United States: Winning The Corrective Action, And Using Clarifications Instead Of Discussions

In a recent Protest Roundup, we discussed Dell Federal Systems, LP v. United States, 2017 WL 2981811 (Fed. Cl. July 3, 2017), a case in which a contractor successfully challenged the scope of the voluntary corrective action an agency took in response to bid protests filed with the Government Accountability Office (GAO).  In this post, we'll take a closer look at the light that the case sheds on where and how contractors can try to minimize the effect of a lost protest or to ensure that a hard-fought protest victory does not get wiped away in corrective action.  In addition, we'll examine the court's distinction between clarifications and discussions and how it may signal another area of divergence from the GAO

I. Background

The Army issued a solicitation for commercial off-the-shelf (COTS) hardware through indefinite delivery, indefinite quantity (IDIQ) contracts.  The Army received 58 proposals, only nine of which were found to be technically acceptable.  Without conducting discussions, the Army awarded contracts only to the nine technically acceptable offerors, whereupon 21 of the 49 unsuccessful offerors (a number of which had lower prices than the awardees) filed protests at the GAO.  The protesters argued inter alia that the solicitation contained ambiguous directions concerning how to fill out two required spreadsheets.  Several of the protesters were found technically unacceptable for incorrectly filling out the spreadsheets – errors the protesters argued could have been easily corrected in clarifications or discussions.

The Army determined that the protests posed significant litigation risk in two regards.  First, the solicitation's spreadsheet instructions should have been clearer and likely were the reason so many offerors made the same errors.  Second, the Army determined that DFARS 215.306(c) likely required the Army to conduct discussions with the offerors, inasmuch as the procurement's value exceeded the regulatory threshold, and the Army did not appear to have a reasonable basis for forgoing discussions.  In light of this analysis, the agency chose not to fight the protests and instead committed to sweeping voluntary corrective action that included opening discussions with "virtually all of the offerors" and soliciting new proposals with revised pricing (even though the original awardees' prices had been disclosed).  This made it likely that all proposals would be technically acceptable, meaning that the nine original awardees' contracts would be in jeopardy in this Lowest Price Technically Acceptable procurement.  Six of the original awardees then filed suit at the Court of Federal Claims, challenging the agency's announced corrective action.

II. Overly Broad Corrective Action

The court agreed with the Army that the ambiguities in the solicitation spreadsheet and the failure to hold discussions in a procurement of this size were rational bases for the agency's decision to take voluntary corrective action, even though both issues likely were untimely as protest grounds either at the court or at the GAO.  The court disagreed, however, with the scope of the proposed corrective action.  Although it recognized that contracting officers are afforded broad discretion in taking corrective action, the court found that the agency's proposed corrective action was not rationally related to the defect to be corrected.

What, then, is the proper correction of a failure to hold discussions with the offerors?  The court held, at least under the facts here, that it was too late to open discussions after awards had been made (and the awardees' prices revealed):

If the Army wished to comply with the GAO's SAIC decision [regarding the requirement to conduct discussions pursuant to DFARS 215.306(c)], it would have been reasonable for the Army to conduct open-ended discussions before it awarded its contracts.  However, now that the contracts have been awarded, any damage caused by not holding discussions—including the disqualification of several offerors as a result of clerical errors—has been done.  The question now is whether holding post-award discussions is a rational remedy for failing to hold pre-award discussions, and the Court finds that this conclusion does not follow.  After all, constructing a henhouse gate is not an appropriate remedy after the fox has done its work—one instead needs new chickens.

The court then noted that the Army failed to consider a narrower solution:  conducting clarifications (rather than discussions) and reevaluating the existing proposals in light of the clarifications.  Clarifications would be sufficient to correct the minor errors in the offerors' spreadsheets, while leaving unacceptable those proposals that contained more substantive problems.  Because the court found that a more narrowly targeted solution existed to the problem of the spreadsheet errors and lack of discussions, the court held that the agency's broad corrective action was arbitrary and capricious.

This holding, although in harmony with a number of other Court of Federal Claims' decisions on overly broad corrective action, is in tension with the GAO's strong deference to agencies' corrective action choices.  Compare WHR Group, Inc. v. U.S., 115 Fed. Cl. 386 (2014) (holding that the corrective action was not rationally related to any procurement defect); Sheridan Corp. v. U.S., 95 Fed. Cl. 141 (2010) (finding agency's intended corrective action should have been more narrowly tailored), with Alliant Enterprise JV, LLC, B-410352.4, Feb. 25, 2015, 2015 CPD ¶ 82 at 2 ("[T]he corrective action taken here is well within the broad discretion afforded to contracting agencies."); Solution One Industries, Inc., B-409713.3, Mar. 3, 2015, 2015 CPD ¶ 167 at 3 (holding that agencies have broad discretion in crafting proposed corrective action).  In the end, whether an agency's corrective action goes too far often comes down to a judgment call.  As Dell illustrates, the court traditionally is more disposed to second-guess agencies than is the GAO.  For that reason, the court may be a better forum than the GAO for parties unhappy with an agency's choice of corrective action.

III. Clarifications vs. Discussions

The second interesting twist in Dell is the court's distinction between discussions and clarifications.  The decision describes only one illustrative ambiguity in any detail.  Nineteen offerors in Dell misunderstood the solicitation's spreadsheet form and mistakenly put "N/A" for certain supplies instead of a price, based upon differing thicknesses of the spreadsheet's dividing lines.  The agency evaluators thought "N/A" meant the offerors would not provide those supplies, in accordance with the spreadsheet instructions not to leave any entries incomplete or blank.  The offerors apparently thought those entries were optional subcomponents and did not need to be completed.

The court found that the unacceptable offerors' spreadsheet problems were "minor or clerical errors" that could be corrected by clarifications rather than full-blown discussions:

Many of the offerors here did not make material mistakes; rather, they filled out a confusing Excel spreadsheet incorrectly. . . .  Similarly, the Army here knew that ambiguities in its spreadsheet had likely caused offerors to make clerical errors.  Indeed, the [memorandum for record] itself acknowledges the "logical conclusion" that offerors were disqualified because of "mere [ ] compliance issues with filling out the form rather than a deficiency in the item proposed."  If this language does not suggest the Army knew that offerors had made clerical errors, it is difficult to see what would.

As such, it was irrational for the Army not to seek clarification from all offerors it knew had been directly affected by the ambiguities it had identified in its own spreadsheet.  Doing so would not have given all offerors the chance to make their proposals technically acceptable—there are several offerors who made more wide-reaching errors—but it would have given the offerors who justifiably thought they were proposing compliant equipment the chance to show that they were in fact proposing compliant equipment.  The Army then could have reevaluated the offerors' proposals instead of resoliciting new proposals.

Discussions are "[n]egotiations . . . between the Government and offerors, that are undertaken with the intent of allowing the offeror to revise its proposal . . . [and that] take place after establishment of the competitive range."  FAR 15.306(d).  Clarifications, by contrast, are "limited exchanges, between the government and offerors that may occur when award without discussions is contemplated."  FAR 15.306(a)(1).  These limited exchanges allow offerors to clarify certain aspects of their proposals, such as past performance information, or to resolve minor or clerical errors.  The distinction between clarifications and discussions is usually characterized as a question of whether the offeror is allowed to revise its proposal.  See, e.g., JWK Int'l Corp. v. United States, 52 Fed. Cl. 650, 661 (2002), aff'd, 56 F. App'x 474 (Fed. Cir. 2003) (Clarifications "are not to be used to cure proposal deficiencies or material omissions, materially alter the technical or cost elements of the proposal, or otherwise revise the proposal.").  GAO and the court have long struggled with finding the dividing line between discussions and clarifications, with the court showing more tolerance for conducting extensive communications under the guise of clarifications.

In Level 3 Communications v. United States, for example, the Court of Federal Claims found that an inquiry into a missing file would be a clarification instead of a discussion because the file would simply allow the contracting officer to confirm the offeror's proposal without an opportunity to revise it.  129 Fed. Cl. 487, 504 (2016).  And in Rivada Mercury v. United States, the court found that hundreds of questions, hours of oral presentations, and yet more follow-up questions constituted clarifications rather than discussions.  131 Fed. Cl. 663 (2017).  In several instances, the question-and-answer process allowed the awardee to change its proposal, but the court nevertheless determined that because the procurement was large and technical, extensive exchanges were reasonable as "clarifications."

The GAO, on the other hand, historically has taken a harder line on clarifications, finding discussions to occur whenever an offeror is allowed to revise its proposal.  See, e.g., Manthos Eng'g, LLC, B-401751, Oct. 16, 2009, 2009 CPD ¶ 216 at 2 (denying protest where protester failed to provide required option year prices); Battelle Memorial Inst., B-299533, May 14, 2007, 2007 CPD ¶ 94 at 4 ("[O]mission of the option year pricing is material, given the RFP's requirements to provide detailed option year pricing for evaluation, and any attempt to cure this omission would necessitate submission of a revised proposal and would constitute discussions."); Gulf Copper Ship Repair, Inc., B-293706.5, Sept. 10, 2004, 2005 CPD ¶ 108 at 6 (finding that an agency opened discussions by affording one offeror the opportunity to revise the past performance section of its proposal).

The Dell court, like the Rivada court and unlike the usual GAO approach, appears to have employed an expansive interpretation of clarifications.  Although the decision does not describe the ambiguities in detail, the spreadsheets' confusing instructions in Dell apparently led many offerors not to provide pricing for certain supplies.  Where an offeror did not propose pricing for an item (based on a reasonable but mistaken belief that it was not required to supply that item), it is difficult to see how an opportunity to add pricing for an item that the offeror did not intend to supply constitutes a clarification rather than discussions.  Although the correction is minor and easily accomplished, it appears to constitute a revised proposal – a hallmark of discussions.

Outside the area of corrective action, these recent decisions employing a more accommodating definition of "clarifications" dovetail with the court's greater willingness to scrutinize the reasonableness of an agency's decision not to conduct clarifications in the first place.  The GAO invariably refuses to second-guess an agency's discretion not to conduct clarifications in FAR Part 15 procurements.  See, e.g., CJW—Desbuild JV, LLC, B-414219, Mar. 17, 2017, 2017 CPD ¶ 94 at 4 n.2 (refusing to apply Court of Federal Claims case law and holding that failure to submit proof of a joint venture agreement was not a minor clerical error); Cubic Simulation Systems, Inc., B-410006; B-410006.2, Oct. 8, 2014, 2014 CPD ¶ at 7 (holding that agency was within its rights to refuse to conduct clarifications and refusing to apply Court of Federal Claims case law); PN & A, Inc., B-406368, Apr. 23, 2012, 2012 CPD ¶ 145 at 3 (holding that agency was not required to conduct clarifications).  The court, on the other hand, has held that agency discretion not to conduct clarifications is not unlimited and, under the right circumstances, may be arbitrary and capricious.  See, e.g., Level 3 Communications., LLC v. United States, 129 Fed. Cl. 487 (2016) (decision not to seek clarifications was arbitrary and capricious where the protester's price was much lower than the awardee's and protester's proposal did not clearly show its proposed working path did not go through Iran); BCPeabody Constr. Servs., Inc. v. United States, 112 Fed. Cl. 502 (2013) (contracting officer abused her discretion by refusing to seek clarification regarding a "copying mistake" in the protester's offer).

The upshot of these cases is that, if a company loses a competition due to a relatively minor mistake that should have been obvious to the evaluators and could have been easily corrected to the Government's benefit, the company may be better off protesting at the court rather than the GAO.

Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Morrison & Foerster LLP. All rights reserved

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Similar Articles
Relevancy Powered by MondaqAI
 
In association with
Related Topics
 
Similar Articles
Relevancy Powered by MondaqAI
Related Articles
 
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Mondaq Free Registration
Gain access to Mondaq global archive of over 375,000 articles covering 200 countries with a personalised News Alert and automatic login on this device.
Mondaq News Alert (some suggested topics and region)
Select Topics
Registration (please scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions