In recent years, our courts have considered the interaction between lien rights that arise under the Builders Lien Act, RSBC 1997, c. 45 and the Land Title Act, RSBC 1996 c. 250. For example, we have previously reported to you on the decision of 4HD Construction Ltd. v. Dawson Wallace Construction Ltd. (2020 BCSC 1224), which clarified the interaction of the Builders Lien Act and the Land Title Act when a party is seeking a discharge of certificates of pending litigation ("CPLs") from land. Recently, in Parkbridge Lifestyle Communities Inc. v New West Custom Homes (Kelowna) Inc., 2022 BCCA 299, the BC Court of Appeal confirmed that a builders lien claim could not be cancelled under the Land Title Act as a result of the lien claimants failure to take any steps in its litigation for over a year.

Background

Under the Builders Lien Act, a lien claimant that files a claim of builders lien is required to commence a notice of civil claim and register a CPL to perfect its lien claim within one year of the lien being filed. The Builders Lien Act is silent as to any litigation steps that must occur after the notice of civil claim is filed. Section 252 of the Land Title Act, however, specifies that an owner may apply to discharge a certificate of pending litigation registered against title to their property if no step has been taken in the proceeding for one year.

In Parkbridge, the BC Court of Appeal considered an appeal by the plaintiff and applicant, Parkbridge Lifestyle Communities Inc. of a decision of a chambers judge dismissing its application to discharge the lien claim filed by the defendant general contractor, New West Custom Homes (Kelowna) Inc., in connection with a 42 home development project being undertaken in Kelowna. Parkbridge was the owner of the development project and hired New West to act as the general contractor for the project. A dispute over construction progress and payment arose, resulting in New West filing a claim of builders lien (the "Lien") against title to the property. As contemplated by the Builders Lien Act, New West subsequently commenced litigation and caused a certificate of pending litigation to be filed against the property.

Chambers Decision

After the Lien was filed, Parkbridge obtained an order for the discharge of the Lien under section 24 of the Builders Lien Act on security of the face value of the lien being made. After the section 24 discharge was obtained, various steps were taken in the litigation, including Parkbridge filing a response to civil claim and counterclaim, and amendments to the counterclaim and New West's notice of civil claim.

Prior to Parkbridge bringing the application for cancellation of builders lien, (heard in September 2020), the last step taken in the litigation was New West filing an amended notice of civil claim on May 23, 2019. In its application, Parkbridge argued that the Builders Lien Act and the Land Title Act should be read together to create a new deadline on lien claimants, such that a claim of lien can be extinguished if no step is taken in the proceeding within a year, despite the litigation being commenced within the time limit prescribed by the Builders Lien Act.

The chambers judge dismissed the application, finding that while the cancellation of a claim of lien pursuant to the Builders Lien Act may result in the cancellation of a related CPL, the inverse was not true, and Parkbridge could not rely on section 252 of the Land Title Act and New West's failure to advance the proceedings for over a period of one year to have the Lien extinguished.

Decision of the Court of Appeal

Parkbridge appealed this decision. The BC Court of Appeal upheld the chambers judge's decision, agreeing that the Land Title Act does not provide a basis for extinguishing a builders lien claim where the lien claimant failed to advance the proceedings for a year (or more).

In making its decision, the Court of Appeal highlighted the distinctions between a CPL and a builders lien claim. A builders lien claim is the mechanism by which a party asserts a claim to an interest in land, while a CPL only gives notice that a claim to an interest in land is being alleged and to assert priority and otherwise limit how the land may be dealt with as the underlying claim is determined. Accordingly, while a party who loses a lien claim will lose a claim to an interest in land, a party who loses a CPL loses only the mechanism to give notice of its alleged claim to an interest in land.

The Court of Appeal further commented that, if the legislature had intended for a discharge of a CPL under the Land Title Act to result in the extinguishing of a lien claim, it would have expressly provided for this in the Builders Lien Act. As a result of its review and consideration of the Builders Lien Act and the Land Title Act, the Court of Appeal confirmed that the fundamental flaw in Parkbridge's position was that the CPL has been discharged from title to the property on the payment of security at the time it brought its application to extinguish the Lien under section 252 of the Land Title Act. At this time, there was no existing CPL and the court accordingly had no jurisdiction to make an order under the Land Title Act.

Takeaways and Items to Consider

This decision of the Court of Appeal confirms that parties seeking relief related to a builders lien claim must carefully consider if that relief is codified in the Builders Lien Act when assessing their strategy. Although both the Land Title Act and the Builders Lien Act deal with charges against land, our courts have recognized that the Builders Lien Act has been drafted to reflect a comprehensive code that sets out various relief and remedies available to lien claimants and owners. Parties to a lien claim dispute must be careful that they do not conflate any remedy or right available under the Builders Lien Act with any remedy or right available under the Land Title Act.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.