Japan: Amendments To Japan's Renewable Energy Act

On April 1, 2017, substantial portions of the Amendments ("Amendments") to The Act on Special Measures Concerning the Procurement of Renewable Energy by Operators of Electric Utilities (the "Act") will become effective. These Amendments, enacted on June 3, 2016,1 represent the most comprehensive set of changes to Japan's feed-in tariff system since the implementation of the Act in 2012.2 The Amendments reflect the efforts of the Ministry of Economy, Trade and Industry ("METI") to cause certified renewable energy facilities to meet certain feasibility criteria and to commence operation and power production within a specified period of time following certification. These Amendments will also require owners of renewable energy facilities to enter into an interconnection agreement with the relevant utility before certification and will introduce a bidding process for determining the purchase price for power generated by large-scale solar projects. In an effort to promote the development of renewable energy beyond solar power, these Amendments will provide for the fixing of the purchase price for three consecutive years following certification in the case of certain renewable energy projects (such as wind, geothermal, and biomass) that require several years and substantial cost to complete a feasibility study.

This Commentary provides a summary of the material changes that will go into effect as a result of the Amendments.

Facility Certification

Beginning on April 1, 2017, a developer of a renewable energy project in Japan will be eligible for facility certification from METI only after entering into an interconnection agreement with the relevant utility (or other distribution and transmission) company.3 Subject to certain exceptions, in order to ensure the continued validity of the applicable purchase price and purchase period after April 1, 2017, (i) projects that METI certified on or prior to June 30, 2016, under the system in effect before April 1, 2017, are required to have entered into an interconnection agreement with the relevant utility by March 31, 2017, and (ii) projects that METI certified between July 1, 2016 and March 31, 2017 under such system are required to have entered into an interconnection agreement with the relevant utility within nine months of the certification date. Each facility with a valid METI certification as of April 1, 2017 that meets the foregoing requirement is deemed recertified as of such date under the new certification system under the Amendments.

Under the Amendments, the facility certification system will be replaced by a business plan certification system. Each project with a valid METI certification as of April 1, 2017 that is deemed recertified under this new certification system will be required to submit to METI a business plan for renewable energy power generation by September 30, 2017.4 Each business plan must set forth (i) the name of the applicant (including its officers and directors, if any); (ii) a description of the renewable energy source and the commencement date for operation; (iii) the classification of the facility; (iv) a description of the interconnection arrangement; and (v) the location, capacity, and maintenance of the facility. Failure to submit a business plan by the due date will result in the loss of the METI certification.

In addition to requiring a business plan, METI will also be authorized to cancel any facility certification and issue an implementation order for any project in order to ensure that certified projects comply with applicable legal and regulatory requirements, such as requirements for environmental assessment or development permit (including any local ordinance requirements). Information relating to a certified facility will be made available to relevant governmental and local authorities to ensure accurate monitoring of compliance with such requirements.

Bidding System

The Amendments will introduce a bidding system for METI certification, which will be designed to reduce the applicable purchase price by promoting competition among developers. This bidding system initially will apply only to solar projects of 2,000 kW or more. According to METI, the first bid will take place in October 2017 and twice annually thereafter, with each bid process expected to be completed within six months. The bid process will be managed by a nonprofit organization to be designated by METI.

Under this bidding system, METI would solicit bids for a stated total capacity, and bidders would be given priority in the METI certification process starting with the party that submits the bid for the lowest purchase price (to the extent of the capacity for which the bid is made). In order to participate in the bid, each bidder will be required to post a bond, the amount of which will be set forth in METI's bid solicitation; each party whose bid is accepted by METI will be required to post an additional bond, which would be returned at the time of the application for METI certification. Each bid must be accompanied by a business plan that would be attached to the application for METI certification in the event the bid is accepted. The requested capacity in the bid must be the same as the capacity specified in the business plan. Once METI accepts a bid, the bidder is required to submit an application for METI certification by the deadline specified in the bid solicitation, together with evidence that the owner of the facility has secured the right to use the land on which the facility will be constructed. In addition, as a condition to METI certification, the owner is required to enter into an interconnection agreement with the relevant utility, pursuant to which the owner would be required to pay construction costs to the utility. Each party whose bid is accepted by METI is required to obtain METI certification within three months of the announcement date of the bid results. Until such METI certification is obtained, such party will not be able to transfer its rights under the bid to a third party. After such party obtains METI certification, any transfer of such party's rights thereunder will be subject to METI approval.

Each bid solicitation by METI is expected to set forth the following bid conditions:
 

  • the total capacity for which solicitation is being made;
  • bid qualification;
  • the amount of bond to be posted by each bidder;5
  • the maximum purchase price;6
  • the selection process for bid acceptance;
  • the applicable purchase period;7 and
  • the submission deadline for application for METI certification.


The introduction of this bidding system will likely increase the complexity for seeking METI certification for large-scale solar projects and the resulting competition likely will cause reductions in the applicable purchase price for such projects.

Three-Year Rule

Under the Amendments, a prerequisite for METI certification is a business plan for renewable energy power generation that provides, among other things, that the certified facility will commence power generation within three years from the date of the facility certification. In the case of a facility whose facility certification was issued before April 1, 2017, and with respect to which an interconnection agreement with the relevant utility was executed between August 1, 2016 and March 31, 2017, power production must commence within three years of April 1, 2017 (i.e., no later than March 31, 2020). Failure to commence power production within the three-year period will result in a reduction in the purchase period by the number of months between the date of the certification and the date on which the affected project actually commences power production. Such reduction in the purchase period also will apply to projects whose purchase price was determined pursuant to the bid system described above.

Transfer of Facility Certification ID

Developers of certified renewable energy projects have sold projects by transferring the METI identification number issued in connection with the facility certification to the purchaser. Prior to April 1, 2017, such transfers generally were effected by submission by the transferor of a Notice of Minor Change to METI, specifying the name of the transferee. The transfer then became effective upon METI's receipt of such notice, without any further action by METI. Under the Amendments, however, a change in the holder of the METI identification number no longer will be regarded as a "minor change," and any such change will be subject to METI approval. Under this new system, the transferor will be required to submit to METI an application for transfer, which application will be examined and approved by METI before the transfer is deemed effective. METI estimates that the standard examination period for a transfer application will be one month, but METI has not clarified its criteria for approval. Sellers and buyers of renewable energy projects after April 1, 2017, therefore, will need to take into account the estimated amount of time required for METI approval of certification identification transfer in determining the schedule for consummating the purchase and sale of such projects.

Other Changes

Under the Amendments, purchasers of power generated by a certified renewable energy project must be distribution and transmission companies under the Electricity Business Act, which, among other things, requires regional utilities to separate their electricity distribution and transmission businesses from their generation and retail businesses. A developer who entered into a power purchase agreement with a utility company prior to April 1, 2017, however, may continue to sell power to the utility company without amending the power purchase agreement.

The Amendments also provide for METI to determine the applicable purchase price for wind, biomass, geothermal, hydro, and solar (less than 10kW) projects for a consecutive three-year period, so as to facilitate potential developers in determining the profitability of any such potential renewable energy project.

Conclusion

The Amendments materially will change the standard timeframe and process for commencing renewable energy projects in Japan, and impose strict requirements for continued validity of the METI facility certification. After April 1, 2017, a developer will be required to (i) enter into an interconnection agreement with the relevant distribution and transmission company; (ii) (in the case of large-scale solar projects) participate in a bidding system in order to become eligible for METI certification; (iii) submit a business plan for the project and obtain METI certification; (iv) commence construction (including construction relating to interconnection); and (v) commence power generation within three years of the date of facility certification. The applicable purchase price and purchase period for large-scale solar projects will be determined after the completion of the bid and METI's acceptance of the business plan. With respect to projects for which METI certification was issued prior to April 1, 2017 and that satisfy the requirements for continued validity of such certification after April 1, 2017, the immediate priority will be the preparation and submission of a business plan by September 30, 2017.

Footnotes

1 "Japan Expands Renewable Energy Program, Tightens Requirements for Renewable Energy Projects," Jones Day Commentary, April 2016.

"Japan Launches the Feed-in Tariff System for Renewable Energy," Jones Day Commentary, July 2012; "Renewable Energy in Japan: One Year After the Implementation of the Feed-in Tariff Law," Jones Day Commentary, August 2013.

3  The execution of such interconnection agreement would mean that the applicant for facility certification must be contractually obligated to pay a specified amount to the utility company to cover the construction cost relating to the connection of the power facility to the utility's power grid.

4  Owners of facilities that METI certified between July 1, 2016 and March 31, 2017 under the pre-Amendment system are required to submit their business plan to METI within six months from the     execution date of the interconnection agreement.

5  Expected to be 500 Japanese Yen/kW at the time of bid submission and 5,000 Japanese Yen/kW upon bid acceptance (before application for METI certification).

6  Expected to be 21 Japanese Yen/kW for the October 2017 bid.

7  Expected to be 20 years.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
 
Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.