UK: Projects & Construction Law Update - August 2018

Last Updated: 29 August 2018
Article by Robert Meakin and Rebecca Evans

Most Read Contributor in UK, November 2018

Cases

Do you have an adequate mechanism for determining payment?

CIMC MBS LTD (formerly VERBUS SYSTEMS LTD) v BENNETT (CONSTRUCTION) LTD (2018)

The Housing Grants Construction and Regeneration Act 1996 (HGCRA) requires that all construction contracts provide an adequate mechanism for determining what payments are due, and when – failure to do so resulting in contractual payment terms being unenforceable and the relevant paragraphs of the Scheme applying (s. 110(1)(a)). With little guidance on what constitutes an 'adequate mechanism' (the answer largely being a question of fact), this case will be of interest to contractors and clients alike, with a sub-contractor successfully obtaining declarations that parts of the agreed payment terms did not comply with s. 110(1)(a).

Bennett engaged CIMC under a JCT Design and Build Sub-Contract 2011 (with amendments) to design, supply and install pre-fabricated bedroom units in a new hotel in London. The units were to be manufactured in China, shipped to Southampton and transported to London.

The payment provisions in the Sub-Contract provided for milestone payments as follows:

  1. 20% of the contractual sum payable upon execution of the Sub-Contract;
  2. 2.30% payable on sign-off of the prototype room by the contractor, employer and hotel operator;
  3. 3.30% payable on sign-off of all snagging items by the contractor, employer and hotel operator;
  4. 4.10% payable on sign-off of units in Southampton; and
  5. 5.10% payable on completion of installation and snagging.

Unsurprisingly, a payment dispute arose and CIMC suspended work over non-payment. It referred the dispute over its payment entitlement to adjudication and sought a number of declarations, most relevantly that milestones 2, 3 and 4 did not comply with s. 110(1)(a) of the HGCRA. The adjudicator disagreed and CIMC commenced proceedings in the TCC.

The TCC considered previous authorities that had found the intention of s.110(1)(a) was to 'do away with uncertainty'. Construing the payment provisions in the context of the Sub-Contract as a whole, the TCC found that milestones 2 and 3 did not comply with s. 110(1)(a) because the criteria and date for sign-off were not clear. The TCC took the view that the term 'sign-off' (as it was used elsewhere in the Sub-Contract) was intended to signify a requirement for client approval. However, there was nothing in the Sub-Contract setting out what this approval process involved. Using the analogy of a surveyor's certificate, the TCC considered that specific criteria and timescales were required in order to provide the requisite certainty, otherwise a failure to sign-off could not be challenged.

The TCC disagreed, however, with CIMC's arguments in relation to milestone 4, finding that, in the context, the term 'sign-off' could be construed as the point at which the units were delivered from the ship at Southampton.

While Judge Wakeman QC invited the parties to make further submissions in relation to the consequences of the above findings, the (so far) unreported decision provides parties with further guidance as to what may constitute an inadequate mechanism for determining payment. Particularly in the context of milestone schedules, both parties (and especially clients) should ensure that there is a clear process setting out how the achievement of each milestone is to be certified. If an approval process is involved, there should be clear criteria against which milestone achievement is measured and deadlines for determining if such criteria have been satisfied.

While we are yet to find out the consequences for the defendant in this case, the risk with non-complying payment provisions is that they will result in the relevant paragraphs of the Scheme being implied into the relevant contract, which is unlikely to have been what the parties contracted for. We will keep readers updated as to the consequences for CIMC and Bennett, so stay tuned...

Looking to set-off sums in adjudication? Make sure your Payment or Pay Less notice anticipates this...

MI Electrical Solutions Ltd v Elements (Europe) Ltd [2018] EWHC 1472 (TCC)

A responding party was caught out when it failed to raise a set-off argument in its Pay Less notice, with the adjudicator and the TCC finding that such failure prevented it from raising set-off as a defence in the adjudication. The question then arose as to whether the set-off was permitted against the adjudicator's decision...

The courts have traditionally adopted a restrictive approach when it comes to permitting set-off against an adjudicator's decision. The rationale for this is that, pursuant to s. 108 of the HGCRA (and sans issues with jurisdiction), the decision of an adjudicator is binding until the relevant dispute is finally determined by legal proceedings, arbitration or agreement. Any provision in a construction contract that entitles a party to withhold sums against or otherwise not pay against an adjudicator's decision defeats the purpose of s. 108. Accordingly, the court's approach is to construe the relevant contract so as to give effect to the intention of Parliament or, if this cannot be done, strike out the offending clauses. The only exceptions to this (which are rarely successfully utilised) are where the set-off follows logically from the adjudicator's decision or is the natural corollary of that decision.

In this case, the claimant sub-contractor applied for summary judgment to enforce an adjudicator's decision against the defendant contractor. A dispute had arisen relating to non-payment. The adjudicator ruled that the contractor's reason for non-payment provided in the Pay Less notice (namely an allegation of delay), was insufficient to justify non-payment. The contractor then tried to rely on arguments in its Response that it was entitled to set-off the cost it incurred in rectifying the subcontractor's defective work. The Pay Less notice had not included any mention of the subcontractor's defective works or the contractor's right to set-off.
The adjudicator concluded that, irrespective of the merits of the defects argument, it could not amount to a defence to a claim in the adjudication as the 'faults' were not the subject of the Pay Less Notice. The contractor subsequently challenged this decision in the TCC.

The TCC sided with the adjudicator, holding that 'The time at which to raise defective works in defence of a cross-claim to a claim for payment is in the Pay Less notice'.. Despite this finding, the contractor invited the TCC to construe the set-off clauses relied on in a manner which permitted set-off against the adjudicator's decision. The TCC declined to do so. Applying the principles discussed above, Mr Nissan QC held that 'the clauses which permit set-off as a matter of contract, have to be read as only permitting it subject to the effect of the Act or they would otherwise not be in compliance with the policy of the Act and would therefore need to be struck down'.

Mr Nissan QC was of the view that the only way the relevant set-off clauses could be construed as consistent with the HGCRA (so they could fulfil some contractual purpose) was to (i) read them simply as not applying to monies due by reason of an adjudicator's decision; or (ii) construe the implied provision that the adjudicator's decision was of binding effect to mean binding irrespective of other contractual obligations (unless there is an exception – though in this case, neither exceptions were found to apply). If Mr Nissan QC was wrong in his construction, the only other option was to treat the set-off provisions as unenforceable as a result of their inconsistency with the policy of the Act.

This decision serves as a reminder for responding parties to set out all of their potential defence and cross-claim arguments (including for set-off) in your Payment or Pay Less notices to ensure you are able to rely on these arguments in any future adjudication. Including such arguments in an adjudication Response will not save you from an earlier failure to raise them. Unless you can rely on one of the applicable exceptions (which will apply only in rare cases) and where there are no issues of jurisdiction, unsuccessful respondents will be bound to make payment in accordance with the adjudicator's decision without any allowance for set-off.

Following Grove v S&T...

DSVG Facade Ltd v Conneely Facades Ltd (2018)

Further to Coulson J's decision in Grove Developments Limited v S&T(UK) Limited, which allowed an employer to commence a second adjudication to assess the true value of sums awarded in a "smash & grab" adjudication, this case considered whether an adjudicator had gone wrong by failing to adjudicate on the true value of the works...

The case of DSVG Facade Ltd v Conneely Facades Ltd centred on whether an adjudicator had acted in breach of the principles of natural justice and failed to exhaust his jurisdiction when he did not go on to determine the true value of works after determining the substantive dispute in a "smash & grab" adjudication in favour of the claimant. The defendant argued that the value of the works ought to have been considered, as this constituted an alternate or secondary claim that was in dispute between the parties.

At enforcement, it was held that, as the adjudication documents (including the adjudication notice), only referred the issue of the claimant's entitlement to the notified sum to the adjudicator, he did not have jurisdiction to decide the true value of that claim, which was a separate issue. The value of the claim was, for Joanne Smith QC, a dispute to be resolved in separate proceedings and it was not open to the defendant to raise the valuation issue as a defence to enforcement.

The case does not challenge the decision in Grove Developments, as is it was clearly still open for the claimant to contest the value of the works in separate proceedings. However, as the case is still unreported, it remains to be seen whether there is any suggestion that a paying party could run the 'true value' argument as a defence in adjudication proceedings if the adjudication notice was sufficiently wide enough to encompass this or if they would still need to wait out the determination of the initial 'smash & grab' adjudication and pay the nominated sum before seeking to have the 'true value' determined – such payment being a pre-requisite to an entitlement to do so per Coulson J in Grove v S&T.

Regulatory Update

National Infrastructure Assessment

On 10 July 2018, the National Infrastructure Commission published the first National Infrastructure Assessment (NIA). The NIA is an assessment of the UK's infrastructure needs and will be published every 5 years. Although non-binding, the Government has committed to responding to the report within 6 months and will identify which recommendations it supports and make alternative proposals for those with which it disagrees. The NIA's recommendations include:

  • Encouraging urban growth by providing £43 billion of long-term transport funding for regional cities, while also giving cities stable five-year budgets from 2021.
  • Half the UK's power should be provided by renewables by 2030.
  • Cutting waste by introducing national rules for what can be recycled. Three quarters of plastic packaging should be recycled by 2030.
  • The Government should only develop one new nuclear power station, instead of the fleet that is currently proposed.

Revised National Planning Policy Framework Published

On 24 July 2018, the Government published the revised National Planning Policy Framework (NPPF). The document contains the economic, environmental and social planning policies for England and is a material consideration in the determination of planning applications. This is the first revision since 2012 and incorporates 85 changes which are intended to facilitate development of housing stock, whilst ensuring that new construction satisfies 21st century challenges and needs. A number of key changes are as follows:

  • Transport should be considered as part of the planning process, so that transport issues are recognised and addressed as fully as possible.
  • Plan policies should set out expectations in relation to the delivery of high quality digital infrastructure, which provides access to services from a range of providers.
  • Plans are expected to have a clear strategy for using land, making more intensive use of existing land and buildings where appropriate. LPAs should refuse applications which they consider fail to make effective use of land (in areas where there is an anticipated shortage of land for meeting identified housing needs).

The full NPPF can be accessed here.

Public Accounts Committee Report – Strategic Suppliers

Also on 24 July 2018, the House of Commons Public Accounts Committee published their report on Strategic Suppliers, the inquiry for which was announced in May this year.

Strategic Suppliers are companies designated as such by the Government and who have contracts across several Government departments worth more than £100m per year, or those deemed significant to a sector. There are currently 27 Strategic Suppliers providing services across the public sector.

The report notes that the collapse of Carillion has brought to a head concerns relating to the Government's approach in relation to contracting out public services and that outsourcing is at a significant crossroads. There are over 30 recommendations set out in the report itself and a number of conclusions. Some of these include:

  • In order to improve transparency, a standard set of contract information (to include contract value, length and KPIs plus a list of other public sector contracts held by the successful company) should be made publically available following the agreement of a contract.
  • The current procurement environment encourages Government and suppliers to place too much emphasis on price, at the expense of quality. Some companies bid at a price which would provide limited margins, expecting subsequent variations to yield reasonable returns.
  • The PAC has seen little evidence of the Government using more SMEs as direct contractors, or the measures to improve the treatment of SMEs in the supply chain.

The full report can be accessed here.

Clyde & Co 'In the News'

John Morris, Global Head of Projects and Construction, was quoted in The Construction Manager, commenting on the level of construction disputes in the UK and the methods of dispute resolution commonly utilised. View the full article here.

David Hansom, Procurement Partner, was featured in Supply Management, with his article on the European Commission's recent review of public procurement across the EU. Readers with a subscription can view the full article here.

Liz Jenkins, Partner, was quoted in Construction News, commenting on the Heathrow expansion and the fact there are still plenty of legal hurdles to overcome despite the third runway being unanimously backed by MPs late last month. Readers with a subscription can view the full article here.

Upcoming event

Off-site Manufacturing report launch

Tuesday 18 September | The Barbican Centre, Silk Street, EC2Y 8DS, United Kingdom

Click here for more information and to register.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Similar Articles
Relevancy Powered by MondaqAI
Fenwick Elliott LLP
Dentons
 
In association with
Related Topics
 
Similar Articles
Relevancy Powered by MondaqAI
Fenwick Elliott LLP
Dentons
Related Articles
 
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Registration (you must scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions