UK: Construction, Property & Real Estate (Case Law Review – April 2006)

Last Updated: 27 March 2006

By Professor Anthony Lavers, Director of Research and Professional Development at Keating Chambers

ADJUDICATION

Adjudicators’ late decisions

Adjudicator’s decisions: better late than never?
By Peter Sheridan and Dominic Helps, Shadbolts, Construction Law Journal (2006) Construction Law Journal Vol 22 No 1 p.52.

The authors, in their regular Construction Act Review slot, consider the (five) reported cases in which late delivery of decisions by adjudicators has been considered. The distinction between making a late decision and communicating it late is observed: the authors blame the lack of clarity in the decisions on lack of clarity in the Act.

Proper responding parties to adjudication
Michael John Construction Ltd v Golledge [2006] BLM Vol.23 No.3 p.5

This concerns a construction contract concluded between a contractor and an unincorporated club. The contract was signed by trustees of the club. The contractor referred payment problems to adjudication and obtained awards in its favour. The defendant trustees resisted enforcement on the ground that the adjudicator had no jurisdiction to bind the trustees, since, under the club’s constitution, the proper responding parties were each and every club member and that the second reference comprised two disputes. The court rejected the defendant’s arguments: the club’s constitution was irrelevant as between the contracting parties and it would be contrary to the purpose of adjudication if simple disputes were required to be separated into individual components.

Natural Justice
Ardmore Construction Ltd v Taylor Woodrow Construction [2006] CILL 2309 Court of Session Outer House

The court emphasised that, generally, courts should be slow to characterise adjudicators’ procedures as contrary to the rules of natural justice. However, here, exceptionally, there was evidence of breach of natural justice by the adjudicator in failing to give one party the opportunity to deal with their opponents’ expansion of their case from that pleaded, so that the adjudicator was basing his decision on matters on which there had been no argument.

See Midland Expressway v Carillion (No. 2) under Keating Chambers Reported Cases on pay when paid clauses in PFI contracts.

See Devonport Royal Dockyard v Carillion Construction under Keating Chambers Reported Cases on the adjudicators’ power to award interest and the duty to give reasons.

See Kier Regional v City & General (Holborn) under Keating Chambers Reported Cases on the effect of disregard of expert evidence by adjudicator.

See Capital Structures v Time & Tide Construction under Keating Chambers Reported Cases on the refusal of enforcement of an adjudication decision under a contract allegedly void for duress.

ARBITRATION AND DISPUTE RESOLUTION

Serious irregularity
Cameroon Airlines v Transnet Ltd [2005] TCLR TI Commercial Court

In a maintenance contract between the Cameroon State airline and South African Airways, a dispute about alleged bribery inducing the formation of the contracts was referred to arbitration in London. The majority of the tribunal had adopted a particular view of quantification for the purposes of calculating repayment. The Employer applied to set aside the award on the grounds of serious irregularity under s.68 Arbitration Act 1996. The court set aside the award; it was not necessary to show that the outcome of remitting the award would even probably be different, but it is necessary to show that the applicant has been unfairly deprived of the opportunity to present its case. The majority of the tribunal had departed without warning from the way the case on quantification was presented and this created a real risk of substantial injustice to the employer who had not been given a chance to address the way the majority were thinking.

International Arbitration Law Review Vol 9 Issue 1 Feb 2006
contains the following articles:

China Arbitration Law v UNCITRAL Model Law
by Weng Sheng Chang, CIETAC and Sarah Hilmer, ACICA.

Human Rights: a speed bump for arbitral procedures? An exploration of safeguards in the acceleration of justice.
by Thomas Schultz, University of Cambridge

Substantive or procedural: an arbitration perspective
by Hakeem Seriki, Vinson & Elkins, London.

Arbitration Law Monthly Vol. 6 No 3 March 2006
contains the following articles:

Judicial support for arbitral proceedings
on Tajik Aluminium Plant v Hydro Aluminium (witness summonses)

Serious irregularity
on Sinclair v Woods of Winchester (procedural and substantive aspects of section 68

Stay of judicial proceedings
on Ahad and Ahmed v Uddin (loss of the right to seek a stay)

Jurisdiction
on Bakwin and Erie International Trading Co v Sothebys (determining the jurisdiction of arbitrators)

Error of Law
on Surefire Systems v Guardian ECL, (Adam Constable) (the grant of permission to appeal)

Mediation
on Burchell v Ballard, Wethered Estate v Davis and Thames Valley Power v Total Gas and Power (judicial support for mediation).

See Surefire Systems Ltd v Guardian ECL under Keating Chambers Reported Cases on whether alleged errors by the arbitrator involved a question of law for the purposes of s.69 Arbitration Act.

Asian Dispute Review January 2006
contains the following articles:

Latest developments in arbitration in Malaysia and Brunei
by Colin Ong, Brunei

Arbitration under the ICC and the JCAA a comparison between the ICC Rules and the JCAA Rules
by Melanie Ries, Bosch Corp, Tokyo

The 2002 Thai Arbitration Act may not change much
by Thavisak Na Ta Kuathung & Craig Arndt, Kanung & Partners, Bangkok

Interim measures of protection in international arbitration proceedings: towards a new paradigm?
by David Howell, Fulbright & Jaworski, London

Practical issues to consider in relation to enforcing and resisting enforcement of international arbitration awards
by Julian Cohen, Masons, Hong Kong

Managing cultural differences in on-line dispute resolution
by Sharanya Rao, Singapore

Mediation in Australia: history, policy and application
by Peter Megens, Mallesons Stephen Jaques, Melbourne

Judicial review of tunnel toll arbitration
by Andrew Aglionby and Catherine Mun, Baker & McKenzie, Hong Kong

CONSTRUCTION AND ENGINEERING CONTRACT LAW

Letter of Intent
Hackwood Ltd v Areen Design Services Ltd [2006] Construction Law Journal Vol 22 No 1 p.68

The court has to consider whether the effect of a letter of intent was to incorporate the JCT form of contract and specifically its arbitration agreement, for the purposes of deciding whether declarations should be granted to the claimant employer that the arbitration proceedings were a nullity under s.72 Arbitration Act 1996 or to the contractor that the claimant was debarred from participating in the arbitration.

JCT Major Project Form
Time and loss and expense in the Major Project Form by Nicholas Lane, Travers Smith, Construction Law Journal (2006) Vol 22 No 1 p3.

The article concentrates on the way the JCT Major Project Form 2003 deals with time and with loss and expense. There is fairly detailed treatment of clause 9 (commencement and completion), Clause 11 (taking over parts of the project), Clause 12 (extensions of time), Clause 13 (acceleration), Clause 14 (bonus) and Clause 21 (loss and/or expense). The author finds the extension of time provisions "conservative" and the absence of programming requirements notable. There is a table comparing events entitling the contractor to an extension of time under the JCT With Contractor’s Design, Design and Build and Major Project Form respectively.

Unfair Contract Terms
The architect, the banker, his wife and the adjudicator: construction and the changing law of unfair contract terms by Phillip Britton, King’s College, London. Construction Law Journal (2006) Vol 21 No 1 p.23

This is an updated version of the paper which won the 2003 SCL Hudson Prize, dealing with changes in unfair contract terms law in the context of construction. He tracks the now well-known adjudication cases Picardi v Cuniberti, (Simon Hughes and Richard Harding), Lovell Projects v Legg, (Piers Stansfield), Westminster Building Co v Beckingham, (Simon Hughes and Gaynor Chambers) and Bryen & Langley v Boston. The author includes tables comparing the factual backgrounds of the four cases and also comparing UCTA as amended and the Unfair Terms in Consumer Contracts Regulations. He notes the arrival of the Unfair Contract Terms Bill 2005.

Condition precedent to claim
Décor Ceilings v Cox Constructions (No. 2) [2006] CILL 2311 Supreme Court of South Australia

CILL has chosen to report this South Australian decision because it usefully reviews the position where contracts provide for notices and other procedural steps in the bringing of delay and disruption claims. It was argued that the contract in question contained a clause providing an exclusive remedy, but the court held that it did not exclude the sub-contractor’s entitlement to claim for general damages for breach of contract. The requirement of notice could operate as a condition precedent to the bringing of a claim.

See Scheldebouw v St James Homes under Keating Chambers Reported Cases on a Construction Manager’s duty of fairness in contract administration.

See Shawton Engineering v DGP International under Keating Chambers Reported Cases on grounds for termination for delay in performance.

GENERAL AND PROFESSIONAL NEGLIGENCE

Occupiers’ Liability
Keown v Coventry Healthcare NHS Trust [2006] BLM Vol. 23 No.3 p.8 CA

The Court of Appeal allowed the Trust’s appeal against a finding of liability under the Occupiers’ Liability Act 1984 towards a child trespasser who had suffered brain injuries in a fall on a Trust building and subsequently committed offences allegedly due to a personality change. The Court of Appeal held that the fire escape from which the child had fallen was not itself dangerous, within the meaning of s.1(1) of the Act.

PRACTICE AND PROCEDURE

The Commercial Litigation Journal No 5 Jan/Feb 2006
contains the following articles:

Electronic disclosure: a practical guide
by Philippa Bennett, Piper Rudnick Gray Cary

Arbitration costs: who pays what?
by Michael Reynolds, Davies Lavery

Mediation: getting the right result
by Hilton Meruis, SJ Berwin

Misrepresentation: signed, sealed … but misrepresented
by Paul Friedman and Shakir Anverally, Clyde & Co.

Fraud: heads in the sand
by Andrew Howell and Dorothy Herman, Barlow Lyde & Gilbert

Insolvency: circumventing the liquidator
by Alexander Stewart, Hogarth Chambers

Experimental litigation training: the hands-on approach
by Fiona Cunningham, Nottingham Law School.

Pre-action disclosure
Northumbrian Water Ltd v British Telecommunications plc [2006] BLR 38 TCC

The TCC dismissed Northumbrian Water’s application for pre-action disclosure of documents relating to tunnelling work by BT, who were suing Northumbrian Water for damage to BT service tunnels allegedly caused by their excavations. The TCC Protocol only deals with disclosure, not pre-action disclosure, so the tests were the four in CPR 31.16(3):

  1. respondent likely to be party in subsequent proceedings
  2. applicant likely to be party to those proceedings
  3. standard disclosure would apply to the documents if proceedings had already started
  4. pre-action disclosure was desirable to dispose of the matter without proceedings, fairly or economically.

The BLR commentary notes that this judgment of HH J Coulson follows the decision of the same judge on a similar issue in Briggs & Forrester Electrical v Governors of Southfield School for Girls (Simon Hargreaves)

Indemnity Costs
Wates Construction Ltd v HGP Greentree Allchurch Evans Ltd [2006] BLR 45 TCC

This concerns the criteria for indemnity costs for unreasonable conduct. Contractor Wates joined its architect HGP, following a roof collapse at a Waitrose retail outlet built by Wates under a design and build contract. Wates settled with Waitrose but its insurer insisted on proceeding against HGP under subrogation rights. At trial, Wates opened by withdrawing the claim and offering to pay costs. HGP attacked the conduct of the litigation against it, when the claim was obviously doomed, especially on the basis of the experts’ joint statement. In the circumstances, the court awarded indemnity costs. HGP had earlier threatened to claim on an indemnity basis if the proceedings were discontinued.

Indemnity Costs again
LMS International Ltd v Styrene Packaging & Insulation Ltd [2006] BLR 50 TCC

Conduct must be unreasonable to justify an award of indemnity costs, although it need not involve morally blameworthy conduct. Exceptionally, refusal to mediate might justify indemnity costs, although not in this case. The decision to defend had been wrong and misguided but no worse; it was arguable and not lacking in good faith. The application for indemnity costs was refused.

KEATING CHAMBERS REPORTED CASES

Interserve Industrial Services Ltd v Cleveland Bridge UK Ltd [2006] All ER (D) 49 TCC

Where a series of adjudications between claimant sub-contractor and defendant contractor were initiated, the defendant tried to resist enforcement of the decision of the second adjudication by maintaining that it could be set off against the third award, which had been issued during the enforcement proceedings. The TCC rejected this argument: under ss.108(3) and 111of the HGCR Act and the CIC Model Adjudication Procedure adopted, defendant was under an obligation to pay the amount of the second award and summary judgment was entered.

Christopher Thomas QC
Simon Hargreaves
Robert Evans

Decoma UK Ltd v Haden Drysys International Ltd [2005] 103 Con LR 1 TCC

This concerns the interpretation of a contract for a paint-spraying system. The issue was whether the party in breach of contract in failing to complete on time and to specification could rely on a contract clause capping its liability. The claimant sought to argue that the defendant contractor would be profiting from its own wrong if it was allowed to do so. The court rejected this argument; it had been clearly agreed that the defendant’s liability would be limited to 5% of contract price and the nature and extent of the breaches of contract were irrelevant.
Marcus Taverner QC

Decoma UK Ltd v Haden Drysys International Ltd (No 2) [2005] 103 Con LR 54 TCC

This is the costs hearing of the substantive trial noted in this section, concerning an attempt to avoid the operation of a contractual liability cap. The defendant had agreed to the claimant accepting out of time a payment into court of £350,000, but did not agree with the claimant’s proposals as to costs. The claimant argued that it should receive all of its costs on preliminary issues, claiming that it was the successful party until it had failed to beat the payment in. The court did not accept this contention; it would not ignore the clear result of the only substantive hearing, which was victory for the defendant.
Marcus Taverner QC

Burford NW3 Ltd v Brian Warwicker Partnership plc [2006] 103 Con LR 112 TCC and CA

