Unicase is a leading law firm in Central Asia, operating both in the region and globally, including Kazakhstan, Uzbekistan, Kyrgyzstan, and Tajikistan. Unicase boasts one of the most expert teams, renowned for its capabilities in regulation and legislative development, which, combined with extensive transaction experience, enables the firm to win major development projects and remain a preferred adviser on corporate law, M&A transactions, dispute resolution, and legislation. Partners and senior lawyers at Unicase have spent a significant part of their professional careers working with leading international operators, which allows them to understand the expectations of both foreign and local clients regarding the format and content of legal consultations, making Unicase a competitive firm.
On April 1, 2022 amendments to the Methodology for Selection of Public Investment Projects (Order No. 129 of the Minister of National Economy of 5 December 2014) entered into force.
Kazakhstan Government, Public Sector

On April 1, 2022 amendments to the Methodology for Selection of Public Investment Projects (Order No. 129 of the Minister of National Economy of 5 December 2014) entered into force. The amendments stipulate the start of application of the so-called "1 to 1"  PPP criteria  under which the state obligations under the PPP projects, including state concession obligations (if necessary), should not exceed the amount of money spent or involved by the private partner (concessionaire) in the PPP (concession) project, including the private partner's own funds.

This innovation could potentially lead to the private partner under the PPP projects would only be able to receive the reimbursement of real costs incurred during the implementation of the project, i.e. the state would not provide additional funding to ensure the profit of the private partner under the project.

However, by Order No. 35 of the Minister of National Economy dated April 13, 2022, 3 key changes were introduced to the "1 to 1" criteria:

1) the amount of state obligations under the PPP project shall now not be greater than the private partner's own or own and borrowed funds;

2) the amount of the private partner's own or own and borrowed funds for the purpose of applying the "1 to 1" criteria has been increased to 20%;

3) "1 to 1" criteria shall not apply to the PPP projects in the social infrastructure and live support facilities.

It is recommended to take into consideration the amendments to the "1 to 1" criteria when planning the PPP and concession projects in Kazakhstan.