UK: Projects & Construction Law Update - June 2018

Last Updated: 12 July 2018
Article by Robert Meakin and Rebecca Evans

Most Read Contributor in UK, October 2018

CASES

Changes in making changes

Rock Advertising Limited v MWB Business Exchange Centres Limited [2018] UKSC 24

The Supreme Court has surprised everyone by doing a u-turn on anti-oral variation clauses, reversing the relatively recent position formed by the courts in 2016, which had found that a contract with anti-oral variation clauses could still be amended by the parties orally or by conduct.

In 2016, three key judgments were handed down which encouraged us all to believe that the courts would be prepared to permit variation by conduct or oral variation arguments, even where the relevant contract contained a 'no oral variations' clause. This was particularly relevant to construction contracts, where it is not uncommon for variations to take place informally or not otherwise in accordance with the requirements of the contract and, of course, for disputes to ensue. Following the 2016 decisions, it was understood that parties would be able to argue that their contract had been varied orally or by conduct, despite the presence of a 'no oral variations' clause, if:

  1. objectively, the parties could be seen to have reached the stage where they intended to vary the contract; and
  2. consideration had been provided.

We have seen this argument put forward by contractors where they have been operating in slight variance to the terms of the original construction contract (on a regular basis and without objection from the employer) and the employer has subsequently sought to enforce the strict requirements of the contract to the contractor's detriment.

One of the three 2016 cases was the Court of Appeal decision in MWB Business Exchange Centres v Rock Advertising [2016] EWCA Civ 553. That decision has now been overturned by the Supreme Court.

Although not directly related to construction contracts, the case of Rock v MWB considered 'no oral variations' clauses in the context of commercial contracts. Rock Advertising occupied office space near Marble Arch under a licence from MWB. Rock had argued that the licence agreement had been varied by a telephone conversation between the parties and that such amendment had the effect of overriding the 'no oral variation' provision. The Court of Appeal accepted this, the rationale being the need to uphold party autonomy and the importance of contracting parties' freedom to agree terms. However, the Supreme Court rejected Rock Advertising's argument on the basis that "the law should and does give effect to a contractual provision requiring specified formalities to be observed for a variation". While Lord Sumption acknowledged the importance of party autonomy, he disagreed with the Court of Appeal's approach, taking the view that:

'Party autonomy operates up to the point when the contract is made, but thereafter only to the extent that the contract allows it. Nearly all contracts bind the parties to some course of action, and to that extent restrict their autonomy. The real offence against party autonomy is the suggestion that they cannot bind themselves as to the form of any variation, even if that is what they have agreed.'

It was found that (where a 'no oral variations' clause is present in a contract) any oral variation would not be effective unless and until it is reduced to writing, or the 'no oral variations' clause is itself removed or suspended by written agreement. The rationale being that this approach fully reflects the parties' autonomy to bind themselves as to their future conduct, whilst preserving their ability to release themselves from the inhibition.

The effect of this decision on construction contracts containing the standard 'no oral variations' clause will be that any amendment to the contract will have to be made in writing, in accordance with the variation procedures in the contract. Without this, it is unlikely that a party would be able to successfully argue that a construction contract has been varied simply because the parties have been doing something a particular way for a period of time, and they may therefore face financial consequences if they are not operating in accordance with the contractual terms. The Supreme Court's decision emphasises the importance of efficient and accurate contract management throughout the duration of a project.

Read the full judgment here.

Limiting design liability under NEC

SSE Generation Limited (SSE) v Hochtief Solutions AG [2018] CSIH 26

In this recent Scottish case considering NEC2 provisions, the Inner House found a contractor liable for remedial works required due to a tunnel collapse at a hydroelectric plant, despite the existence of a clause limiting the contractor's liability for defects in the works due to its design provided the contractor could show it used reasonable skill and care to ensure compliance with the Works Information. Importantly, it was found that the collapse arose as a result of the contractor's implementation of its design – to which, it was held, the limitation of liability provision did not apply.

In December 2005, SSE Generation Limited (Employer) engaged Hochtief Solutions AG (Contractor) to design and build a hydroelectric scheme at Fort Augustus in Scotland. The scheme included an 80km tunnel and was governed by an NEC2 Engineering and Construction Contract with bespoke amendments, including Secondary Option (M) (Contract).

