UK: The Brand New Law On Liquidated Damages

Last Updated: 18 December 2015
Article by Lisa Kingston

This article considers the law of penalties in the construction context; the appeal in each of Cavendish Square Holdings v Makdessi and ParkingEye Limited v Beavis; the decision of the Supreme Court in the conjoined appeals and how liquidated damages practice is likely to change in the wake of the Supreme Court's decision.

On 4 November 2015, a seven-strong bench of the Supreme Court1 considered the law of penalties for the first time when it handed down its decision in the conjoined appeals in Cavendish Square Holdings BV (Appellant) v Tatal El Makdessi (Respondent). The decision (which reconsiders the law on penalty clauses in relation to commercial contracts between sophisticated parties (in the Cavendish Square Holdings v Makdessi appeal), and at a consumer level under the Unfair Terms in Consumer Contracts Regulations 1999 (in the ParkingEye Limited v Beavis appeal)), is one of the most important common law decisions in a century in the construction law context, since it impacts upon the law relating to liquidated damages.

The law of penalties in the construction context

Most construction contracts contain a provision for liquidated damages in the event of certain specified breaches of contract by the contractor,2 and the level of liquidated damages is agreed by the parties prior to the contract being entered into. Prior to the decision of the Supreme Court in Cavendish Square Holdings BV (Appellant) v Tatal El Makdessi (Respondent), in order to be recoverable, the predetermined level of liquidated damages had to represent a genuine pre-estimate of the employer's likely loss should the specified breach occur. There was no requirement for the employer to prove that it had actually suffered the loss provided for by the liquidated damages provision, and the employer would still be entitled to the amount of liquidated damages stipulated by the contract even if its actual loss was lower. This all sounds too good to be true from the employer's perspective, but there was a catch: if the level of liquidated damages did not represent a genuine pre-estimate of the employer's loss, it was open to challenge by the contractor further down the line on the basis it represented a penalty clause which is not recoverable as a matter of English common law.   

The common law on penalty clauses was established a little over 100 years ago by the decision in Dunlop v Matthew Tyre Co Limited v New Garage Motor Co Limited (1915) AC 79, which laid down various principles to help distinguish liquidated damages from penalties. Whilst the principles set out in Dunlop v Matthew Tyre Co Limited v New Garage Motor Co Limited have been refined by the courts since 1915, the law on liquidated damages has historically been evolutionary as opposed to being the subject of drastic change.

The traditional test under the old law was that provided the employer had made a genuine attempt to pre-estimate its loss (rendering the clause compensatory), the courts would be unlikely to regard it as a penalty. However, if the amount of liquidated damages bore absolutely no resemblance to the loss, was extravagant and unconscionable, and was intended to deter a breach of contract, then the court would be more willing to construe it as an unenforceable penalty.3

The Cavendish Square Holdings v Makdessi appeal

The facts

In Cavendish Square Holdings v Makdessi,4 Mr Makdessi agreed to sell a controlling stake in what was to become the largest advertising group in the Middle East to Cavendish under the terms of a share sale agreement ("the Agreement"). The Agreement contained restrictive covenants requiring Mr Makdessi not to become involved in a competing business in default of which (i) he would forfeit the final two instalments of deferred consideration that were to be payable to him by Cavendish for his shares, and (ii) he would be required to transfer all his remaining shares to Cavendish at a price which excluded any goodwill value. Mr Makdessi accepted he had breached the restrictive covenants, but he denied the clauses were enforceable on the basis they were penalties.

Decision at first instance

Mr Justice Burton found that the purpose of the restrictive covenants was not to deter a breach of contract, but to adjust the consideration between the parties. Cavendish was entitled to assess the value a breach of the restrictive covenants by reference to the greatest loss that could conceivably be proved to have followed from the breach, as any breach could have a very substantial impact on the goodwill of Cavendish's business. Accordingly, the clauses were not found to be penalty clauses.

Decision of the Court of Appeal

In reaching its decision, the Court of Appeal reviewed various authorities on the law on penalties and commented that the early cases (starting with Dunlop v Matthew Tyre Co Limited v New Garage Motor Co Limited) had established that the purpose of a penalty clause was to deter breaches of contract, and a clause would only be a penalty if it was "extravagant" and "unconscionable". The Court of Appeal noted that the modern cases take a more flexible approach and focus on the dominant purpose of clauses: if the dominant purpose is to deter a breach of contract and the charge is commercially justified, then it will not be rendered a penalty clause. 

The Court of Appeal overturned the decision of Mr Justice Burton and agreed with Mr Makdessi that the two clauses were unenforceable penalty clauses. The provisions were not a genuine pre-estimate of loss, but were extravagant and unreasonable compared with the likely damage arising from the breach; they also had no commercial justification. As a result, they were unconscionable, intended to deter a breach of contract, and penal.  

Cavendish appealed to the Supreme Court, the issues before which were: (i) whether the rule against penalties applies to commercial contracts between sophisticated parties with equal and substantial bargaining power; (ii) if the rule does apply to such contracts, whether the penalty clauses are within the scope of the rule; and (iii) if the clauses are within the scope of the rule, whether they are penalties.

The ParkingEye Limited v Beavis appeal

The facts

In ParkingEye Limited v Beavis, Mr Beavis drove into the Riverside Retail Park car park in Chelmsford that was managed by private car park operator, ParkingEye. The car park displayed prominent signs at its entrance and on noticeboards within the car park advising there was a maximum stay of two hours, after which time a parking charge of £85 would apply (that would reduce to £50 if paid within 14 days). Mr Beavis overstayed the maximum stay by one hour, as a result of which he was charged £85. He refused to pay the £85 on the basis that the clause was a penalty and was therefore unenforceable.    

Decision at first instance

Judge Moloney QC found in favour of ParkingEye and held that a motorist who parked in the car park did so on the terms and conditions at the entrance and on the noticeboards, which represented the contract between ParkingEye and Mr Beavis. The contract included an obligation to leave within two hours, in default of which there was an agreement to pay the £85 charge. The judge acknowledged that the charge had the characteristics of a penalty as ParkingEye did not suffer any identifiable financial loss as a result of Mr Beavis' breach.

ParkingEye had a back-to-back contract with the owners of the car park that provided for: (i) an initial two-hour free period; (ii) ParkingEye to pay a fixed weekly charge to the owners; and (iii) ParkingEye to retain any £85 charges it recovered from motorists parking in the car park. The charges were used to fund the operating costs of the car park, weekly payments to the owner of the car park, and to generate profit for ParkingEye; ParkingEye's business model was therefore reliant upon motorists breaching the two-hour free period.

Judge Moloney QC found that the predominant purpose of the £85 charge was to deter motorists from breaching the two-hour free period (and therefore the contract), which would at first glance render it a penalty. However, the charge was commercially justifiable, it was not improper or excessive in amount, nor was it unfair pursuant to the Unfair Terms in Consumer Contract Regulations 1999 ("UTCCR"). It was accordingly upheld.

Mr Beavis appealed to the Court of Appeal. His appeal centred on whether (i) the £85 charge was unenforceable at common law on the basis it was a penalty; and (ii) the charge was unfair (and therefore unenforceable) under the UTCCR. 

Decision of the Court of Appeal

The Court of Appeal followed the first instance court's approach of examining the £85 charge having regard to the actual loss suffered; the deterrent effect of the clause; and whether it was justifiable commercially in reaching a conclusion as to whether the clause was extravagant and unconscionable under Dunlop v Matthew Tyre Co Limited v New Garage Motor Co Limited.

The court held that the penalty charge was not a genuine pre-estimate of loss; it was aimed at deterring motorists from overstaying the two-hour permitted period (i.e. deterring a breach of contract); it was not extravagant or unconscionable; and crucially, it was justifiable for both commercial and social reasons. The £85 charge was therefore upheld.

Mr Beavis (supported by the Consumers' Association as intervener) appealed to the Supreme Court.

Decision of the Supreme Court in the conjoined appeals

The Supreme Court was unanimous that the doctrine of penalties should not be abolished, but their lordships rejected the traditional test set down in Dunlop v Matthew Tyre Co Limited v New Garage Motor Co Limited that a clause will be a penalty if it is not a genuine pre-estimate of loss and is extravagant or unconscionable, or if its purpose is to deter a breach of contract. The majority5 of the Supreme Court held that the correct approach in commercial cases was to have regard to the nature and extent of the innocent party's (e.g. the employer's) interest in the performance of the obligation that was breached as a matter of construction of the contract.

The test, formulated by the majority, is whether the clause in question is:

"...a secondary obligation which imposes a detriment on the contract-breaker out of all proportion to any legitimate interest of the innocent party in the enforcement of the primary obligation. The innocent party can have no proper interest in simply punishing the defaulter. His interest is in performance or in some appropriate alternative to performance. In the case of a straightforward damages clause, that interest will rarely extend beyond compensation for the breach, and we therefore expect that Lord Dunedin's four tests would usually be perfectly adequate to determine its validity. But compensation is not necessarily the only legitimate interest that the innocent party may have in the performance of the defaulter's primary obligations."

The Supreme Court went on to explain the practical application of the test in terms that a penalty clause whose purpose is to punish the contract breaker is likely to be an unenforceable penalty clause. On the other hand, a clause that is intended to deter a breach of contract is less likely to be a penalty clause, even if it does not represent a genuine pre-estimate of loss. In order to determine whether or not a clause is a penalty, the key is to consider whether the liquidated damages clause is out of all proportion to the employer's legitimate interest in enforcing the contractor's obligations under the contract. If it is, it will be penal and unenforceable.

Applying this new test to the facts, the Supreme Court unanimously held in the Cavendish Square Holdings v Makdessi appeal that the clauses in question were not penal. The clauses were primary obligations under the contract, (as opposed to secondary obligations that only come into play once a breach of contract occurs (i.e. an obligation to pay liquidated damages if the works are delayed)), as they provided for an adjustment to the purchase price that was equivalent to other primary price calculation clauses in the contract which meant the penalty rule was not engaged. Further, the clauses were justified commercially by Cavendish's legitimate interest in protecting the goodwill of the business, and the parties were the best judges of how that interest should be reflected in the contract.

In the ParkingEye Limited v Beavis appeal, the Supreme Court held that whilst the £85 charge was a secondary obligation which was intended to deter motorists from a breach of contract (i.e. overstaying), it was not a penalty. This was so because not only ParkingEye, but also the car park owner had a legitimate commercial interest in charging motorists who overstayed which extended beyond the recovery of any financial loss. The interest of the car park owner was the provision and efficient management of customer parking for the retail outlets; the interest of ParkingEye was income from the £85 charge which met the running costs of what was considered by the Supreme Court to be a legitimate commercial scheme, plus a profit margin. The reasoning behind the imposition of the charge was entirely reasonable, and because it was in proportion to ParkingEye and the car park owners' commercial interests, it was not found to be penal.

Practice points

  • Liquidated damages are secondary obligations and are in principle caught by the new rule for penalties.
  • The Supreme Court made it clear that as a general rule, if a liquidated damages clause has been negotiated in a commercial contract made between two parties of comparable bargaining power, and has survived scrutiny by the parties and their legal advisers, then there will be a strong initial presumption that the clause is not out of all proportion to the employer's legitimate interests in timely completion. This is the case even if it is penal in its nature and impact; it is intended to deter a breach of contract; and it is not representative of any actual financial loss the employer may have suffered.
  • Going forward, reputational issues, goodwill, the interests of third parties, and other losses that cannot be easily quantified will be able to be taken into account in determining the level of liquidated damages. These losses will fall under the banner of commercial "interests".  
  • If the employer seeks a level of liquidated damages that does not appear to you to be commensurate to the commercial impact of the works being delayed, then the liquidated damages clause may be worth challenging on the basis it is unenforceable.
  • To mount a challenge to a liquidated damages clause (and also before you enter into any new contracts), ask the employer for documentary proof of the legitimate commercial interest to which the liquidated damages clause allegedly relates. If the documents provided appear to suggest that the liquidated damages provision does not represent a reasonable and proportionate protection of the employer's legitimate commercial interest in the works being delayed, then you should resist, or otherwise renegotiate the level of liquidated damages on the basis that it is out of all proportion to the employer's legitimate interests in timely completion.
  • If you are unable to challenge your liquidated damages provision, you may be able to argue that: the employer is responsible for the delay; there has been a breach of condition precedent by the employer (i.e. the employer has failed to comply with the notification or certification provisions called for by the contract); or you are entitled to an extension of time. Continue to keep these alternative options under review.
  • If you are successful in any challenge as to the level of liquidated damages, you should bear in mind that it remains open to the employer to pursue a claim for general damages in the usual way. The quantum of any such claim for general damages may, however, be lower than the equivalent liquidated damages provision, as the latter now allows for commercial considerations to be taken into account and does not require strict proof of financial loss.

Conclusion

The decision of the Supreme Court in Cavendish Square Holdings BV (Appellant) v Tatal El Makdessi (Respondent) has replaced the century-old test in Dunlop v Matthew Tyre Co Limited v New Garage Motor Co Limited with a modern test that reflects the fact that in some circumstances, parties have a legitimate commercial interest in enforcing the performance of contractual obligations which go above and beyond compensation for any identifiable commercial losses they may suffer as a result of the breach, or the deterrence of a breach of contract. In the construction context, this new test requires a consideration of the commercial justification for the liquidated damages clause at the time the contract was entered into, and whether it is out of all proportion to the employer's legitimate commercial interest in the works completing on time.

Whilst the new test is ultimately to be welcomed, there is plenty of scope for satellite litigation as to what might amount to a "legitimate" commercial interest which will no doubt be played out in the courts in the years to come.


Notes:

1. A Supreme Court bench would usually comprise three or five judges: the fact that seven judges heard the appeal demonstrates its importance.

2. The most common breach to which liquidated damages will attach is a failure by the contractor to complete the works on time (which is why they are often known as delay damages), but liquidated damages may also apply to other types of breach as might be specified by the parties to the contract, an example being plant performance shortfalls in EPC contracts.

3. When the Technology and Construction Court considered the decision in Dunlop v Matthew Tyre Co Limited v New Garage Motor Co Limited in the construction context in Alfred McAlpine Capital Projects Ltd v Tilebox Ltd [2005] EWHC 586 (TCC), the judge, Mr Justice Jackson (as he then was), held that there had to be a substantial discrepancy between the level of damages stipulated in the contract and the level of damages that was likely to be suffered before it could be argued that the pre-estimate was unreasonable. Indeed, Mr Justice Jackson noted that there had only been four instances in previous cases where liquidated damages had been struck down as a penalty, and in each case there had been a "wide gulf" between the damages that were likely to be suffered and those stipulated by the liquidated damages provision. The court further held that the point in time at which the assessment as to whether the liquidated damages provision was a genuine pre-estimate of loss was the time at which the contract was entered into, not the time when the breach occurred.

4. Which was considered before ParkingEye Limited v Beavis.

5. Of Lord Neuberger and Lord Sumption (with whom Lord Clarke and Lord Carnwath agreed).

Please click here to view previous issues of Insight

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Lisa Kingston
 
In association with
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.