UK: Payment In Practice Under Part 8 Of The Local Democracy, Economic Development And Construction Act 2009

Last Updated: 7 January 2015
Article by Lisa Kingston

This final issue of Insight of 2014 focuses on an important subject that has been out of the limelight for some time, but which has come back into focus in time for the Christmas break: the payment regime under the Local Democracy, Economic Development and Construction Act 2009 ("LDEDCA").

We last wrote about the "new" (as it then was) payment regime in issue 18 of Insight, two years ago this month1. The payment regime was preceded by eight years of debate and months of delay before finally being implemented on 1 October 2011, and a flurry of case law was expected to follow in its wake. To the surprise of many, there has been no reported case law on the payment regime until very recently, when the decisions in ISG Construction Ltd v Seevic College [2014] EWHC 4007 (TCC) ("ISG v Seevic") and Harding (t/a MJ Harding Contractors) v Paice and another [2014] EWHC 3824 (TCC) ("Harding v Paice") were handed down by the Judge in Charge of the Technology and Construction Court, Mr Justice Edwards-Stuart, within two weeks of each other earlier this month.

This 42nd issue of Insight (i) provides a reminder of the key principles of the payment regime; (ii) reviews the decisions in ISG v Seevic and Harding v Paice; and (iii) provides practice points in relation to both payment and adjudication going forward in light of Mr Justice Edwards-Stuart's judgments in ISG v Seevic and Harding v Paice.

A reminder of the key principles of the payment regime

The starting point for the payment regime is the payment due date. The payment due date is either prescribed by the contract, or, in default of contractual provision, the Scheme for Construction Contracts (England and Wales) Regulations 1998 (as amended) ("the Scheme") will apply. Under the Scheme, the payment due date is whichever is the later of (a) the expiry of 30 days following the completion of the work, or (b) the making of a claim by the payee.

The payment process is as follows:

  1. The Payment Notice is due from the Employer/Main Contractor or Employer's agent (such as the Architect, QS, Engineer or contract administrator ("Payer"), or, if the contract so provides, Contractor or Subcontractor ("Payee") within five days of the due date for payment (under the Scheme), or as otherwise provided by the contract. The Payment Notice must state the sum which is considered due and the basis on which that sum is calculated. A Payment Notice must be issued even if the sum due is zero, which will most commonly be the case during the defects liability period.
  2. If no Payment Notice is served, any preceding payment application issued by the Payee will stand as the Payment Notice, provided the payment application meets the requirements of a valid Payment Notice in that it states the sum which is considered due and the basis on which that sum is calculated.
  3. If no Payment Notice is issued, or the Payment Notice served is invalid, the Payee must immediately issue a Default Payment Notice stating the sum which is considered due and the basis upon which that sum is calculated. The service of a Default Payment Notice will extend the final date for payment by the number of days between the date on which the Payment Notice should have been served and the date of service of the Default Payment Notice.
  4. If the Payer wishes to dispute the sum that is stated to be due in the Payment Application, Payment Notice or Default Payment Notice, the Payer may serve a Payless Notice stating the sum which is considered to be due and the basis on which that sum is calculated. The Payment Notice is due seven days before the final date for payment under the Scheme, or as otherwise provided by the contract. The effect of the Payless Notice is to revalue the contractor's work as at the date of service of the Payless Notice, and the revaluation can take account of any LADs, set-offs or abatements.

ISG v Seevic

The facts

The Employer, Seevic College ("Seevic") retained ISG Construction Limited ("ISG") to carry out work under the terms of a JCT Design and Build Contract 2011 ("the Contract").

Under the terms of the Contract, ISG was required to submit monthly interim payment applications stating the sum it considered to be due and the basis upon which that sum was calculated. The final date for payment was fourteen days from the due date. The Contract further contained the usual procedure whereby Seevic was to serve a Payment Notice not later than five days after the due date stating the amount it considered to be due. If Seevic intended to pay less than the amount stated in the Payment Notice or interim application, it was to serve a Pay Less Notice no later than five days before the final date for payment.

ISG duly submitted its payment application and Seevic failed to either make payment or issue a Payless Notice, as a result of which ISG referred the dispute to adjudication ("the first adjudication"). In its Notice of Adjudication, ISG asked the adjudicator to determine the contractual value of its work as at the date of the payment application. The adjudicator found that ISG was entitled to the full amount it said was due in its interim payment application (which also stood as the Payment Notice) because Seevic had failed to comply with the notice procedure set out in the Contract and serve a Payless Notice.

