UK: The JCT 2005 Standard Forms of Construction Contract

Introduction

  1. The JCT’s introduction of the 2005 suite of standard form construction contracts is certainly more than just a "facelifting" exercise. Not only have the 2005 forms been redrafted using less legalistic language and sorted into a more user-friendly format, important developments have also been incorporated, triggered by changes in both the industry and the law.

  2. Space and time prevent an exhaustive analysis of all such developments. Instead, the focus of this talk will be on four key areas in which the most striking changes appear to have been made, namely:

(I) Layout and Structure of the 2005 forms

  1. The drafting of the 2005 forms has been heavily influenced by a search for uniformity and modernisation (probably influenced by the fact that they are newly published by Sweet & Maxwell). This has manifested itself in several different ways.

Section-Headed Approach

  1. The documents published so far adopt a "section-headed" approach rather than a "clause-by-clause" structure, splitting each contract into parts with titles such as "Carrying Out the Works", "Control of the Works" etc.

  2. To a familiar user of the 1998 forms, such a re-jigging certainly appears a little unfamiliar. The sectional approach has had the effect of rearranging the conditions in such forms. (It is important to be aware that, although there have been some significant changes to substance, for the most part the new forms do reflect the provisions of the old (although those provisions may have moved around – so you will need to cross-check!)).

  3. The net result is an undoubtedly more "user-friendly" contract designed to be more accessible to contracting parties and construction professionals alike.

Project-Specific Approach

  1. Perhaps in an attempt to encourage contracting parties to properly fill in details of the works to which the contract relates, "project-specific" information, traditionally located in the Appendix to the conditions, has been shifted to the front of the Contract in what is generally known as the "Contract Particulars".

  2. The Contract Particulars also include, for the first time, the identity of parties to whom third party rights are to be given and factors regulating liability under the contract such as net contribution clauses for subcontractors. This is an important inclusion and is discussed in more detail below.

Integration of Supplements

  1. Another welcome development is the integration of some supplements into the main text of the 2005 Contracts, obviating the need to read two documents together or, in the case of hard copies, to make numerous amendments to clauses.

  2. For example, under the Standard Building Contract 2005 ("SBC 2005"), sectional completion is dealt with by express contractual provisions (in particular, the Articles of Agreement, the Contract Particulars, the Definitions under clause 1 and the Conditions) rather than by the addition and incorporation of a supplement.

Greater use of Schedules

  1. On the other hand, curtailments to the body of the standard form text have been made by cross-referring back to the Contract Particulars. For example, under the 1998 standard form contract there were lengthy options for the insurance of the works under clauses 22A, 22B or 22C, meaning that once one of these has been selected, the other two clauses are rendered superfluous. The result was unwieldy and potentially confusing.

  2. Clause 6.7 of SBC 2005 now simply provides:

"Insurance Options A, B and C are set out in schedule 3. The Insurance Option that applies to this Contract is that stated in the Contract Particulars"

Publication of Guides

  1. The JCT has produced "guides" to assist the user in finding the equivalent provisions in the older standard form contracts in the new editions.

  2. Whether such guides will be used by contracting parties as a reference tool (which is presumably what they are intended to be) or as a resource for bespoke amendments remains to be seen…

(II) Contractor’s Design Responsibilities

  1. The 2005 reformatting of the JCT contracts has seen two notable additions to the range, namely the Minor Works Building Contract with Contractor’s Design ("MWD 2005") and Intermediate Works Building Contract with Contractor’s Design ("ICD 2005"), specifically tailored for the smaller end of the market where the contractor provides some design input subject to supervision from the architect or contract administrator.

  2. Neither contract is intended to be a substitute for a design and build contract; indeed, both appear only to be suitable in circumstances where the parties intend that the contractor is to be responsible for a discrete element of the design.

  3. Perhaps in order to emphasise this point, both contracts oblige the employer (i) to supply detailed requirements for the intended "contractor’s design portion", (ii) to examine the contractor’s proposals in respect of such requirements and (iii) to satisfy himself that those proposals are adequate (see Seventh Recital).

  4. It is of course open to an employer to delete or amend such provisions in an attempt to impose a more onerous design responsibility upon a contractor than was intended by JCT draftsmen. This may well be an area where disputes occur.

  5. More interestingly from the lawyer’s point of view, the contractor’s design obligation differs between the two contracts. Under ICD 2005, the standard of care in relation to the design of the particular portion is that of a professional designer.1 Conversely, under MWD 2005 the standard is that of reasonable skill, care and diligence.2 The question which presumably will be left for the courts to decide is whether the reasonable skill and care to be expected of a contractor carrying out design work is different to the skill and care to be expected of a professional designer.

Contractor’s obligation to "complete" the design

  1. By including a clause within SBC 2005, DB 2005, IDP 2005 and MWD 2005 which expressly provides that a contractor is not responsible for checking the adequacy of any design contained within the employer’s requirements, the JCT appears to have kicked the principle laid down by the decision in Cooperative Insurance Society v Henry Boot Scotland Limited (2003) CLJ 19 109 squarely into touch.

  2. In Boot, HHJ Seymour QC held that a contractor charged with "completion" of design work was under a duty of care to examine an employer’s pre-existing design and to satisfy himself that the same was such that would produce a completed design capable of being constructed.

  3. However, this is not to say that a contractor has no responsibility whatsoever in relation to the design:

    1. under SBC 2005, DB 2005 and ICD 2005 (though not MWD 2005), a contractor is obliged to notify any inadequacies in the employer’s requirements upon becoming aware of the same, and then to seek reimbursement for related costs by way of a variation;

    2. Further (save under MWD 2005), it is incumbent on the contractor to ensure that the employer’s design complies with any statutory requirements (except in the case of DB 2005 where the employer’s requirements state that they are so compliant).

Design Review Procedure

  1. Both DB 2005 and SBC 20053 contain a "design review procedure" whereby the contractor is required to submit all design documents that it prepares for review. Following such a review, design documents are graded as follows:

    1. "A" – contractor to proceed with the works in accordance with the design document. To prevent any undue delay, a design is deemed to have been marked "A" in the event that it is not returned within 14 days of submission;

    2. "B" – contractor proceed with the works in accordance with architect/employer comments. Design must also be amended to take on board such comments;

    3. "C" – contractor to resubmit design document incorporating comments made. No works to be carried out.

  2. A contractor is only entitled to be paid in respect of such work where it has been executed in accordance with designs marked A or B.

  3. It remains to be seen whether an employer may seek to cross the line between making comments on designs which are for the purposes of gaining confidence that the contractor is having proper regard to the contractual requirements and making comments which, in effect, attempt to vary the design requirements via the back door. To protect against this, a contractor is required to raise any challenges to comments which appear to introduce a variation within 7 days of the comment being made. Absent this, such comments will be deemed not to constitute a variation.

(III) Third Party Rights

  1. Despite a clear market demand for collateral warranties, especially following the infamous decision of the House of Lords in Murphy v Brentwood, the JCT has consistently refused to incorporate provisions for a contractual warranty between main contractor and third parties (principally purchasers, tenants and funders). Inevitably, such a provision led to a proliferation of bespoke forms of collateral warranties.

  2. The granting of third party rights has already been included in the 2003 Major Project Form ("MPF") (although this did not and does not extend to the provision of warranties).

  3. Perhaps encouraged by the MPF, or alarmed by the number of bespoke warranties in existence, SBC 2005, DB 2005 and IC/ICD 2005 now include provisions for main contractor and subcontractor collateral warranties in favour of purchasers, tenants and funders.

  4. However, it should be noted that the nature of such provisions varies markedly across the 2005 suite of contracts. For example, the MW/MWD05 contains no such clauses, whereas the SBC 05 makes provision for collateral warranties, sub-contractor collateral warranties and the granting of third party rights.

  5. Should such provisions exist, it is critical that the Contract Particulars in relation to warranties or third party rights are carefully filled in. In addition to identifying the beneficiaries, the parties also need to identify the part of the works to be purchased or let and whether or not a warranty or third party rights are to be granted (if a choice is available).

  6. Specific details requiring attention include whether or not a contractor is to be liable for non-repair losses incurred by the beneficiary and any "cap" to be applied to the net contribution clause of the warranty. Should no purchasers, tenants or funders be identified by name, class or description, then an employer will not be able to subsequently ask for warranties or third party rights in relation to the same.

  7. A notice identifying (i) the relevant purchaser, tenant or funder and (ii) his particular interest in the works must be served by actual, special or recorded delivery upon the contractor, following which the contractor has fourteen days to enter into the relevant form of warranty. Third party rights vest in the appropriate beneficiaries upon the contractor’s receipt of a notice from the employer.

  8. Should sub-contractor remedies be required (as provided for under IC/ICD 05, SBC 05 and DB 05) then it is incumbent upon the contractor to "comply with the requirements set out in the Contract Documents as to obtaining such warranties". It is up to the parties to decide whether such an obligation is absolute or restricted to using the contractor’s "best endeavours" or "reasonable endeavours".

  9. The 2005 suite anticipates that standard form warranties (such as the JCT CWa/P&T (for purchasers and tenants) or the JCT CWa/F (for funders)) will be adopted by the parties, but the contracts provide that the agreed forms are subject to bespoke amendments.

(IV) Dispute Resolution

  1. For the lawyer and construction professional alike, perhaps the most significant practical development implemented by the 2005 forms has been the apparent sea change to the familiar JCT dispute resolution procedure.

  2. Whilst the draftsmen have shied away from a "uniform" procedure, applicable across the entire 2005 suite of, it is fair to say that the new forms see arbitration as being on the wane.

SBC 2005

Adjudication

  1. The JCT Adjudication rules have been scrapped in favour of the Scheme for Construction Contracts.

  2. One significant consequence of this is that it would seem that no more than one dispute at a time can be referred. It had previously been decided that under the JCT adjudication provisions (but not the Scheme) multiple disputes could be referred in one adjudication – R Durtnell & Sons v Kaduna Ltd [2003] BLR 225.

Arbitration

  1. Arbitration still exists but is no longer the default position; for it to apply, an express entry must be made in the Contract Particulars against Article 8.

  2. Even though the draftsmen did not go as far as removing the provision for arbitration entirely, such as in the case of the MPF, this development remains a particularly interesting one, especially in the light of the recent shake-up of the TCC.

MW 2005/IC2005

  1. The dispute resolution procedure under these two forms is broadly the same as the SBC 2005. However, given that both forms may well be used by parties who fall within the definition of "residential occupiers" for the purposes of s.106 Housing Grants, Construction and Regeneration Act 1996, the accompanying guides to each contract contain a "health warning":

IC 2005

  1. Care needs to be taken where an Intermediate Building Contract is used for a contract with a residential occupier within the meaning of section 106 HGRA 1996…

  2. Since Part II of that Act does not apply to contracts with residential occupiers, as defined, the Employer’s Architect or contract administrator may be under a duty to advise his or her client(s) accordingly, in particular with regard to adjudication and as to whether or not to disapply Article 7 and clause 9.2.

MW 2005

  1. The Contract complies with the requirements of the Housing Grants, Construction and Regeneration Act 1996 in providing for adjudication and certain payment provisions; however, not all building contracts are subject to this Act. For example, a contract with a residential occupier within the meaning of section 106 of the Act is excluded and therefore it does not need to contain adjudication provisions, but a residential occupier in entering into a Minor Works Building Contract will be accepting adjudication as a means of resolving disputes.

5. Conclusions

  1. In general terms, the changes implemented by the 2005 suite of JCT contracts are to be welcomed and evidences the fact that constructive criticism from commentators is not necessarily ignored! 4

  2. However, as with all contracts, it will be open to the parties to amend, add or omit certain clauses – especially those which appear unfamiliar. For example, issues in relation to the existence and extent of a contractor’s design responsibility may be an area which proves to be particularly fruitful for those in the legal profession.

For further information…(!)

  1. See the forthcoming publication "Keating on the JCT Contracts" which will:

  • Be published by Sweet & Maxwell (and written by members of Keating Chambers)

  • Provide clause by clause commentary on (eventually) all of the new suite

  • Be in looseleaf and updated format

  • Contain extensive cross-referencing to Keating on Building Contracts (new edition also out shortly!)

Footnotes

1. clause 2.34.1

2. clause 2.1.1

3. although only if the Contractor’s Design Portion in the Seventh Recital is applicable

4. By way of example, we would like to think that the removal of all provisions in relation to nominated subcontractors is in no small part due to the criticism levied towards the same in Keating on Building Contracts!

The articles and papers published by Keating Chambers are for the purpose of raising general awareness of issues and stimulating discussion. The contents must not be relied upon or applied in any given situation. There is no substitute for taking appropriate professional advice.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
 
In association with
Related Topics
 
Related Articles
 
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Registration (you must scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions