UK: The Court Of Appeal In Persero II: How To Enforce "Binding But Non-final" Dispute Board Decisions Under The FIDIC Form Of Contract

Last Updated: 11 August 2015
Article by Robbie McCrea

PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2015] SGCA 30

This article is a follow-up to two International Quarterly ("IQ") articles on the Persero series of cases, the first of which followed the Persero I Court of Appeal decision in Issue 01, 2011, and the second followed the Persero II High Court decision in Issue 12, 20141. As promised we have continued to monitor the progress of this influential series of cases, and we set out below our conclusions on the enforcement of non-final DAB decisions following the latest (and final) decision by the Court of Appeal in Persero II.

Introduction

The 1999 FIDIC Suite of Contracts2 includes a dispute resolution mechanism that was designed to give the parties quick, costeffective and immediately binding awards through the Dispute Adjudication Board ("DAB") mechanism at Clause 20 of the Conditions of Contract.

However, an apparent oversight in the drafting of Clause 20 has left many parties with an entirely different experience from that intended by the FIDIC drafters, and even today there is no settled pathway to enforce a DAB decision where the non-complying party has prevented the decision from becoming "final".3

A DAB decision will become final if neither party provides written notification of their dissatisfaction with the decision within 28 days of receiving it (pursuant to Sub-clause 20.4). It is therefore a straightforward matter for either party to ensure a DAB decision remains "nonfinal".

Both final and non-final DAB decisions are immediately binding on the parties. However, final decisions cannot be appealed, and if a party fails to comply with a final decision Sub-clause 20.7 expressly allows the other party to refer to arbitration the discrete issue of non-compliance in order to enable the DAB decision to be enforced as an arbitral award.

Although the FIDIC drafters have stated that their intention was that non-compliance with "non-final" DAB decisions be enforceable in the same manner as "final" decisions,4 there is no express provision in the Conditions of Contract to allow it. This has led to debate as to how to enforce a binding but non-final DAB decision.

The issue has been dealt with in a multitude of ways by DABs, arbitral tribunals and legal commentators. However, because DABs and arbitration are private, there has been very little guidance from the courts.

For this reason there has been widespread interest in a series of cases involving this issue in Singapore, the "Persero" series, which culminated in the decision of the Singapore Court of Appeal in PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2015] SGCA 30, the reserved judgment being issued on 27 May 2015.

In a split decision, the Majority of the Court of Appeal found that binding but non-final DAB decisions could be submitted directly to arbitration on the discrete question of noncompliance.

While the Majority's decision is on face value a victory for contractors seeking the protection of a security of payment regime, the result is bittersweet. Interim enforcement of the DAB decision was obtained only after going through two sets of arbitration, High Court and Court of Appeal proceedings, and over a period of six years. A decision on the merits of the underlying dispute is still to be decided.

Furthermore, the pathway to interim relief laid down by the Majority differs from all previous judgments in the Persero series, whereas the Minority judgment held that the Conditions of Contract provide no scope whatsoever for expedited relief by enforcing non-final DAB decisions.

Parties would therefore be well advised to proceed carefully when pursuing the enforcement of non-final DAB decisions under the FIDIC Conditions of Contract.

Background

The Persero series involves a dispute between parties to a contract based on the FIDIC Red Book, and which is governed by the law of Indonesia. A DAB was established and subsequently ordered that the employer ("PGN") pay the contractor ("CRW") in excess of US$17 million (the "DAB Decision"). PGN accordingly issued a Notice of Dissatisfaction ("NOD") pursuant to Sub-clause 20.4 and refused to comply with the DAB Decision. The Persero series is based upon CRW seeking expedited enforcement of the DAB Decision.

CRW first attempted to enforce the DAB Decision by proceeding to arbitration in 2009 under Sub-clause 20.6 on the discrete question of whether CRW was required to comply with the DAB Decision. The arbitral tribunal found in CRW's favour and held in a final award that PGN had an obligation to make immediate payment of the sum awarded in the DAB Decision. This is consistent with the stated intention of the contract drafters.

The 2009 tribunal's award was subsequently set aside by the High Court of Singapore. The High Court reasoned that the tribunal could not convert the non-final DAB Decision into a final award without determining the merits of the underlying dispute. However, the Court opined that if CRW were to obtain a second DAB decision on the discrete question of non-compliance with the first DAB Decision, it could then submit the second DAB Decision to arbitration where the tribunal could decide the issue as it would be hearing the issue referred on its merits. This is known as the "two-dispute" approach.

The High Court decision was appealed to the Court of Appeal which confirmed that the 2009 Arbitral Award should be set aside. However, the Court of Appeal did not endorse the two-dispute approach. Instead, the Court considered that the tribunal would have been able to enforce the DAB Decision by way of interim relief, if CRW had also submitted the underlying dispute to the tribunal as part of the same referral. Under this approach the tribunal could first give an interim award on the issue of non-compliance with the DAB Decision, and then go on to hear the substantive dispute on its merits. This is known as the "one-dispute" approach.

CRW subsequently commenced a new arbitration under the one-dispute approach. By majority, the 2011 tribunal issued an interim award compelling PGN to give prompt effect to the DAB Decision (the "Interim Award") pending the tribunal's final determination of the underlying dispute.

The Interim Award and the one-dispute approach were upheld by the High Court in Persero II5 in its decision of July 2014, which found that Clause 20 of the Conditions of Contract establishes a "security of payment regime", the principal purpose of which is to facilitate the cash flow of contractors by requiring the employer to pay immediately, while preserving its right to argue later the substantive merits of the dispute in arbitration (i.e. "pay now, argue later"). Accordingly, the arbitral tribunal was entitled to grant a final and binding award that the DAB Decision be complied with immediately, albeit as the first step of the primary dispute being finally decided in due course.

PGN appealed Persero II to the Court of Appeal.

The Court of Appeal in Persero II

The 2015 Court of Appeal by majority ruled in favour of CRW and upheld the Interim Award. However, the Court found that neither the one-dispute approach nor the two dispute approach was strictly correct. Instead, it considered that binding but non-final DAB decisions should be enforceable by way of interim awards in and of themselves, that is, without referring the secondary dispute back to the DAB and without the need to also submit the underlying dispute to arbitration.

The Majority judgment

As a preliminary matter the Majority considered the DAB's powers under Sub-clause 20.4 and set out the following three propositions:6

(a) "A DAB decision is immediately binding once it is made. ...

(b) The corollary of a DAB decision being immediately binding once it is made is that the parties are obliged to promptly give effect to it until such time as it is overtaken or revised by either an amicable settlement or a subsequent arbitral award.

(c) The fact that a DAB decision is immediately binding once it is made and unless it is revised by either an amicable settlement or arbitral award is significant ... the issuance of an NOD [notice of dissatisfaction] self-evidently does not and cannot displace the binding nature of a DAB decision or the parties' concomitant obligation to promptly give effect to and implement it."

The Majority then considered the two-dispute approach that was preferred by the High Court in Persero I and rejected it on the basis that, in light of the above three propositions, "any requirement to refer a question as to the immediate binding effect of a binding but nonfinal DAB decision back to the DAB seems to us not only wholly superfluous, but also contrary to the express words of cl 20.4[4]".7

In respect of the one-dispute approach that was preferred by the Court of Appeal in Persero I and the High Court in Persero II, the Majority rejected the notion that all differences between the parties would need to be settled in a single arbitration. The Majority instead found that a "paying party's failure to comply with a binding but not final DAB decision is itself capable of being directly referred to a separate arbitration under cl 20.6".8

In practice, however, the Majority's decision may be less of a departure from the onedispute approach than a first glance would suggest. This is because the Majority also found that the non-complying party could, by filing a counterclaim, require that the underlying dispute also be heard as part of the same arbitration, albeit after the tribunal had first made a final award in respect of noncompliance with the DAB decision.9

The Minority judgment

In a 95-page dissenting judgment, Senior Judge Chan Sek Keong found the opposite. His Honour's opinion was that, unlike final decisions under Sub-clause 20.7, there is no scope in Sub-clause 20.6 or elsewhere in the Conditions of Contract for interim enforcement of non-final DAB decisions.

His Honour considered that the Interim Award should be set aside on one or more of the following three grounds:

  1. Failure to comply with the non-final DAB Decision did not fall within the scope of "dispute" in Sub-clause 20.4, or anywhere in the arbitration agreement, and therefore it could not be the subject of an arbitral award.
  2. The 2011 Majority Arbitrators had no mandate under Sub-clause 20.6 to issue the Interim Award pending the final adjudication of the Underlying Dispute.
  3. Even if the 2011 Majority Arbitrators did have the mandate under Sub-clause 20.6 to issue the Interim Award, the Interim Award was, and was intended to be, in substance a provisional award outside the ambit of "award" in s.2 of the Singapore International Arbitration Act ("IAA") and was not enforceable under s.19 of the IAA as a judgment.
  4. Accordingly, His Honour considered that in order to enforce the DAB Decision CRW would need to go outside the contractual machinery, for instance by seeking summary judgment in a court of competent jurisdiction.

Conclusion

Far from providing the much needed clarity that was hoped for (by contractors at least), the Persero series has concluded by adding yet more interpretations of the disputes mechanism at Clause 20. Prospective claimants must now consider the four potential approaches endorsed in the Persero series when considering enforcement of a non-final DAB decision, namely:

  1. Submit the issue of non-compliance with the DAB decision directly to arbitration.
  2. Obtain a second DAB decision in relation to non-compliance and refer that second DAB decision to arbitration (the twodispute approach).
  3. Submit the entire substantive dispute to arbitration, seeking in the first instance an interim award that the DAB decision be complied with immediately, on the basis that the substantive dispute will be heard on its merits in due course as part of the same referral (the one-dispute approach).
  4. Seek to enforce the DAB decision outside the contractual machinery, for instance by seeking summary judgment in a court of competent jurisdiction.

It should be noted that the Persero series were decided in Singapore under Indonesian law, and the judgments included consideration of a number of factual and jurisdiction-specific matters. These should be considered carefully before placing reliance on the Persero decisions in relation to other jurisdictions and cases.


Footnotes

1. These articles are both available in the IQ archive on the Fenwick Elliott website www.fenwickelliott.com

2. The Red Book, the Yellow Book and the Silver Book.

3. Either party can prevent a DAB decision from becoming final by giving written notification of their dissatisfaction with the decision within 28 days of receiving it (pursuant to Sub-clause 20.4).

4. The FIDIC Contracts Committee issued a Guidance Memorandum on 1 April 2013 in which they sought to clarify that in the event of non-compliance with non-final DAB decisions, "the failure itself should be capable of being referred to arbitration under Sub-clause 20.6".

5. PT Perusahaan Gas Negara (Persero) TBK ("PGN") v CRW Joint Operation (Indonesia) ("CRW") [2014] SGHC 146.

6. At paragraph 57.

7. At paragraph 66. The Majority's principal rationale behind this finding was that while PGN's NOD only expressly covered its dissatisfaction with the DAB Decision, by PGN choosing not to comply with the DAB Decision its NOD also implicitly expressed dissatisfaction with the requirement that the DAB Decision be complied with, and therefore the dispute over non-compliance was already encompassed in the NOD. With respect, this reasoning is questionable.

8. At paragraph 83.

9. The Court's position was summarised at paragraph 88.


International Quarterly is produced quartely by Fenwick Elliott LLP, the leading specialist construction law firm in the UK, working with clients in the building, engineering and energy sectors throughout the world.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Robbie McCrea
 
In association with
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.