Both architects and mechanical and electrical engineers were held liable to the claimant owners in respect of design defects to the doors of a leisure/ retail centre which permitted serious cold draughts to enter the units. The defendant engineers settled without admitting liability and pursued a Part 20 claim against the architects. The TCC, interpreting s.2 of the Civil Liability (Contribution) Act 1978, held that ‘responsibility’ meant more than causal responsibility and includes ‘blameworthiness’. Acts of omission which are not causative of loss, may nevertheless be taken into account in assessing contribution under the Act, although they should be given less weight. This finding was upheld by the Court of Appeal. The architects, who had believed the engineers to be entirely responsible for internal environment, were allocated a 40% liability contribution.
Justin Mort

Shawton Engineering Ltd v DGP International Ltd [2006] BLR 1 CA

This case arose from a design sub-sub-contract relating to a process plant at Sellafield for handling nuclear waste. The issue arose as to the circumstances in which a contracting party could lawfully terminate a contract for delay in performance where the obligation was to complete within a reasonable time. The appellant sub-contractor was unsuccessful in the appeal.
David Thomas QC
Adam Constable

Carillion Construction v Devonport Royal Dockyard [2006] BLR 15 CA

This is part of extensive litigation arising from the dockyard redevelopment project, being an appeal on the adjudicator’s powers to award interest. The Court of Appeal dismissed the client’s appeal against the TCC decision. There is no free-standing power to award interest under cl.20(c) of the Scheme. However, in the circumstances, the client had not disputed the power of the adjudicator to award interest on moneys outstanding. The parties had therefore agreed that interest should come within the scope of the adjudication, conferring on him a jurisdiction he would not otherwise have had.
Stephen Furst QC
Louise Randall

Scheldebouw BV v St. James Homes (Grosvenor Dock) Ltd [2006] CILL 2313 [2006] BLM Vol.23 No.3 p.1 TCC

The TCC held that the client could not itself replace its construction manager in the administration of trade contracts for cladding on the Grosvenor Waterside development. The court considered that this would be inconsistent with a decision maker’s obligation of impartiality, fairness and honesty and could only be achieved by express contractual provision.

Note that Jackson J was here obliged to consider issues, albeit on different facts, left over from Costain v Bechtel (David Thomas QC), in which he also presided.
Simon Hughes

Surefire Systems v Guardian ECL Ltd [2006] BLM Vol.23 No.3 p.11 TCC

This was an attempt to obtain leave to challenge an award under s.69 of the Arbitration Act. Surefire was a trade contractor for the design and installation of a fire and voice alarm system in the County Hall building in London and Guardian a cable installation sub-contractor who claimed loss and expense. Surefire attempted to challenge the award sums where the contractual payment mechanism had not been used. The court held that neither of these issues involved a question of law for the purposes of s.69.
Adam Constable

Midland Expressway Ltd v Carillion Construction (No.2) [2006] CILL 2317 TCC

This is the so called Tiger Tails case, deriving its nickname from white lines on the Birmingham Northern Relief Road (the M6 Toll Road). The court held (amongst a number of other points) that provisions in a building contract for payment on entitlement, were contrary to s.113 HGCR Act as being pay-when-paid clauses. Since this is a provision commonly used in PFI projects, back to back with the concession agreement (which is excluded from the HGCR Act by the Construction Contracts (England and Wales) Exclusion Order 1998), the implications for the industry are considerable.
Nerys Jefford

Kier Regional Ltd v City & General (Holborn) [2006] All ER (D) 64 TCC

The adjudicator’s decision to disregard expert evidence submitted on behalf of the defendant as irrelevant could not render the adjudication award unenforceable. There was no breach of the rules of natural justice and no failure to consider relevant material. If the adjudicator had been wrong in deciding the evidence was irrelevant, this was the kind of error inherently possible under the adjudication system, not a ground for refusal of enforcement by summary judgment.
Adrian Williamson QC

Capital Structures plc v Time & Tide Construction Ltd [2006] All ER (D) 98 TCC

The adjudication provisions in a contract would be lost if, as alleged here, the contract itself, a settlement agreement, was void for economic duress. If the effect was that there was no valid contract, the adjudication provision had become void, so the adjudicator would have no jurisdiction to hear disputes, including the question as to whether there had been economic duress. Accordingly, it would not be appropriate to grant summary judgment for enforcement of the decision.
Simon Hargreaves

The articles and papers published by Keating Chambers are for the purpose of raising general awareness of issues and stimulating discussion. The contents must not be relied upon or applied in any given situation. There is no substitute for taking appropriate professional advice.

This material is prepared for Chambers by our Director of Research and Professional Development, Professor Anthony Lavers (LL.B. M.Phil Ph.D. MCI.Arb MRICS Barrister) Visiting Professor of Law, Oxford Brookes University.

This material is prepared for Chambers by our Director of Research and Professional Development, Professor Anthony Lavers (LL.B. M.Phil Ph.D. MCI.Arb MRICS Barrister) Visiting Professor of Law, Oxford Brookes University. www.keatingchambers.com.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

 
In association with
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.