UK: Ebola & Isis: Force Majeure Under The Standard Forms

Last Updated: 5 December 2014
Article by Lisa Kingston

This 41st issue of Insight (i) examines what force majeure is, (ii) considers the approach of the domestic standard forms to situations such as the Ebola pandemic and the ISIS threat, and (iii) provides practical tips for those who might be affected by force majeure on how to mitigate the risks that might arise.


Whilst it is unlikely in the most part that the threats posed by ISIS and Ebola will ever materialise, the existence of these threats has certainly caught the attention of the business community. Ebola has caused significant trading delays and disruption in West Africa: the export of commodities is being affected (as a result of which commodity prices have increased); a number of airlines have cancelled flights; there are areas where travel is either restricted or difficult; and some contractors have declared force majeure. The ISIS threat has caused similar problems in western Iraq and north of Baghdad, where trade sanctions and embargoes have also been imposed.

What is force majeure?

In general terms, force majeure is an event that relieves the parties from performing their obligations under the contract. Such events are usually exceptional events that are deemed to be beyond the control of the parties, and which make performance of the contract physically or legally impossible, as opposed to more difficult, time-consuming or expensive. Examples may include natural disasters such as hurricanes, floods, earthquakes and other "acts of god", as well as man-made disasters including war, terrorism, civil disorder, supply shortages and labour strikes.

The doctrine of force majeure is not one that is recognised by English law; instead parties have to rely on the common law concept of frustration. Frustration occurs when a contractual obligation has become incapable of being performed because the circumstances in which performance is called for would render it a thing that is radically different from that which was contemplated by the contract. It is a difficult test to fulfil, as what is essentially required is a radical turn of events which completely changes the nature of the contractual obligations, such as a change in the law which makes performance of the contract impossible. Due to the inherent difficulties that the concept of frustration presents, contracting parties often define the circumstances under which force majeure will apply themselves, by listing possible force majeure events in their contracts. Sometimes, force majeure is not defined at all which can be very problematic, as the declaration of an event that transpires not to be a true force majeure event carries considerable risks, as will be seen below.

Force majeure under the standard forms

JCT Standard Building Contract 2011

The JCT suite makes an express reference to the concept of force majeure at clauses 2.29.14 and 8.11, but notably, it does not define force majeure, nor does it provide any examples as to what might constitute a force majeure event.

Force majeure is, however, listed as a "Relevant Event" under clause 2.29.14. Other Relevant Events include civil commotion, or the use or threat of terrorism and/or the actions of the relevant authorities in dealing with such an event or threat. Civil commotion, or the use or threat of terrorism, would probably cover any ISIS-related performance failures, but any performance failures arising out of the Ebola pandemic would probably fall under the force majeure heading as epidemics are not independently listed as being Relevant Events.

A force majeure event must be formally notified by the service of a notice under clause 2.27 which deals with Relevant Events that cause a delay, following which the architect or contract administrator must give an extension of time. Whilst an extension of time is available, there would be no corresponding claim for loss and expense as force majeure and civil commotion are not listed as "Relevant Matters" under clause 4.24.

In practical terms, it would probably be difficult to obtain an extension of time based on force majeure as a Relevant Event alone, not least because it might well initiate a debate (which may become contentious) as to whether the event was a true force majeure event, or not.

On a worst case scenario basis, Clause 8.11 provides for termination by either party by reason of force majeure (again, force majeure is not defined) in circumstances where the carrying out of the whole or substantially the whole of the works is suspended for the relevant continuous period of the length stated in the contract particulars. At the expiry of the relevant period of suspension, either party may give notice to the other that, unless the suspension ceases within seven days of receipt of the notice, the contractor's employment may be terminated on the service of a second notice which is given upon the expiry of the first notice.

Termination for reason of force majeure carries considerable risks if the force majeure event is not a true force majeure event, which at the worst might include a claim for repudiatory breach of contract and consequential losses.

NEC3

The force majeure provision under NEC3 is at clause 19.1. Clause 19.1 deals with prevention arising from 'force majeure' and includes (i) any matters that are beyond the control of the parties and (ii) events that stop the contractor completing the works at all, or by the date shown on the accepted programme.

In order for a force majeure event to fall within clause 19.1, three tests have to be satisfied. First, there must be no reasonable way of completing the works on time (it is not sufficient to show that the contractor has been delayed and that it will be expensive to make good that delay). Secondly, the force majeure event must be an event that neither party could prevent with the use of reasonable measures. The third and final part of the test emphasises the unexpected nature of force majeure in that it must have been unreasonable for an experienced contractor to have allowed for the event.

It is conceivable in principle that both ISIS and Ebola may constitute force majeure events, but it is very likely that there would be reasonable measures that could be taken to mitigate the effects of ISIS or Ebola as far as they might affect the domestic construction market, for example by re-routing the supply chain of any affected materials.

There is no need to provide specific notification of force majeure under NEC3, as force majeure is notified under Clause 16 which deals with early warning. This is an important point because it might be that an event becomes a force majeure event over the course of the contract.

If a force majeure event occurs, the project manager is to give an instruction to the contractor stating how he is to deal with the event. There are various options open to the project manager. He may decide to abandon the works on the basis that the project is no longer viable; he may change the works information with a view to circumventing the force majeure event; or he may permit progress to be delayed until the force majeure event is overcome (in which case completion will be delayed).

The management of a true force majeure event under NEC3 therefore sits with the project manager/employer, and true force majeure events carry far less risk for contractors than under the JCT form as the contractor does not bear the burden of proving the event was a true force majeure event. It is also incumbent upon the project manager to manage any time consequences of the force majeure event.

In practice, if the force majeure event stops the contractor completing the works by the date shown on the accepted programme, and it is forecast to delay completion by more than 13 weeks, the employer can elect to terminate the contract provided (i) that the event qualifies as a true force majeure event and (ii) the three force majeure tests mentioned above are satisfied. There is no equivalent provision under NEC3 for the contractor to terminate by reason of force majeure, and contractors are therefore in employers' hands as far as force majeure is concerned.

Provided that no other compensation event provides for the force majeure event, unlike JCT, the occurrence of a force majeure event is a compensation event under clause 60.1(19). This means that the contractor can recover cost. There is also scope for a further compensation event if the project manager makes a change to the works information as a result of any instruction he might issue in connection with the force majeure event.

FIDIC

FIDIC is traditionally regarded as being an international standard form but it has started to be used in the domestic context1, and it therefore warrants a mention.

Force majeure is dealt with at clause 19 of the FIDIC 1999 Red Book. It is defined as being an event which is beyond a party's control, against which that party could not reasonably have provided before entering into the contract, which could not reasonably have been avoided or overcome, and which is not substantially attributable to the other party.

Clause 19 includes a very wide and non-exhaustive list of force majeure events which includes natural catastrophes (which might cover the Ebola epidemic), rebellion, terrorism, revolution, insurrection and military or usurped power (which would probably cover ISIS).

Notices must be given within 14 days of a party being aware of the force majeure event or circumstances, or when the party should have been aware of it, and the test under FIDIC is therefore objective.

If a party is prevented from performing any of its obligations under the contract by reason of force majeure, provided the requisite notice has been given, it is entitled to an extension of time for any delay, and sometimes its costs. The point to note about FIDIC is that claims for additional costs related to rebellion, terrorism, revolution, insurrection and military or usurped power must relate to the country where the site is located, and so sites that are located near borders with countries that are affected by ISIS would be excluded. Further, there is no entitlement to additional cost for natural catastrophes (which force majeure category the Ebola pandemic is most likely to fall into), which may make it more difficult to claim for additional cost arising out of the Ebola pandemic, unless the Ebola pandemic was accepted as being a force majeure event only, and not a natural catastrophe.

Finally, if the force majeure event continues for 84 days, or for multiple periods of more than 140 days, either party can terminate the contract on the provision of 7 days' notice. The engineer then determines the contractor's entitlement to payment for completed work and any consequential costs such as demobilisation and repatriation of staff. The approach to termination is thus much more flexible than the approach that is taken under NEC3.

Practical tips when dealing with a potential or actual force majeure event

  • Review your contract and ask yourself whether the impact of Ebola and/or ISIS fits with any definition of force majeure that might appear in your contract, having regard to the ordinary and natural meaning of the force majeure definition. If there is any ambiguity as to whether the event is a true force majeure event, it will be construed against you.
  • If your force majeure event does not transpire to be a true force majeure event, then any failures in your performance (i.e. by suspending the works) may render you vulnerable to a claim for breach of contract. The safest route is to proceed with caution and not to assert force majeure until you are sure you are dealing with a true force majeure event.
  • As a belt and braces measure, check whether the definition of and procedures for claiming a force majeure under your contract have been amended. Standard form contracts are frequently amended and you do not want to be caught out.
  • If the event is a force majeure event, assess as a matter of fact whether there is, or there is the potential for there to be, an impact on (i) the works; (ii) the programme; (iii) the completion date; (iv) the cost; (v) your performance of the contract; or (vi) the performance of the other party to the contract.
  • Next, consider carefully whether there are any reasonable steps that you could take to avoid or mitigate the force majeure event, or its consequences. Could you, for example, speak to your supply chain to see if you can re-route to avoid areas that are affected by Ebola, or put contingency plans in place to protect against the worst case scenario? Focus on what you can do, as opposed to what you can't do, and if you can, agree the actions you propose to take with the other party.
  • If you are confident that the event is a force majeure event, check your contract to see if any notices are required in order to declare force majeure, and follow the appropriate contractual mechanism as to the service of those notices to the letter. If you fail to do so, your claim for force majeure may be barred and/or you may lose your entitlement to additional cost or time.
  • Ensure you have the necessary documentary evidence available to prove that the event was a true force majeure event, and make sure you can substantiate your claim for additional time and/or cost in case it is challenged further down the line.
  • If all else fails, take the low risk approach and endeavour to agree an orderly termination of the contract on mutually acceptable terms.

Conclusion

The treatment of force majeure in the JCT form reflects the traditional approach to the allocation of risk whereby the majority of risk is placed in the hands of the contractor and there is an entitlement to additional time but not cost. NEC3 is much more contractor friendly in that the management of true force majeure events rests with the project manager, and both time and cost are afforded to contractors who are adversely affected by the project manager's management of the force majeure event. FIDIC, on the other hand, reflects the more extensive nature of the risks that are undertaken by contractors who work in the international market, often contracting outside their own jurisdictions. It has an extensive list of force majeure events and provides contractors with an entitlement to additional time and cost, provided that the force majeure event is not a natural catastrophe (which may exclude the Ebola pandemic).

The approach of the standard forms to force majeure is variable. However, this is probably less problematic in the domestic context, where any force majeure event relating to Ebola or ISIS would most likely relate to supply issues regarding materials, which could probably be mitigated by the use of reasonable measures in the form of alternative suppliers or the use of comparable materials.

Ultimately, if parties wish to make more precise provision for force majeure relating to threats arising from insurgent groups and pandemics than is currently provided by the standard forms, it is open to them to make the appropriate amendments.

PS - how you can help support the fight against Ebola

The Construction and Development Partnership ("CODEP") is a construction industry led development charity that operates in London and Sierra Leone. It is currently focusing on providing relief to the quarantined, in particular the Ebola orphans, and running education forums to help spread the word about the best ways to try and prevent the spread of the Ebola virus. For further information, or to donate to the CODEP Ebola Emergency Appeal, please go to https://www.justgiving.com/codep-ebola/.

Footnote

1 It was used in both Peterborough City Council v Enterprise Managed Services Ltd [2014] EWHC 3193 (TCC) and the Forth Replacement Bridge in its amended form.

Please click here to view previous issues of Insight

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Lisa Kingston
 
In association with
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.