ARTICLE
28 August 2015

No Short Cuts Allowed: The FWS Must Comply With NEPA Before Extending Programmatic Take Permits To 30 Years

FH
Foley Hoag LLP

Contributor

Foley Hoag provides innovative, strategic legal services to public, private and government clients. We have premier capabilities in the life sciences, healthcare, technology, energy, professional services and private funds fields, and in cross-border disputes. The diverse experiences of our lawyers contribute to the exceptional senior-level service we deliver to clients.
Earlier this month, the Judge Lucy Koh set aside the Fish & Wildlife Service's decision to extend its programmatic permit for bald and golden eagle SOARING EAGLE-1000 pixels widetakes from five to 30 years.
United States Environment

Earlier this month, the Judge Lucy Koh set aside the Fish & Wildlife Service's decision to extend its programmatic permit for bald and golden eagle takes from five to 30 years.  The extension was sought by the wind industry for the obvious reason that the uncertainty attached to a five-year permit makes financing a 20- or 30-year project very difficult.  I agree with the concern and support the extension, but the FWS's attempt to short-circuit NEPA requirements in order to get the extension done quickly was doomed from the start.

Indeed, this case mostly stands for the proposition that bureaucratic overreach is almost always counterproductive.  The extension was not just opposed by environmental groups and native American tribes.  It was also opposed by the National Park Service – and FWS's own staff, including the writer of the rule!  Eliza Savage, described by the Court as having "'responsibility for overseeing the drafting and revision' of the Proposed 30-Year Rule," was the source of the following nuggets from the administrative record:

  • It was a "no-brainer that [FWS] needed to do a NEPA analysis," (referring to the rule's "critical NEPA deficiencies").
  • The [30-year] permits will be inherently less protective for eagles than 5-year permits
  • The regulatory process for the extension of the permit was a "train wreck" that "no one could be proud of"

Ms. Savage and others at FWS warned that the permit was on legally tenuous ground.  Consistent with that, staff's final recommendation to FWS director Dan Ashe was to "shelve the ... rule and do an EIS."  Director Ashe rejected the recommendation.

Bad idea.  If FWS had bitten the bullet in 2012 and prepared the EIS, it would be done now.  An effort to accelerate permit protection for wind farms has only increased the uncertainty for wind farm developers.

Short cuts almost never work.

To view Foley Hoag's Law and the Environment Blog please click here

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.