UK: The New FIDIC Yellow Book Dispute Resolution Procedure: Part 1 - the Proposed New Dispute Resolution Mechanism

Last Updated: 2 May 2017
Article by Robbie McCrea

Introduction

In December 2016,  FIDIC presented a pre-release version of its second edition of Conditions of Contracts for Plant and Design Build ("the Proposed 2017 Yellow Book") which is due to be published during the course of 2017.1 As expected, FIDIC has made substantial amendments to the dispute resolution provisions in the 1999 Yellow Book, and it has addressed the provisions relating to "binding but not-final" Dispute Adjudication Board ("DAB") decisions which have been the cause of persistent dispute since the 1999 Yellow Book was released.

However, rather than scale back following the controversy caused by the binding but not-final DAB decision, and the severe consequences to contractors that have in many instances resulted, FIDIC has chosen to affirm this direction. The Proposed 2017 Yellow Book therefore retains the same core structure of the DAB as a mandatory pre-condition to arbitration, including that non-final DAB decisions must be promptly complied with, and it has expanded this concept through the inclusion of a similar mandatory procedure of binding but not-final Engineer determinations. 

The Proposed 2017 Yellow Book offers a refurbished dispute resolution mechanism, which includes some helpful and much needed revisions to its predecessor, and introduces some useful new provisions. It is an ambitious dispute platform and will, without question, be subject to dispute and debate. At its best, it offers both parties the ability to obtain fast and inexpensive relief, with three tiers of binding determinations designed to prevent the need for arbitration. At its worst, it places two-tiers of mandatory determinations in the way before a party can begin to obtain a final binding decision in arbitration.

Parties will need to think carefully about whether a three-tiered system of determinations is suitable for their needs. Key issues are whether or not these provisions do in fact offer the system of relief promised, including how non-final determinations of the Engineer and DAB are likely to be treated in the jurisdiction that the contract is based as well as under the governing law of the contract, and attempting so far as possible to agree in advance between the Parties and Engineer as to how this mechanism will work.

This paper will address the Proposed 2017 Yellow Book dispute resolution provisions in two parts, with Part 1 included in this edition of International Quarterly, and Part 2 to be published in the next edition. The parts are as follows:

Part 1 will set out the key provisions of the proposed new dispute resolution mechanism in the 2017 Yellow Book, and assess these against the 1999 Yellow Book provisions. 

Part 2 will address the merits of including a DAB, and Engineer's determinations in their proposed new form, as a pre-condition to arbitration.

Part 1 – the proposed new dispute resolution mechanism

Background

The dispute mechanism in the Proposed 2017 Yellow Book follows on from a worldwide trend of promoting dispute avoidance over arbitration.

The 1999 Yellow Book introduced the now infamous Dispute Adjudication Board into its contracts for the first time, which replaced the Engineer's binding decision in the 1987 FIDIC Conditions of Contract as a pre-condition to arbitration.  The 1999 Yellow Book still requires the Engineer to make a determination as the first step in the claims process, albeit under a reduced timescale.

In the 2008 Gold Book, FIDIC expanded the role of the DAB further by defining it as a Dispute Avoidance / Adjudication Board, and including a new clause 20.4 "Avoidance of Disputes" which permits the parties to agree to request that the DAB provide informal assistance with any issue or disagreement between the parties, which shall not bind either party should they proceed to obtain a formal determination. 

The Proposed 2017 Yellow Book goes further again. Like the 2008 Gold Book, the DAB is defined as a "Dispute Avoidance / Adjudication Board", and it is empowered to provide informal assistance. In addition, the role of the Engineer has been increased to play a facilitative role and to issue binding determinations that will become final unless an NOD is issued.

The dispute resolution mechanism compared

As described above, the Proposed 2017 Yellow Book follows the same core structure as the 1999 Yellow Book, which can be broadly divided into the following constituent parts:

  • Making a claim;
  • The role of the Engineer;
  • Avoidance of disputes (new);
  • The DAB;
  • Amicable settlement; and
  • Arbitration.

These are each discussed and assessed against the 1999 Yellow Book provisions below.

Making a claim

The 1999 Yellow Book includes separate provisions for the Employer and Contractor to make a claim, with a notable difference being that Contractors must make their claim within 28 days of becoming aware of the event giving rise to the claim, and provide a fully detailed claim within 42 days (Sub-clause 20.1), whereas Employers need only provide notice "as soon as reasonably practicable (Sub-clause 2.5)." 

The Proposed 2017 Yellow Book includes one consolidated clause for claims, Sub-clause 20.2, under which both parties must progress their claims within the 28 and 42 day periods under Sub-clause 20.1 of the 1999 Yellow Book.  It also includes a new procedure enabling a waiver of these time-limits in certain instances2, which is clearly designed to provide some clarity and a mechanism for determining when a claim will be time-barred.

The role of the Engineer

The role of the Engineer has been expanded under the Proposed 2017 Yellow Book, including new functions and obligations. In relation to claims, the Engineer must3:

  • Consult with the parties to attempt to reach agreement, and if no agreement is reach within 42 days;
  • Make a "fair determination" within a further 42 days.

Under the 1999 Yellow Book4, the Engineer was required to consult and ultimately make a fair determination within just one 42 day period.  Under both the Proposed 2017 Yellow Book and the 1999 Yellow Book, the Engineer may request that further information be provided before making a determination. 

The Proposed 2017 Yellow Book also includes an express requirement that the Engineer act "neutrally" in discharging the above duties5. Although many would consider that neutrality is already encompassed as a matter of common sense in the obligation to issue a "fair determination," and this has been confirmed to be the case as a matter of English law,6 the position is not so clear in all jurisdictions and the addition of an explicit obligation of neutrality is a helpful addition.

Furthermore, whether both the Proposed 2017 and 1999 Yellow Books provide that the Engineer's determinations shall be binding on the parties unless and until revised by the DAB or in arbitration7, the Proposed 2017 Yellow Book goes further to state that unless either party issues an NOD with the agreement or determination issued by the Engineer within 28 days, that agreement or decision shall become final and conclusive8. Parties will therefore need to be conscious of these time limits.

The Proposed 2017 Yellow Book has therefore extended the Engineer's role in claim resolution from a minimum 42 days to 84 days, with the prospect of its determination becoming final if neither party issues a valid NOD. The new provisions do not state how a final Engineer's determination is to be enforced, although we expect the intention is that a party would obtain a DAB decision on the failure to comply followed by an arbitral award pursuant to Sub-clause 21.7 (discussed further below).

Avoidance of Disputes

A new "Avoidance of Disputes" provision has been added which permits the parties to jointly ask the DAB to informally discuss and/or provide assistance with any issue or disagreement9. The parties will not be bound to act on any advice given in this process.  This provision is taken from the 2008 Gold Book10, and it is in keeping with FIDIC's promotion of dispute avoidance, but its practical effect is questionable.

The issue is that the DAB is, by this clause, being asked to act as a kind of mediator, whereas in the following clause, it must act as adjudicator, and these functions are not usually compatible. A mediator will often become privy to confidential and other commercial considerations of the parties, and is there to facilitate settlement, and this is plainly not compatible with the role of adjudicator who must decide the parties' legal rights and obligations. This dual role scenario has already been met with some concern in the UK11.

The DAB

The DAB procedure under the Proposed 2017 Yellow Book retains its core aspects, namely that a DAB must issue its decision within 84 days of a dispute being referred to it, and that decision shall be immediately binding upon the parties who shall promptly give effect to it. However, the new provision includes a number of revisions designed to clarify and assist in enforcing these obligations, including12:

  1. DAB decisions are now expressly binding on the Engineer;
  2. The Parties and Engineer must comply with the DAB's decision "whether or not a Party gives a NOD with respect to such decision under this Sub-clause"; and
  3. If the DAB awards payment of a sum of money, that amount shall be immediately due and payable after the payer receives an invoice, without any requirement for certification or notice. In addition, the DAB may require an appropriate security to be issued for payment of the sum awarded. 

Furthermore, Sub-clause 21.7 provides that if either party fails to comply with a DAB decision, whether final or not-final, the other party may refer the failure itself directly to arbitration pursuant to Sub-clause 21.6. 

The above provisions were intended by FIDIC to have already been provided for in the 1999 procedure, but which as many contractors have painfully found out, the 1999 wording was not so clear and has been the subject of fervent debate since those conditions were released. This debate is captured in the Persero series of cases in Singapore, which ran for eight years on the issue of whether a non-final DAB decision issued under Sub-clause 20.4 could be enforced summarily by an arbitral award13.

Under both the 1999 and Proposed 2017 wording, either party can prevent a DAB decision from becoming final by issuing an NOD within 28 days. However, the Proposed 2017 wording adds that if no arbitration is commenced within 182 days after the NOD is issued, then that NOD shall be deemed to have lapsed and be no longer valid. This will allow DAB decisions to become final where arbitration is not pursued, and that is helpful; however, where finality is relevant to enforcement, this provision may also be subject to dispute. For instance, if a party commences arbitration but then allows it to lapse, will a new 182 day period commence or does that prevent a non-final DAB from ever becoming final? 

Finally, the new wording includes a revised provision for when no DAB is in place, which now permits the parties to proceed directly to arbitration if a dispute arises and there is no DAB in place14.  This is a potentially important revision compared to its equivalent in the 1999 Yellow Book, Sub-clause 20.8, which is headed "Expiry of Dispute Adjudication Board's appointment15." 

The 1999 Yellow Book wording was subject to debate before the Swiss Supreme Court16 and the UK Technology and Construction Court,17 and both courts found that the DAB was a mandatory pre-condition to arbitration, and that Sub-clause 20.8 would only be used in the exceptional situation where the mission of a standing DAB has expired before a dispute arises between the parties, or other limited circumstances such as the inability to constitute a DAB due to the intransigence of one of the parties. Although the Swiss Case ultimately permitted the DAB to be avoided after the Contractor had spent over 18 months attempting to have it constituted, the English case refused to allow the litigation to proceed until the DAB procedure was completed.

Under the Proposed 2017 Yellow Book, parties will be able to skip the DAB procedure if it is not in place when the dispute arises, although once the DAB has been set up or once the parties begin the process of setting up a DAB, no matter how frustrating that process may be, the DAB will become mandatory and the process will not be able to be abandoned. 

Amicable settlement

The mandatory amicable settlement period has been reduced from 56 days to 28 days under the Proposed 2017 Yellow Book18. Furthermore, where either party fails to comply with a DAB decision, that failure may be referred directly to arbitration and the amicable settlement period will not apply19. This clarifies that the parties' obligation to "promptly" comply with a DAB decision means in less than 28 days.

Arbitration

The arbitration provisions for non-final DAB decisions are effectively the same under both contracts, namely that where an NOD has been issued, either party may refer the dispute to be finally decided in international arbitration.20 The Proposed 2017 Yellow Book also expressly permits an arbitral tribunal to take account of any non-cooperation in constituting the DAB in its awarding of costs.

As noted above, the new wording includes an expanded Sub-clause 21.7 (Sub-clause 20.7 of the 1999 Yellow Book), which permits any failure to comply with a DAB decision, whether final or not-final, to be referred directly to arbitration. In relation to non-final DAB decisions, the right to enforcement by interim relief or award is subject to the fact that the merits of the dispute are reserved until resolved in a final arbitral award. Although this revised contractual clarification/position will be welcomed by contractors, there are still likely to be challenges in many jurisdictions as to whether the enforcement of non-final DAB decisions via an arbitral award is supported by the local or governing laws of the contract. 

Conclusion

The proposed new dispute procedure provides some useful revisions which address fairly well some of the problem areas of the 1999 Yellow Book, and which are aimed at promoting compliance with the pre-arbitration steps. These include better defined responsibilities and accountability for the Engineer, and revisions to the DAB and arbitration provisions which should avoid the perpetual 1999 Yellow Book disputes as to whether an NOD cancels the binding effect of a DAB decision, and whether a non-final DAB decision can be summarily enforced in arbitration. 

The new procedure also expands the pre-arbitral steps, including a mandatory additional 42 day period in the Engineer's determination, plus a further 28 days to issue an NOD. To the extent that non-final determinations by the Engineer and DAB are able to be enforced, including under the Governing law of the contract, then the new wording will be welcomed by contractors as providing for quick relief and something like the security of payment regime that were intended by FIDIC in the 1999 Yellow Book21.

However, to the extent that these non-final determinations are not able to be enforced then, except in limited circumstances (for instance, where no DAB is in place at the time of dispute), parties may be required to go through an even longer mandatory claims procedure than under the 1999 Yellow Book before they are able to commence an arbitration that will give them final and enforceable relief. Parties should therefore think carefully as to whether this mechanism, in whole or part, is suitable for their particular needs.

In Part II of this paper, which will be presented in the next edition of International Quarterly, we will discuss the merits of including these mandatory pre-arbitral procedures.


  • 1. It may be that the second edition of the Yellow Book that is eventually published contains some differences compared with the Proposed 2017 Yellow Book discussed in this article and so this article should be read with this possibility in mind.
  • 2. Sub-clause 20.3 of the Proposed 2017 Yellow Book.
  • 3. Sub-clause 3.7 of the Proposed 2017 Yellow Book.
  • 4. Sub-clauses 3.5 and 20.1 of the 1999 Yellow Book.
  • 5. Sub-clause 3.4 of the Proposed 2017 Yellow Book.
  • 6. Per the Court of Appeal in Amec Civil Engineering Limited v Secretary of State for Transport [2005] CILL 2288.
  • 7. Sub-clauses 3.7.4 and 3.5, respectively.
  • 8. Sub-clause 3.7.5 of the Proposed 2017 Yellow Book.
  • 9. Sub-clause 21.3 of the Proposed 2017 Yellow Book.
  • 10. The FIDIC Guide to the Gold Book states that: "Prevention is better than cure, and the DAB is entrusted also with the role of providing informal assistance to the Parties at any time in an attempt to resolve any agreement."
  • 11. For instance, in Glencot Development and Design Co Ltd v Ben Barrett & Son (Contractors) Ltd, HHJ LLoyd QC commented that the conduct of the adjudicator meant that this was a case of "apparent bias" in that he appeared to lack impartiality, having been privy to a number of without prejudice offers and some rather heated discussions in his capacity as mediator.
  • 12. Sub-clause 21.4 of the Proposed 2017 Yellow Book.
  • 13. A summary of the Persero series is set out in this article
  • 14. Sub-clause 20.8 of the Proposed 2017 Yellow Book.
  • 15. Sub-clause 20.8 of the 1999 Yellow Book.
  • 16. Decision 4A_124/2014
  • 17. Peterborough City Council v Enterprise Managed Services Limited [2014] EWHC 3193 (TCC).
  • 18. Sub-clause 21.5 of the Proposed 2017 Yellow Book.
  • 19. Sub-clause 21.7 of the Proposed 2017 Yellow Book.
  • 20. In Sub-clause 20.6 of the 1999 Yellow Book and Sub-clause 21.6 of the Proposed 2017 Yellow Book.
  • 21. See for instance, PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2015] SGCA 30 at paragraphs 70 and 71.

International Quarterly is produced quartely by Fenwick Elliott LLP, the leading specialist construction law firm in the UK, working with clients in the building, engineering and energy sectors throughout the world.


The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Robbie McCrea
 
In association with
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.