In April 2009, a substantial part of the tunnel collapsed. The Employer instructed the Contractor to carry out remedial works, however it refused arguing that it was not liable under the Contract. The Employer appointed third party contractors to carry out the remedial works and later issued a claim for breach of contract in the sum of £137m (being the remedial costs). The Contractor denied liability and counterclaimed for £10m (being its putative loss of profit in not carrying out the remedial works, together with additional costs incurred).

We briefly set out the relevant provisions of the Contract:

  • Clause 80.1 of the Contract set out the Employer's risks and excluded any loss or damage occurring as a result of a "Defect which existed at takeover" (the risk of which remained with the Contractor). Defect was defined in Clause 11.2(5)) as either:

    • a part of the works which is not in accordance with the Works Information; and/or
    • a part of the works designed by the Contractor which is not in accordance with the applicable law or the Contractor's design which has been accepted by the Project Manager.
  • Clause 6.3.2 of the Works Information required the Contractor to "provide a reliable service without requirement for major refurbishment or significant capital expenditure".
  • Clause 81.1 provided that, until the Defects Certificate, risks that were not carried by the Employer were carried by the Contractor. Pursuant to Clause 83, each party indemnified the other against claims that were due to an event that was at its risk.
  • Option M excluded the Contractor's liability for defects arising from its design, provided the Contractor used reasonable skill and care to ensure that the design complied with the Works Information.

The Outer House (court at first instance) found that the tunnel collapse was caused by insufficient shotcrete and rock bolts deployed in poor rock conditions but that the Contractor was not in breach of its duty of care in the construction of the tunnel, partly because the terms of Option M operated to exclude its liability.

For the commercial judge, the collapse was an Employer's risk event: it did not arise from a "Defect that existed at take-over" and the Employer was only entitled to low availability damages in accordance with the Contract, for the Contractor's failure to return to remedy the works. The Employer filed a reclaiming motion to the Inner House and the Contractor cross-appealed.

The Inner House allowed the reclaiming motion and rejected the cross-appeal two to one (with the Lord President dissenting). As to whether the tunnel collapse was the consequence of a Defect under the Contract, Lord Menzies and Lord Glennie held that:

  • the cause of collapse was a Defect which existed at take over: as the works had not been carried out in accordance with the Works Information and the collapse therefore satisfied the first limb of the definition of Defect; and
  • the Contractor's implementation of its design was also not in accordance with a "design which had been accepted by the project manager" (the design had obliged the Contractor to apply steel rib support to any uncovered erodible rock, which was not adhered to) and thus the second limb of the Defect definition was also satisfied.

Accordingly, as a Defect existed at take-over, the collapse could not constitute an Employer's risk under Clause 80.1. As Clause 81.1 provided that any risks not carried by the Employer were carried by the Contractor. The Inner House went on to consider whether or not the Contractor was protected by the limitation wording in Option M.

Whilst the Court recognised that Option M provided a limitation on the Contractor's liability for defects arising from its design, it was irrelevant to the tunnel collapse, which was caused by the implementation of that design. The Option M limitation could not therefore apply, irrespective of whether or not the Contractor had exercised reasonable care and skill in its implementation.

Given the lack of English cases considering NEC wording, this case will likely prove persuasive for future English Court decisions (particularly given that the NEC2 wording relevant to this issue is the same as that contained in NEC3 contracts and substantially the same as that contained in NEC4 contracts (see X15.1 in both)). Contractors might therefore note that these limitation provisions are likely to be interpreted as only operating to limit the contractor's liability for loss/damage caused by its design and not offering protection where the loss/damage was caused by the implementation of that design, irrespective of the reasonable care and skill deployed.

Read the full judgment here.

Enforcing judgment debts and the appropriateness (or not) of creditor's petitions

Victory House General Partner Ltd v RGB P&C Limited [2018] EWHC 1143 (Ch)

A contractor was unsuccessful in its attempt to wind up the employer company for failing to pay a judgment debt following enforcement of an adjudication decision. The High Court confirmed that where a respondent to a winding up petition could show it had a bona fide cross-claim on substantial grounds, as a general rule and where no special circumstances exist, the petition should be dismissed. Interestingly, the employer relied on the recent case of Grove v S&T(UK) in successfully arguing its position...

Payment issues and disputes are prevalent in the construction industry, with parties often employing various methods to ensure cash flow or otherwise recover disputed sums. This case shows that, in practice, even seemingly simple methods of debt recovery are not always straightforward.

As a refresher, and at a high level, in order to successfully petition to wind up a company, a creditor must be owed at least £750 and show that the company is unable to pay its debts within the meaning of section 122(f) of the Insolvency Act. This may be evidenced simply by the fact that the debt remains unpaid 21 days following the service of a statutory demand. The winding up petition must then be filed at court and the appropriate notice given in the Gazette. The winding up petition will then be set down for hearing. Setting aside procedural issues, the court will generally dismiss a winding-up petition in cases where the creditor has a collateral purpose / ulterior objective, the debt is bona fide disputed on substantial grounds or the company has a genuine right to set-off or cross-claim. For these reasons, it is important that claimants make genuine enquiries of the company and properly consider whether a winding up petition is the appropriate course of action in the circumstances.

In this case, the contractor and the employer were in dispute as to sums payable from the employer to the contractor. Two adjudications followed. The first adjudication resulted in a judgment against the employer, which it failed to pay.. However, it subsequently paid in excess of £8.5m to the contractor on account. The second adjudication wrapped up the value of all the works to date (including that from the first adjudication) but resulted in a decision that the works were valued at just over £7m. Consequently, the sum due was nil. The contractor subsequently petitioned to wind up the company following non-payment of the judgment debt from the first adjudication, while the company submitted that, if the judgment debt was paid, they would immediately become entitled in the law of restitution to be repaid that sum, resulting in a bona fide cross-claim. On this basis, the company argued that it would be inappropriate to wind it up by reason of non-payment of the judgment debt.

The company relied on the recent case of Grove v S&T (UK) where Coulson J held that, provided an employer had paid an amount determined as payable in an adjudication, it could subsequently bring an adjudication as to the 'true value' of the relevant works and, where the figure determined in the second adjudication was smaller than the first, the employer would be entitled to ask for repayment of the figure appropriately calculated. The company submitted that, in its case, while there had not been a second adjudication on the same interim certificate, the second adjudication on the later certificate subsumed the earlier one. The second adjudicator had made a determination as to the 'true value' of the works up to that point and determined no sum was payable. The argument followed that if the employer paid the judgment debt 'there would immediately rise up, upon payment, a cause of action for repayment of that figure'.

Mr Justice Morgan accepted this and applied Re Bayoil SA [1999] 1 WLR 147 which confirmed that the established rule about disputed debts applied to disputed cross-claims also (where they exceed the petition debt). He did not accept the contractor's argument that Re Bayoil did not apply because it dealt with an arbitration award instead of a judgment debt and was not persuaded there were any special circumstances to take this case outside the general rule which he stated was 'an important rule which should be consistently applied and not departed from too readily'.

This case is a reminder for claimants to always consider whether or not particular courses of action to recover disputed sums are appropriate in the circumstances. While not dealt with in this judgment, a potential risk for the claimant of having a petition dismissed on the grounds discussed is that the claimant may find itself liable for the company's costs on an indemnity basis. Commencing winding up proceedings should generally be regarded as a last resort and not simply used as a means of enforcing a debt.

Read the full judgment here.

REGULATORY UPDATE

Government funding the removal of unsafe cladding on social housing

On the 16 May 2018, the government announced that it will fund the removal of unsafe cladding currently used in social housing. The estimated cost of this is £400 million.

The announcement specifies that a fund will be established where local authorities and housing associations may apply for funding to finance the reasonable costs of removing and replacing unsafe cladding currently present in social housing.

The announcement comes following the Grenfell tragedy and pre-empted the final report of the Hackitt review of Building Regulations and Fire Safety (see further below). It also follows last year's offer to provide similar financial support to social landlords. Since then the government has consulted with social landlords who have voiced concern about prioritising the provision of important services, repairs, maintenance and investment in new homes. This additional source of funding should alleviate, at least in part, these difficulties currently faced by social landlords.

It remains to be seen how the fund will be accessed in practice and the criteria that will determine access to funds.

Building a Safer Future, Independent Review of Building Regulations and Fire Safety: Final Report

On 17 May 2018, Dame Judith Hackitt's long anticipated independent review of Building Regulations and Fire Safety (Report) was finally published.

The Report focuses on residential buildings of 10 or more stories and recommends multiple changes, including:

  1. a revised statutory framework setting out clearer responsibilities and accountability for duty holders;
  2. greater powers of enforcement and penalties for breaches of fire safety obligations including a new mandatory incident reporting mechanism; and
  3. a new a Joint Competent Authority (JCA) to oversee enforcements

It is recommended that the JCA consist of the Health and Safety Executive, fire and rescue authorities and local authority building standards.

The Report suggests that duty holders consult the JCA at three "Gateway Points": i) the planning permission stage; ii) the full plan approval stage; and iii) the completion stage. At each of these stages, duty holders would be required to satisfy strict criteria demonstrating their understanding and implementation of building safety management before they could continue to the next phase of the project.

Importantly, the Report suggests that the time limit for taking action against a duty holder should increase from 2 years to 5-6 years from the time of the offence.

The report is clear that the framework suggested will need to be implemented, in part at least, by primary legislation. Nevertheless, the Report encourages the industry to embrace these recommendations immediately and for businesses impacted to consider how the recommendations can be implemented in the soonest possible time.

Click here to view the Report.

RICS publishes new draft Appointment Forms

RICS publishes consultation versions of its 2018 suite of standard form consultant's appointments.

The Royal Institute of Chartered Surveyors (RICS) has published consultation versions of what is intended to be its next suite of standard form consultant's appointments. The consultation closes on the 15 June 2018, with the intention that the finalised forms be published in the Autumn.

The intended 2018 suite of documents are set to replace the current 2008 suite of documents. The documents to be included in the new 2018 suite largely mirror those of the 2008 suite but have some important additions. The documents proposed in the 2018 suite include:

  • a standard form of consultant's appointment for use in construction projects of any size and value;
  • a short form consultant's appointment, likely to be used for more straight forward projects of smaller values;
  • a short form consultant's appointment for designated services (this is a new addition to the suite of documents and is intended for specialist services which may be non-construction , for example, expert witness services); and
  • thirteen scope of services documents (compared to the 6 in the 2008 suite).

The modernisation of the documents looks to take into account the raft of changes to legislation and jurisprudence since the previous suite of documents, including the Construction (Design and Management) Regulations 2015 and the Bribery Act 2010, as well as changes in custom and practice within the industry.

The consultation page can be accessed here.

CLYDE & CO 'IN THE NEWS'

Anthony Albertini, partner in our construction team, was featured in Construction News, with his article entitled 'Crackdown on poor payment is a half-baked policy' which commented on the recent announcement by the Cabinet Office of its plans to exclude suppliers with poor payment practices from winning major government contracts. Readers with a subscription can view the article here.

A growing team: We continue to grow our regional presence through the hire of Peter O'Brien (partner), Kate Lister (senior associate) and Josh Roberts (associate) who now form our Bristol based Projects & Construction Team. The team specialises in construction dispute resolution, representing clients in a range of dispute forums in the UK and overseas.

Technology and off-site manufacturing survey

In recent years the use of technology, and off-site manufacturing in particular, has captured the construction industry's attention. It is now heralded by some as the potential 'silver bullet' to tackling the chronic problem of low productivity - but perceived barriers remain, which are inhibiting widespread adoption.

Clyde & Co is keen to help our clients navigate these barriers. With this in mind, we're carrying out a global survey to better understand the direction of travel and the industry concerns.

We'd be very keen to hear the views of your organisation.

We would appreciate it, if you could complete the survey by Friday 15 June. It should take no longer than five minutes.

Please find the survey here: https://www.research.net/r/NQQ6ZW7

Upcoming events

Firm Foundations – Unfair Payment Practices

Thursday 28 June | The St Botolph Building, 138 Houndsditch, London, EC3A 7AR

Click here for more information and to register

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
 
In association with
Related Topics
 
Related Articles
 
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Registration (you must scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions