UK: NEC 3 And Target Cost Contracts: Defined Costs, Disallowed Costs And Defects

Last Updated: 24 August 2016
Article by Claire King

In this edition of Insight, we examine the role of Defined Costs and Disallowed Costs in the NEC3 Target Cost Contracts and look at the confusion sometimes encountered when dealing with the defects (and the costs associated with rectifying them pre and post completion). As Claire King explains, the provisions are in many ways counter-intuitive and require both the Contractor and Employer to buy into the philosophy behind the Contract in order for it to succeed.

Overview of the NEC3 Target Contracts

Options C and D of the NEC3 suite of Contracts provide for what is known as a target cost contract.1 This contains a mechanism for sharing risk and rewards known colloquially as a "pain/gain" mechanism.  This fits well with the philosophy behind the NEC suite of contracts more generally which is designed to achieve more of a collaborative approach to contracting than the traditional JCT style contract using "foresighted collaboration" to reduce the risks in the construction process.2

As noted in the NEC3 Guidance Notes,3 target cost contracts can be useful where the extent of the work to be done is not fully defined or where the risks anticipated are, for some reason, greater than usual.  The financial risks are shared between by the employer and the Contractor in a way which is meant to ensure that the Contractor is motivated to carry out the works as cost efficiently as possible.

In such contracts, a target cost or price is agreed between the parties. This includes the Contractor's estimate of what are called "Defined Costs" in the NEC3 form plus a fee which is meant to cover the Contractor's costs, overheads and profit.

During the course of the works, the Contractor is reimbursed for its "Defined Costs" plus paid an agreed fee minus any "Disallowed Costs".  Together, this is the "Price for Work Done to Date". Defined Costs (broadly speaking actual costs subject to the nuances detailed below) are assessed by the Project Manager during the course of the project by reference to Contractor's accounts and records which the Project Manager has the right to inspect at any time.

The target cost is adjusted during the course of the works for Compensation Events and (if selected as an option) inflation.4 At the end of the contract, a comparison is made between the final Defined Costs and Fee (the final "Price for Work Done to Date") and the target costs. If the final Price Work Done to Date is less than the target then the Contractor will make a share in the saving depending on the level agreed. If, however, it is greater than the target cost, the Contractor will pay a share of the difference (again at the level agreed). This "pain/gain" mechanism is designed to encourage efficiency and to align the Contractor's interests with those of the employer more closely, so it is argued, than the traditional forms of contracts.

The Definitions of Defined Pre-Completion Costs and Disallowed Costs

So what is the definition of Defined Costs? The exact definition of "Defined Cost" (which also appears in Options E5 and F6) varies depending on which NEC3 option is being used. Under Option C, Clause 11.2(23) it includes:

"the amount of payments due to Subcontractors for work which subcontracted without taking account of amounts deducted for

  • Retention;
  • Payment to the Employer as a result of the Subcontractor failing to meet a Key Date;
  • The correction of defects after Completion;
  • Payments to Others;
  • The supply of equipment, supplies and services included in the charge for overhead cost within the Working Areas in this contract; and
  • The cost of components in the Schedule of Cost Components for other work.

Less Disallowed Costs" [Emphasis added]

Broadly speaking, Defined Costs are the actual costs incurred by the Contractor on the Works minus retention and any costs which would fall within the overheads covered in the Fee.  From those are deducted "Disallowed Costs".

"Disallowed Cost" is defined by Clause 11.2(25).  They are, broadly speaking, costs that the Project Manager has decided are either: (1) not justified by the Contractor's accounts and record; (2) shouldn't have been paid to a subcontractor in the first place; or (3) were incurred because the Contractor did not follow the acceptance or procurement procedures laid down in the Works information or didn't give an early warning notice as required7.

The Contractor's "Defined Costs" will generally be the subject of regular audits and, for large projects, the level of information required to justify "Defined Costs" (and that they are not "Disallowed Costs") can be substantial.  The topic of establishing "Defined Costs" is, however, one for another article.

The costs of the following are also, amongst other items, expressly include in Disallowed Costs:

"

  • Correcting defects after Completion; and
  • Correcting defects caused by the Contractor not complying with a constraint on how he is to Prove the Works stated in the Works information."

Unless defects occur AFTER completion, or as a result of failing to comply with a constraint in the Works Information, the Contractor is then entitled to be paid for correcting "defects" which occur before Completion.  To many, this is entirely counter-intuitive8

Costs of Defects and the philosophy of Target cost contracts

A degree of "rework"9 or defects pre-completion is an inevitable part of the construction process, although it will obviously vary significantly from project to project. One study estimated that the median cost of re-work for construction projects was 4.03% of the total project costs but noted that the scale of rework was often significantly under-reported meaning that the actual costs associated with it were likely to be higher (at a median of 5.04%). In another Australian study, the means direct and indirect costs of rework were found to be 6.4% and 5.9% of the contract value respectively.10

Contractors used to fixed price contracts will price this rework or pre-completion defects into their prices.  In fact, under the NEC3 Target cost contract, there is arguably no reason to do so as they should be paid for this in any event.

For those on the employer's side of the fence, who are used to fixed price contracts, paying for the costs of rectifying pre-completion defects and/or rework because it forms part of Defined Costs is a hard pill to swallow. As such, the natural instinct for Project Managers who have not understood (or fully bought into) the philosophy of the NEC3 Target Contract properly, is to resist paying for pre-completion defects and the costs of the rework associated with them (although no doubt this will depend on their scale and severity!).

We are aware of instances where, on large infrastructure projects, the NEC3 target cost form has been amended to include much more stringent restrictions on costs that can be recovered as part of Defined Costs and/or deducted as Disallowed Costs.  These include providing that costs related to "breach of contract" can be deducted from Defined Costs as Disallowed Costs and that Defined Costs have to be "reasonably and properly" incurred.

The risk in adding these bespoke changes is that it shifts (potentially fairly significantly if you consider the statistics on rework costs above) the balance of risk on which the NEC3 target cost contract is built.  Permitting the recovery of the costs for the correction of defects pre-completion has, arguably, an indirect benefit to the Employer because when the Contractor is paid for remedying the defect, his Defined Cost increases. As a result, the Contractor's potential for making a gain share is reduced. If the Target Cost is exceeded, then the Contractor may have to give this money back. Therefore, the Contractor is incentivised to minimise the defects in order to keep Defined Cost down in the hope of ensuring a bigger gain share.

Other potential benefits that have been suggested include discouraging Contractors from hiding defective work rather than rectifying them at their own costs and also incentivising them to minimise any "snags" prior to completion.11

If, on the other hand, the costs of Defects before Completion are irrecoverable (either because they are not considered to be reasonably and properly incurred or because they are alleged to be a breach of the contract - albeit it is doubtful that a defect pre-Completion can be a breach given Completion has not yet occurred), then there is a very high risk that the Contractor will price the cost for this in somewhere else.12 Where then is the Contractor's motivation to minimise re-work and or defects pre-Completion which the NEC3 target cost contracts state they are designed to achieve?

Likewise, if the target is unachievable, the incentive to try to achieve it and to act efficiently in order to do so is effectively removed. The risk is then that the behaviours the NEC3 form is designed to try and discourage resurface in which case the whole point of using the NEC3 Target contract form in the first place should be reconsidered.

Drawing these strings together, it is arguable that Target cost contracts, being a variation of cost plus contracts, create inherently adversarial interests, in that the Contractor is primarily paid for his costs while the employer is required to scrutinise these costs to ensure that they are valid.

Not surprisingly, issues often arise as to whether the costs incurred by the Contractor may be disallowed. Disallowed costs can be difficult to identify in practice, as is the case, for example, with costs which the employer perceives to have been incurred as a result of the Contractor's inefficiency.

Further, there is less certainty for the employer under target cost arrangements about what the actual final cost will be: the nature of the Target cost contract is such that the employer also shares in the Contractor's risk. However, for those numerous instances where some form of cost plus contract may be more appropriate (for example, where a contract must be let before design development is sufficiently advanced to allow a lump sum price to be fixed; or where the employer wishes to participate in the design; or where Contractors are simply not prepared to take lump sum contracts due to the size and complexity of the project), the target cost option has clear advantages. Incentives can work if they genuinely result in an alignment of objectives between the parties. A realistic target cost and effective project management can play an instrumental role in maximising the chances of a Target cost contract delivering benefits for both parties. Giving careful consideration to the pain/gain share mechanism and tailoring it to the particular needs of the project is also of utmost importance.


Footnotes

1 Option C does this in relation to an Activity Schedule while Option D does this in relation to a Bill of Quantities.

2 See the preface to the Engineering and Construction Contract Guidance notes for NEC 3 dated April 2013 (the "NEC3 Guidance Notes") by Dr Martin Barnes CBE.

3 See page 14 of the NEC3 Guidance Notes.

4 Option X1. For Option D the costs are also adjusted as the works completed by the Contractor is measured (as to which see the NEC3 Guidance Notes).

5 Cost Reimbursable Contract.

6 Management Contract.

7 With certain exceptions, the Contractor must notify the Project Manager within eight weeks of becoming aware of an event that it considers to constitute a Compensation Event. If the Contractor fails to do so, it may not be entitled to a change in price (Clause 61.3), or if the Project Manager decides that costs were incurred – whether pursuant to a Compensation Event or otherwise – only because the Contractor failed to give an Early Warning Notice ("EWN") required under the contract, then those costs become Disallowed Costs (Clause 11.2(25)).

8 See "Disallowed Costs v Defined Costs in NEC Contracts" by Robert Gerrard, the NEC Users' Group Secretary, as published in the Magazine of the Chartered Institute of Building dated 3 May 2015, in which he noted that a significant number of queries that are made to the NEC Users are on the question of Disallowed Costs in NEC Contracts.

9 One possible definition of this is: "Activities in the field that have to be done more than once in the field, or activities which remove work previously installed as part of the project regardless of source, where no change order has been issued and no change of scope has been identified by the owner". See Navigant's report "The Impact of Rework on Construction & some practical remedies" dated August 2012; and Fayek, Aminah Robinson, Majula Dissanayake and Oswaldo Campero, Measuring and Classifying Field Rework: A Pilot Study by the Department of Civil and Environmental Engineering, University of Alberta, May 2003.

10 See Calculating total rework costs in Australian construction projects by Peter E.D. Love and David J. Edwards as published in Civil Engineering and Environmental Systems on 25 January 2007.

11 See "Do Target Cost Contracts deliver value for money?" by Ian Heaphy dated July 2011 (SCL Paper D126).

12 Arguments as to the meaning of reasonable and whether it adds anything or not to "properly" (which is clearly aimed at propriety) also open the door to disputes and again may result in changes in behaviour away from the collaboration envisaged.

With thanks to Jonathan More and Laura Bowler for their assistance.


Please click here to view previous issues of Insight

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Claire King
 
In association with
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.