United States: IRS Issues Additional Guidance On Beginning Of Construction Rules For Renewable Projects - December 20, 2016

Summary

On December 15, 2016, the Internal Revenue Service released Notice 2017-04, which provides welcome guidance on how to meet the "beginning of construction" requirements for wind and other qualified facilities. There has been much uncertainty about when construction of these types of facilities begins for renewable energy tax credit purposes. The Notice (1) extends the "Continuity Safe Harbor" placed in service date for projects that started construction before 2014; (2) provides that the "combination of methods" rule set forth in prior guidance only applies to facilities on which construction begins after June 6, 2016; and (3) clarifies that for purposes of the 80/20 Rule, the cost of new property includes all costs properly included in the depreciable basis of the new property.

In Depth

On December 15, 2016, the Internal Revenue Service (IRS) released Notice 2017-04 (the Notice). The Notice provides guidance on how to meet the "beginning of construction" requirements for wind and other qualified facilities (including biomass, geothermal, landfill gas, trash, hydropower, and marine and hydrokinetic facilities). The Notice extends the Continuity Safe Harbor placed in service date by which a facility can meet the beginning of construction tests for facilities that began construction before 2014. Specifically, the Notice states that if a facility is placed in service by the later of (1) a calendar year that is no more than four calendar years after the calendar year during which construction of the facility began, or (2) December 31, 2018, the facility will be considered to satisfy the Continuity Safe Harbor.

Following prior IRS guidance, a facility was considered to have satisfied the Continuity Safe Harbor if the facility was placed in service within the four-year period following when construction commenced or December 31, 2016, whichever is later. The change in the Notice provides welcome guidance for projects that began construction prior to 2014 and were unlikely to be placed in service within the four-year period, but are anticipated to be placed in service by the end of 2018.

The Notice also provides that the "combination of methods" rule set forth in Notice 2016-31 only applies to facilities on which construction begins after June 6, 2016 (the date on which Notice 2016-31 was published). The combination of methods rule prohibits a taxpayer from relying upon the Physical Work Test and the Five Percent Safe Harbor in alternating calendar years to satisfy the beginning of construction rules or the Continuity Requirement. Seemingly, this rule permits projects that met the Physical Work Test and the Five Percent Safe Harbor in different years prior to June 6, 2016, to rely on the method used in the most recent year. Finally, the Notice clarifies that for purposes of the 80/20 Rule, the cost of new property includes all costs properly included in the depreciable basis of the new property.

According to the Notice, the IRS will issue separate guidance addressing the extension and modification of the investment tax credit (ITC) for solar facilities under Section 48.

Background

On December 18, 2015, the Protecting Americans from Tax Hikes Act of 2015 (PATH Act) amended the production tax credit (PTC) and the ITC. Specifically, the PATH Act included multi-year extensions of the PTC and the ITC for wind and solar projects, along with a gradual phase-out of the credit.

In the case of wind, the PATH Act extended the PTC through 2019 (including the corresponding election to take the ITC in lieu of the PTC for wind projects), such that wind projects that begin construction prior to the end of 2019 will be eligible for the PTC or ITC. Previously, the PTC for wind only applied to projects beginning construction before the end of 2014.

The PATH Act also reduced the PTC and ITC for wind by 20 percent for projects commenced in 2017, by 40 percent for projects commenced in 2018, and by 60 percent for projects commenced in 2019. For energy facilities other than wind, such as biomass and geothermal projects, the PATH Act extended the PTC through the end of 2016 and included a corresponding extension of the election to take the ITC in lieu of the PTC. For more information on the PATH Act's extension of renewable energy tax incentives, including the extension of the ITC for solar projects, click here.

The Notice updates the guidance provided in prior notices (Notice 2013-29, Notice 2013-60, Notice 2014-46, Notice 2015-25 and Notice 2016-31, together referred to herein as the Prior Guidance). The Notice explains that the IRS will not issue private letter rulings to taxpayers regarding the application of the Notice, the Prior Guidance or the beginning of construction requirement under Sections 45(d) and 48(a)(5).

Notice 2013-29

Under Notice 2013-29, a taxpayer may establish that construction has begun on a qualified facility by demonstrating that "physical work of a significant nature" has begun (Physical Work Test) or by satisfying a 5 percent safe harbor (Five Percent Safe Harbor). Notice 2013-29 lists several examples of work that meets the Physical Work Test, including, with respect to a wind energy facility, the beginning of the excavation for the foundation, the setting of anchor bolts into the ground or the pouring of the foundation's concrete pad. Both onsite and offsite work may be taken into account. The IRS also imposed a requirement that a "continuous program of construction," as defined in the Prior Guidance (Continuous Construction Test), be maintained after performance of physical work in 2013 until the relevant project is placed in service.

The Five Percent Safe Harbor set forth in Notice 2013-29 provides that the construction of a qualified facility is considered to begin before January 1, 2014, if a taxpayer pays or incurs (within the meaning of the accrual rules of Treasury Regulation Section 1.461-1(a)(1) and (2)) 5 percent or more of the total cost of the facility before such date. Thereafter, the taxpayer must make continuous efforts to advance toward completion of the facility (Continuous Efforts Test) in order to be deemed to have begun construction (the Continuous Construction Test and the Continuous Efforts Test are referred to herein collectively as the Continuity Requirement).  

For more information on these tests and their requirements, see McDermott's article on Notice 2013-29.

Notice 2013-60

In September 2013, the IRS issued Notice 2013-60, clarifying questions left outstanding by Notice 2013-29. Specifically, Notice 2013-60 provided that a facility was to be considered to satisfy the Continuity Requirement if it was placed in service before January 1, 2016 (the Continuity Safe Harbor). Notice 2013-60 also permitted a taxpayer to claim the PTC or ITC even if the taxpayer was not the owner of the facility on the date construction began. For more information, see McDermott's article on Notice 2013-60.  

Notice 2014-46

Notice 2014-46 clarified that the Physical Work Test focuses on the nature of the work performed rather than the amount or cost of such work. Notice 2014-46 also provided guidance regarding transfers of a facility by the taxpayer after construction has begun, but before that taxpayer placed the facility in service. Notice 2014-46 modified the Five Percent Safe Harbor rule set forth in earlier guidance by providing that, if a taxpayer incurred at least 3 percent of the total cost of such a facility before January 1, 2014, the Five Percent Safe Harbor may be satisfied with respect to some (although not all) of the individual facilities that are part of this larger project. For more information, see McDermott's article on Notice 2014-46.

Notice 2015-25

Notice 2015-25 extended the relevant Continuity Safe Harbor placed in service dates under the earlier notices so that the beginning of construction guidance mirrored the statutory extension of the PTC and the ITC under the Tax Increase Prevention Act of 2014 (TIPA). Prior to the extension under TIPA, Sections 45(d) and 48(a)(5) required that construction of a qualified facility begin before January 1, 2014, for the facility to be eligible for the PTC or the ITC. Based on the language of those sections as in effect before TIPA, the guidance prior to Notice 2015-25 provided advice on determining whether construction had begun on a qualified facility prior to January 1, 2014. Because TIPA extended the date by which construction of a qualified facility must begin to January 1, 2015, Notice 2015-25 extended the Continuity Safe Harbor placed in service date to meet the Continuity Requirement to January 1, 2017. For more information, see McDermott's article on Notice 2015-25.

Notice 2016-31

Notice 2016-31 extended the relevant Continuity Safe Harbor placed in service dates to correspond with the extension and modification of the PTC by the PATH Act. Specifically, Notice 2016-31 provided that a facility will be considered to satisfy the Continuity Requirement if the facility is placed in service by the later of (1) a calendar year that is no more than four calendar years after the calendar year during which construction on the facility began, or (2) December 31, 2016. As an example, Notice 2016-31 provides that if construction on a wind facility began on January 15, 2016, and the facility is placed in service by December 31, 2020, the facility will be considered to satisfy the Continuity Safe Harbor.    

Notice 2016-31 also set forth a "combination of methods" rule under which a taxpayer cannot alternate between the Physical Work Test and the Five Percent Safe Harbor to satisfy the beginning of construction requirement or the Continuity Requirement. For example, if a taxpayer relied on the Physical Work Test to satisfy the beginning of construction rules in 2015, and then in 2016 incurred costs totaling 5 percent or more of the total cost of the facility, the taxpayer could not then use the Five Percent Safe Harbor to satisfy the beginning of construction requirement or the Continuity Requirement. Instead, the Continuity Safe Harbor is applied beginning in 2015. 

Notice 2016-31 also (1) revised and added to the list of excusable disruptions that will not be taken into account when determining whether the Continuity Requirement has been met, (2) provided additional examples of work that meets the Physical Work Test for different types of renewable energy facilities, (3) revised the list of preliminary activities that do not constitute "physical work of a significant nature" for purposes of the Physical Work Test, (4) provided additional guidance on whether and how multiple facilities are treated as a single facility for beginning of construction purposes, and (5) provided additional guidance on the application of the Five Percent Safe Harbor to retrofitted facilities. 

For more information on these tests and their requirements, see McDermott's article on Notice 2016-31.

Notice 2017-04

The Notice modifies the Continuity Safe Harbor by providing that if a taxpayer places a facility in service by the later of (1) a calendar year that is no more than four calendar years after the calendar year during which construction of the facility began, or (2) December 31, 2018, the facility will be considered to satisfy the Continuity Safe Harbor. By changing the date from December 31, 2016, to December 31, 2018, the Notice allows certain projects on which construction began prior to 2014 to qualify for the Continuity Safe Harbor. For example, if construction began on a facility on January 15, 2013, and the facility is placed in service by December 31, 2018, the facility will be considered to satisfy the Continuity Safe Harbor. Under the Prior Guidance, this facility would not have been eligible for the Continuity Safe Harbor, and the taxpayer would have needed to demonstrate that the Continuity Requirement was met under the relevant facts and circumstances. Alternatively, if construction begins on a facility on January 15, 2016, and the facility is placed in service by December 31, 2020, the facility will be considered to satisfy the Continuity Safe Harbor.    

The Notice also states that the "combination of methods" rule set forth in Notice 2016-31 only applies to facilities on which construction begins after June 6, 2016 (the date on which Notice 2016-31 was published in IRB 2016-23). Therefore, if a taxpayer meets the Physical Work Test with respect to a facility in 2014 and the Five Percent Safe Harbor test for the facility in 2015, the taxpayer seemingly can apply the Continuity Safe Harbor test from 2015, meaning that the taxpayer must place the facility in service by December 31, 2019, in order to satisfy the Continuity Safe Harbor. Taxpayers that begin construction on facilities after June 6, 2016, however, will be prevented from restarting the four-year window for placing the facility in service by using the other beginning of construction method to qualify the facility as having begun construction in the later year. 

The Notice provides that, as indicated in the Prior Guidance, a retrofitted facility may qualify as originally placed in service for purposes of the PTC and ITC if the fair market value of used property does not constitute more than 20 percent of the facility's total value. Thus, the cost of the facility's new property must be at least 80 percent of the facility's total value (the 80/20 Rule). The Prior Guidance indicated that the Five Percent Safe Harbor is applied only with respect to the cost of new property used to retrofit an existing facility, and that all costs properly included in the depreciable basis of the facility are taken into account to determine whether the Five Percent Safe Harbor has been met. The Notice clarifies that for purposes of the 80/20 Rule, the cost of new property includes all costs properly included in the depreciable basis of the new property. Taxpayers had questioned whether indirect costs that were allocable to the depreciable basis could be included for these purposes, and the Notice appears to affirmatively answer this question.      

Conclusion

The Notice provides much-needed guidance with respect to facilities on which construction began prior to January 1, 2014, that otherwise would not have been placed in service within the four-year Continuity Safe Harbor window. The Notice also provides useful clarity with respect to the "combination of methods" rule and the scope of eligible property under the 80/20 Rule.

IRS Issues Additional Guidance On Beginning Of Construction Rules For Renewable Projects - December 20, 2016

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
 
In association with
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.