additionally, the NCLT also referred to the judgment in Sanjay D Kakade v. HDFC Ventures Trustee Co Ltd4 wherein the National Company Law Appellate Tribunal (NCLAT) held that investments made in the corporate debtor by means of Share Subscription and Shareholders Agreements involving a preemption right in favour of the financial creditor and/or a put option in the Shareholders Agreement obligating the promoters to buy-back shares at a fair market value, such a transaction would be treated as a 'financial debt' as the transaction has the commercial effect of borrowing.

The NCLT, thus, held that the unpaid buyback amount had the commercial e[ect of borrowing and constituted financial debt; however, Spectrum's unilateral appointment of a valuer contrary to the SSA's requirement and the consequent unilateral valuation will not bind VPhrase.

Noting that the amount claimed initially was INR 93,79,692 which fell below the IBC's threshold of INR 1 crore, the NCLT rejected Spectrum's attempt to inflate the valuation as non-compliant with the SSA, thereby dismissing the petition.

Mandate of pre-institution mediation under Section 12A of the Commercial Courts Act, 2015 applies to counterclaims

Aditya Birla Fashion & Retail Ltd v. Saroj Tandon

Delhi High Court | September 2, 2024 2024 SCC OnLine Del 6099

The Delhi High Court held that pre-institution mediation is mandatory for the filing of a counterclaim involving a commercial dispute not contemplating any urgent relief. While the judgment aligns with the strict interpretation of the statutory provisions of the Commercial Courts Act, 2015 (Act) and Code of Civil Procedure, 1908 (CPC) mandating pre-institution mediation as a means to reduce the workload of the Courts, it must be analysed whether the mandate indeed yields any objective results. While the judgement rightly upholds the ethos of a legal mandate that cannot be given a go bye, however, if a party is clearly disinclined to settle, the chances of any positive outcome of such a mandate are very low, particularly considering that parties generally attempt to settle their disputes prior to approaching the Court in the first place. Therefore, it remains to be seen whether such a mandatory provision actually serves its purpose of eTiciently resolving disputes and reducing burden on Courts or whether it merely postpones the litigation.

SUMMARY OF FACTS

Saroj Tandon (Saroj) had leased a shop to Aditya Birla Fashion & Retail Ltd (ABFRL). During Covid-19, ABFRL ceased its business operations and sought termination of the lease and refund of security deposit. However, Saroj failed to return the security deposit constraining ABFRL to file a commercial suit seeking recovery of money along with an application under Section 12A of the Act for mandatory pre-institution mediation.

As Saroj failed to appear for mediation, it was declared as non-starter and the commercial suit was filed and registered. Along with her written statement to the suit, Saroj filed a counterclaim seeking rentals without any urgent relief. The counterclaim involved a commercial dispute and was, therefore, also registered as a commercial suit.

ABFRL filed an application under Order VII Rule 11 of the CPC seeking rejection of the counterclaim on the ground that Saroj had failed to invoke mandatory pre-institution mediation. The said application was dismissed by the Commercial Court.

Against such dismissal, ABFRL filed the present petition under Article 227 of the Constitution of India.

DECISION OF THE COURT

In order to determine whether invoking pre-institution mediation under Section 12A of the Act is mandatory for filing a counterclaim in commercial disputes when no urgent relief is sought, the Delhi High Court analysed Order VIII Rule 6A and Order IV Rules 1 & 2 of CPC and held that a 5 2022 SCC OnLine SC 1028 counterclaim is of the nature of a distinct suit and must be treated procedurally as such. Counterclaims in commercial disputes are subject to the same legal obligations as commercial suits.

Having regard to Rule 3 of the Commercial Courts (PreInstitution Mediation and Settlement) Rules, 2018 (2018 Rules) which requires initiation of mandatory mediation process against the 'opposite party' as well as Rule 2(g) of the 2018 Rules which defines 'opposite party' as 'a party against whom relief is sought in a commercial dispute', the Court clarified that the Legislature never intended to exempt any party from the mandate of pre-institution mediation, upholding the indefeasible right of such 'opposite party' to participate in mediation.

The Court also referred to the Supreme Court's decision in Patil Automation Pvt Ltd v. Rakheja Engineers Pvt Ltd5 holding that non-compliance of pre-institution mediation would entail rejection of the plaint.

While rejecting Saroj's argument that an unsuccessful mediation prior to the filing of the original suit, in all probability, renders a pre-counterclaim mediation to be a futile exercise, the Court noted that the subject matter and nature of relief in a counterclaim may be dissimilar, and the approach of the original plainti[ cannot be anticipated in a mechanical manner. It was held that a mandatory prerequisite cannot be given a go-bye on whims and fancies even if the conduct of the counterclaimant is reflective of disinclination towards any settlement.

Equal treatment of government enterprises and private parties for grant of stay on the execution of an arbitral award

International Seaport Dredging Pvt Ltd v. Kamarajar Port Ltd

SupremeCourt of India | October 24,2024 2024 SCC OnLine SC 3112

The Supreme Court clarified that while determining the conditions for grant of stay of an arbitral award, no special treatment can be accorded to government enterprises and statutory undertakings over private respondents. Thus, factors such as nature (government or private), size, success and public image of the undertaking cannot be applied while deciding the conditions for grant of interim stay of an award. The decision reinforces the principle of equality and fairness in arbitration and will help ensure that government enterprises are held to the same standards of accountability and financial responsibility, thus promoting a more equitable environment for all parties in commercial disputes.

SUMMARY OF FACTS

Kamarajar Port Ltd (KPL) entered into a contract with International Seaport Dredging Pvt Ltd (ISDPL) for capital dredging. Disputes arose between the parties constraining ISDPL to invoke arbitration on several claims.

The arbitral tribunal passed an award (Award) directing KPL to pay INR 21.07 crore (Principal Sum) along with interest and INR 3.2 crore as costs (Cost). KPL challenged the Award under Section 34 of the Arbitration and Conciliation Act, 1996 (Act) before the Madras High Court and sought interim stay on execution of the Award under Section 36 of the Act.

The conditions for grant of interim stay of an arbitral award directing payment of money are guided by the principles of the Code of Civil Procedure, 1908 (CPC). While Order XLI Rule 5 of CPC empowers an Appellate Court to direct a party to deposit or furnish security of the decretal amount, Order XXVII Rule 8A of CPC provides that no security shall be required from the Government as the judgment-debtor.

The High Court granted an interim stay on the award subject to KPL furnishing a bank guarantee for merely the Principal Sum within a period of 8 weeks (Stay Order). The Court refused to issue orders qua the Cost component observing that KPL is not a fly-by-night operator and is a statutory undertaking.

ISDPL challenged the Stay Order before the Supreme Court of India.

DECISION OF THE COURT

The key issue for consideration was whether the High Court was correct in determining conditions for grant of stay of the Award – such as furnishing a bank guarantee instead of depositing the security amount and not including the Cost component – because KPL is a statutory undertaking.

Relying on its decision in Pam Developments Pvt Ltd v. State of West Bengal,6 the Supreme Court observed that since Section 36(3) of the Act postulates that a Court must merely 'have due regard' to the principles of CPC while granting interim stay of an arbitral award for payment of money, the law qua arbitration proceedings does not di[erentiate between statutory undertakings and private entities.

In support of its observation, the Court took note of Section 18 of the Act which mandates that parties shall be treated with equality. In this regard, the High Court erred in relying on the status of KPL as a statutory enterprise to frame the stay conditions.

Based on the principles for grant of interim stay under CPC, the Court modified the Stay Order and subjected the stay of the Award to KPL depositing 75% of the entire awarded sum including the Cost component.

Transfer of property to minor is not invalid

Neelam Gupta & Ors v. Rajendra Kumar Gupta & Anr

Supreme Court of India | October 14, 2024 2024 SCC OnLine SC 2824

The Supreme Court recently held that a sale is not a contract and that a minor can be a valid transferee of an immoveable property. In light of prevailing family disputes in India entailing adversarial property claims and harassment, this decision is significant in protecting the rights of minors from unscrupulous family litigation ensuring that the property is in the custody of the intended beneficiary. In property disputes, where the issue of adverse possession is often raised, this decision provides an important clarification that the limitation period of 12 years for claiming title under adverse possession under Section 27 (read with Article 65 of the Schedule) of the Limitation Act, 1963 commences when the defendant's possession become adverse and not when the right of ownership arises to the plaintiT.

SUMMARY OF FACTS

Rajendra Kumar Gupta (RKG) filed a suit in 1986 (Suit) seeking recovery of possession of land from Ashok Kumar Gupta and Rakesh Kumar Gupta (Defendants) contending to be the sole purchaser of the land from Sitaram Gupta, their common cousin, vide a registered sale deed in 1968, and claiming to have been dispossessed of the land in 1983 by the Defendants.

On the other hand, the Defendants contended that the land was jointly purchased by their father and the father of the RKG, in the name of Sitaram Gupta in 1963. They asserted that Sitaram Gupta had no right to sell the land to RKG since the same was purchased jointly. They also contended that the suit was barred by limitation, on principle of adverse possession i.e. the Defendants had perfected their title over the land by having possession over the same adverse to the title of RKG for a period of 12 years or more.

The Trial Court upheld the Defendants' contentions. The First Appellate Court set aside the finding of the Trial Court that the land was a joint family property but upheld the dismissal of the suit on the ground of limitation. The Chhattisgarh High Court reversed the concurrent findings and concluded that the Defendants had failed to prove their possession as being adverse to the title of RKG for a continuous period of 12 years or more.

Against this judgment, the legal representatives of the Defendants approached the Supreme Court.

DECISION OF THE COURT

While deciding on the twin issues of whether sale of the land by Sitaram Gupta to RKG was valid and whether the Defendants had perfected their title by way of adverse possession (i.e. by being in continuous and uninterrupted possession of the land for more than 12 years), the Court noted that the Defendants had not disputed the First Appellate Court's finding on the land not being a joint family property before the High Court, and proceeded on the basis that the land was not a joint family property.

Rejecting the Defendants' contention that the sale between RKG and Sitaram was void since Sitaram was a minor in 1963 and RKG was a minor in 1968, the Court held that the sale of land cannot be said to be a contract. Taking note of Section 54 of the Transfer of Property Act, 1882 (TOPA), it was held that 'sale' was a transfer of ownership in exchange for a price paid or promised or part-paid and part-promised. On a conjoint reading of the provisions of TOPA and the Indian Contract Act, 1872, it was held that the transfer of an immovable property in favour of a minor was permissible. Thus, a minor can be a transferee though not a transferor of immovable property.

On adverse possession, the Court stated that if possession of the land was permissive in nature, the Defendants could not claim title by way of adverse position. The Court further held that as per Article 65 of the Limitation Act, 1963, the starting point of limitation to claim title by way of adverse possession commences only from the date when the Defendant's ownership becomes adverse to the title of the Plaintiff.

Footnotes

1 2024 4 SCC 1

2 (2013) 1 SCC 641

3 2022 (9) SCC 186

4 Company Appeal (AT) (Ins) No. 481 of 2023

5 2022 SCC OnLine SC 1028

6 (2019) 8 SCC 112

Dispute Resolution & ADR Newsletter - November 2024 (pdf)

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More