Four days before the decision was issued in the first adjudication, in an attempt to circumvent its failure to serve a Payless Notice, and concerned that it might lose the first adjudication, Seevic issued a Notice of Adjudication ("the second adjudication"). Seevic's Notice of Adjudication asked the adjudicator to determine the value of ISG's works as at the date of ISG's payment application.

Seevic argued that, notwithstanding the first adjudication, there was a separate dispute in relation to the value of ISG's works that could be referred to adjudication. This separate dispute provided the adjudicator with jurisdiction to decide the value of ISG's works and, accordingly, the amount that was due to ISG. The second adjudicator (who incidentally also decided the first adjudication) found that the value of the works was lower than that stated in ISG's payment application, and ordered ISG to repay the difference between the sum it had received in the first adjudication and the true value of the interim payment application as determined by the second adjudication.

Following the two adjudications, ISG made an application for (i) summary judgment to enforce the first adjudicator's decision (on the basis that its interim payment application was agreed in the absence of a valid Payless Notice to the contrary under the Contract) and (ii) a declaration that the second adjudicator's decision was unenforceable (on the basis that the second adjudicator lacked jurisdiction).

The decision

Mr Justice Edwards-Stuart noted that ISG v Seevic was very similar to Watkin Jones & Sons Ltd v Lidl UK Gmbh [2001] EWHC 453 (TCC) which was concerned with the payment regime under the JCT Standard Building Contract with Contractor's Design, 1998 edition. In that case, the employer had also failed to comply with the notice provisions under the contract, and had used adjudication proceedings as a means of revaluing the contractor's payment application.

Mr Justice Edwards-Stuart followed the decision in Watkin Jones & Sons Ltd v Lidl UK Gmbh and held that, in the absence of fraud, contractors are entitled to the amount stated in their payment application regardless of the true value of that work in circumstances where the employer does not serve a valid Payless Notice. The first adjudicator had decided that the sum claimed in the payment application was the sum that was due to ISG, that sum had been agreed by Seevic in the absence of a valid Payless Notice, and the contractual notice regime prevented any argument to the contrary. Any decision otherwise would have the effect of completely undermining the statutory regime.

The judge pointed out that the contractor's only entitlement to payment is through the interim application machinery, or at the final account stage at the end of the project: the contractor has no entitlement to be paid the value of his work during the course of the works. Equally, Seevic had no contractual entitlement to a revaluation, let alone a financial award in consequence of it.

As regards the second adjudication, Mr Justice Edwards-Stuart found that the second adjudicator lacked jurisdiction as he had decided the same or substantially the same dispute as that which was decided in the first adjudication, and his second decision was therefore unenforceable.

Harding v Paice

The facts

Mr Paice and Ms Springall (together "Paice") were property developers who engaged MJ Harding ("Harding") to carry out residential works to two properties in Surrey under the terms of a JCT Intermediate Building Contract 2011 (with amendments) ("the Contract") in March 2013.

Work commenced in April 2013, but the relationship between the parties deteriorated and Harding gave notice to terminate the Contract in January 2014. The termination provisions provided that (i) Harding was required to submit a final account in respect of the work it had carried out, including the total value of the work properly executed, up to the date of termination (under Clause 8.12.3); (ii) Paice was to pay the amount that was "properly due" in respect of the account within 28 days of submission of its final account (under Clause 8.12.5); and (iii) Paice had the option to commence adjudication or litigation within 28 days of the issue of the Final Certificate, in which case the Final Certificate ceased to be conclusive (Clause 1.9).

Paice did not make payment, and the scenario was almost identical to that in ISG v Seevic in that Harding commenced adjudication proceedings claiming it was due the sum in its final account on the basis that Paice had failed to serve a valid Payless Notice, and Paice issued counter-adjudication proceedings in an attempt to revalue Harding's final account.

Rather than let Paice's counteradjudication go ahead, Harding applied for an injunction to prevent it from proceeding. Harding argued that the failure by Paice to serve a valid Payless Notice meant that the sum in its final account became the amount that was "properly due" under Clause 8.12.3 of the Contract. Harding further argued (in identical terms to ISG) in the alternative, that the substance of its account had been already referred to adjudication and it could therefore not be revisited.

The decision

Mr Justice Edwards-Stuart noted that Clause 8.12.5 was curious because, unlike the interim payment machinery in the Contract, it did not require the employer to pay the amount stated in the contractor's interim account. Instead, the employer was to pay the amount "properly due" in respect of the account, in order to reflect the reckoning process that is inherent in final accounts.

The judge further noted that the adjudicator appeared to have proceeded on the basis that if Paice wished to pay less than the sum in Harding's account, it had to serve a valid Payless Notice. In the absence of a valid Payless Notice, the adjudicator concluded that Paice had to pay the amount stated in Harding's account (incidentally, Mr Justice Edwards- Stuart came to the same conclusion in relation to Seevic's failure to serve a Payless Notice in ISG v Seevic, albeit the crucial point to note is that ISG v Seevic concerned an interim account, not a final account).

Mr Justice Edwards-Stuart disagreed with the adjudicator's conclusion in relation to Paice's failure to serve a valid Payless Notice. He pointed out that if the adjudicator's conclusion was correct, it would deprive the employer forever of the right to challenge the contractor's account, and in some cases (for example, if the contractor had considerably overvalued its account), the contractor would be permitted to receive a windfall to which he would otherwise not be entitled, and which the employer could never recover.

In terms of the jurisdiction argument (i.e. that the substance of Harding's account had already been referred to adjudication and could therefore not be revisited), Mr Justice Edwards- Stuart held that, as a matter of fact, the adjudicator had not determined the amount "properly due" to Harding under Clause 8.12.3. Instead, the adjudicator had reached the conclusion that the absence of a valid Payless Notice automatically meant that the sum claimed in the final account was due and had to be paid.

Some practice points

  • As yet, there is no reported case law as to the level of detail that might be necessary for the breakdown of the sum due and the basis on which the sum is calculated. You should therefore err on the side of caution and include a detailed breakdown with reference to the contractual matrix, rather than provide insufficient detail and risk your Notice being rendered invalid.
  • If the employer fails to serve a Payment Notice and the contractor serves (i) a valid payment application that qualifies as a Payment Notice or (ii) a Default Payment Notice, and the employer does not serve a valid Payless Notice, then the contractor's payment application/Payment Notice or Default Payment Notice will stand. The amount due to the contractor will be the sum which is set out in the payment application/ Payment Notice or Default Payment Notice. The Notices are in practical terms a "battle of the forms" in that the last served valid Notice will trump all previous Notices, and be determinative of the sum due.
  • If the employer fails to serve a Payless Notice, it is taken to be agreeing the value stated in the payment application/Payment Notice, other than where the final account falls to be considered.
  • If the employer fails to serve a valid Payless Notice, it is no longer entitled to seek a repayment of money paid to the contractor in subsequent adjudication proceedings by seeking a revaluation of the contractor's interim account.
  • As a matter of contractual entitlement, employers can only revalue the contractor's work on (i) the valuation dates for interim applications as determined by the contract upon service of a valid Payless Notice, or (ii) at the final account stage. This is so, irrespective of the true value of any work that might be carried out by the contractor at any given stage during the course of the project.
  • It is likely, following the decision in Paice v Harding, that Payless Notices will not apply to final accounts as this would have the effect of preventing the employer from challenging the contractor's final account.

Conclusion

The decision in ISG v Seevic on interim accounts is entirely in keeping with the "pay, now, argue later" ethos of the LDEDCA, and it ought to improve cash flow for contractors. It should also put an end to the current practice regarding interim accounts, whereby some employers who fail to serve a Payless Notice commence separate adjudication proceedings in order to argue that there is a separate adjudicable dispute in relation to the value of the contractor's works. Such tactics are a throwback to the previous regime that was concerned with the "amount due",2 as opposed to the amount that is said to be due on the face of the Payment Notice or Default Payment.

As for final accounts, following Harding v Paice, it is unlikely going forward that a failure by the employer to serve a Payless Notice will be critical to its ability to challenge the contractor's final account, as this would create a very unfair situation whereby the employer would be prevented from challenging the contractor's final account for all time.

Footnotes

1. See http://www.fenwickelliott.com/files/insight_issue_18.pdf.

2. The old system was mired with problems, including how abatements should be dealt with, and it often presented difficulties where the contract provided for payment against certificates but no certificates were ever issued.

Please click here to view previous issues of Insight

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Lisa Kingston
Similar Articles
Relevancy Powered by MondaqAI
Goodman Derrick LLP
 
In association with
Related Topics
 
Similar Articles
Relevancy Powered by MondaqAI
Goodman Derrick LLP
Related Articles
 
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Registration (you must scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions