Turkey has finally set the ball rolling on solar development, almost one year after the first license applications were received from developers. A new round of solar tenders is expected.

The Energy Market Regulatory Authority of Turkey received the first solar license applications in June 2013. No licenses have been issued to date. The Law No. 5346 on the Utilization of Renewable Energy Resources for the Purpose of Generating Electrical Energy — the so-called renewable energy law — limits the total installed capacity of licensed solar power plants to 600 megawatts. The Ministry of Energy allocated this capacity to 27 regions. Of these 27 regions, Konya province has the largest allocated capacity with 92 megawatts in total, followed by Van and Ağrı provinces.

There was significant interest from both domestic and inter­national sponsors in the June 2013 round of applications. A total of 9,000 megawatts of solar projects were proposed.

For most, if not all, regions, multiple solar power license appli­cations were submitted for the same substation, and a tender will be required to determine the winning bidder. In the event of multiple applications, the state-owned electricity transmission company, TEİAŞ launches a tender in which bidders bid to pay TEİAŞ an amount per megawatt of capacity for the license, and TEİAŞ will award the license to the bidder offering the highest price. The price offered by the successful bidder will be paid to TEİAŞ within three years (at the latest) after the plant goes operational. Theoretically, if there are no competing bids for the same area or substation, applicants may proceed with the licens­ing and interconnection formalities.

TEİAŞ has launched three tenders so far. The first was held in May 2014 for Elazığ and Erzincan provinces in eastern Turkey. These two tenders were important, as the prices offered were expected to set a pattern for bids in the subsequent tenders. The winning applicant in Elazığ bid TL 827,000 per megawatt (US$321,000) and in Erzurum TL 68,000 (US$27,000). The differ­ence in prices is mostly due to the higher solar irradiance in Elazığ compared to Erzurum. Although a difference was expected, the high price of TL 827,000 was not.

TEİAŞ conducted the second and third rounds of solar power tenders in late January 2015, covering southeastern and western regions of Turkey. Amounts bid by the participants were even higher than in the first round tender.

The January round of tenders was launched for the following regions.

Other than the regions numbered 8 and 9, which have a rather small capacity, there are sub-capacities allocated in other regions and, hence, multiple winners. It is no surprise that the highest bids per megawatt were submitted for the Konya region, a top region for investments with its vast flat lands: TL 2,510,000 or USD$1,013,000 per megawatt. What is surprising is the prices bid per megawatt, which are seen by sector repre­sentatives as exorbitant.


Turkey enacted some much-anticipated amendments to the renewable energy law in 2011 to put in place new feed-in tariffs and other incentives. The amendments provided feed-in tariffs for licensed renewable generators that opt into the "renewable energy support mechanism." They also introduced incentives for the use of domestically-manufactured components. The support mechanism refers to both parts: the feed-in tariffs and the incen­tives to use locally-manufactured components.

Power generators that wish to opt into the support mecha­nism for a particular year must apply to the Energy Market Regulatory Authority by October 31 of the preceding year. EMRA evaluates all complete applications and publishes a preliminary list of qualified applicants on its website by November 10. The application must cover the entire power generated by a facility from renewable energy sources. In other words, once a generator opts into the support mechanism, power generated based on renewable sources cannot be sold under any other transaction outside the support mechanism such as bilateral power purchase agreements. Therefore, every year, the generator will choose between the feed-in tariff and direct sales in the power market. Settlement of power sales under the support mechanism is coor­dinated by the Market Financial Settlement Center run by TEİAŞ.

Feed-in rates are valid for 10 years for power generators that commence operations by December 31, 2020. In addition to feed-in rates, renewable energy legislation provides for incre­mental price incentives for generators that use certain domes­tically-manufactured mechanical and electromechanical components in their facilities. Incentives for using domestically-manufactured components are available for five years after a project commences operations.

The table below shows the feed-in tariffs, as well as the maximum amount of domestic component incentive that can be obtained if all domestic components listed in the legislation are used in a solar power plant:

For generators that use certain domestically-manufactured mechanical and electromechanical components in their projects, additional incentives are granted. In a photovoltaic power plant, the following components are granted the additional incentive:

The implementing regulation on domestic components requires that at least 55% of the components used in a solar facility must be locally manufactured. In order to reach this percentage, the regulation provides for different percentages for different parts, and if the total of these sum to 55% or more, then the generator is granted the incentive. For instance, in a PV module, glass is assigned 20%, frame 15%, back sheet 20%, junc­tion box 20%, and ribbon 5%. If a generator uses locally-manu­factured glass, frame and junction box, then it will be granted the additional US$13 incentive for use of locally-manufactured PV modules.

The legislation requires that components be actually manu­factured in Turkey; mere assembly of parts is not sufficient.

In order to benefit from the domestic component price incen­tives, generators must submit two items to the Ministry of Energy. One is a "domestic manufacturing certificate" attesting to the domestic origin of the relevant component, to be prepared by a certified public accountant using a form provided in the regulations and approved by the Chamber of Industry or Chamber of Industry and Commerce with which the component supplier is affiliated. The other is a "product certificate" to be prepared by a national accreditation agency recognized by the International Accreditation Forum and attesting to the conformity of the component to national or international standards.

Currently, the local manufacturing sector is underdeveloped and generators are heavily dependent on imported products.

In addition, all renewable energy generators enjoy three other incentives, including reduced licensing fees and priority in grid connection.

The first is payment of only 10% of the license application fee otherwise applicable, and exemption, for a period of eight years, from the annual license fee.

The second is priority in grid connection.

The third is an 85% reduction in permitting costs, rent and other costs of gaining rights of access and usage of state-owned land (available only to projects that are in operation before December 31, 2015). The break on rent or easement fees runs for 10 years after a project commences operation.

In the wake of the significant amounts bid in the recent tenders, the solar power sector has been discussing how feasible the projects will be.

Most winners are subsidiaries of leading Turkish energy com­panies, but there are also international players. One might inter­pret this as a good sign that big players are ready to invest large sums to proceed with solar projects.

However, the sector's skepticism is understandable, especially in view of the bitter experience with wind power tenders a few years ago, where applicants ended up paying TEİAŞ large amounts of money that made their projects infeasible.

There are still 16 provinces or regions awaiting solar tenders.

Pre-Licensing Process

All generators are issued a preliminary license during the pre-construction stage that will be replaced by a permanent license at the beginning of construction. The winning bidders in the tenders that have already taken place will be granted pre-licenses.

Solar bidders had first to get an authorization from the Directorate of Meteorology to set up a measurement station on the site and then submit to EMRA measuring data of at least one year, including an on-site measurement conducted for at least six months, as part of their applications. The application package also includes a letter of guarantee in an amount calculated based on the contemplated installed capacity and the applicant's orga­nizational documentation with the required statutory provisions. Applicants must be a joint stock company or a limited company.

During the pre-licensing period, the applicant must obtain the required permits, approvals and licenses to start construction such as zoning permits and environmental clearances, and also secure title to or a right to use the relevant land. No solar power plant is allowed on agricultural lands.

The pre-licensing period is 24 months, unless there is a force majeure event (unavoidable and unforeseeable events beyond the reasonable control of the generator, including acts of God and war) or the period is extended by EMRA, which has authority to extend for up to another 12 months. If the generator fails to secure the required permits, approvals or licenses within the pre-licensing term, then no permanent license will be issued.

No direct or indirect change in the shareholding structure of the generator is usually allowed during the pre-licensing period. Any such change will lead to revocation of the pre-license. However, a change is allowed in the shareholding structure of a foreign shareholder of the pre-license holder. For instance, shares in the foreign parent of a pre-license holder may change hands.

Once all obligations of the pre-license period are fulfilled, then the pre-license holder may apply for a permanent license. Such licenses are granted for a minimum of 10 years and maximum of 49 years.

There are also some share transfer restrictions applicable to license holders. Any direct or indirect acquisition of at least 10% of the shares of a licensed company (5% in public companies), or share transfers resulting in a change of control, require prior approval by EMRA.

The legislation grants a step-in right to lenders in limited or non-recourse project financings. Lenders may ask EMRA to approve the transfer of the license to another legal entity, pro­vided that this entity assumes all the obligations of the related license holder.

Distributed Generation

Another area of interest is dis­tributed generation or so-called "unlicensed generation." As the name suggests, facilities with a generating capacity of up to a certain limit are exempted from pre- licensing requirements. The upper limit has been recently taken to one megawatt from 500 kilowatts, and the Council of Ministers, without any legislative amendment, is authorized to increase the limit up to 5 megawatts.

Solar power has been used for water heating for a long time in Turkey (without the need for any license or permit). In view of increasing electricity prices and falling cost of photovoltaic technology, Turkey has seen an increasing interest from com­mercial players and "prosumers" in roof-top installations.

In addition to exemption from licensing requirements, unli­censed generators are exempted from corporate formalities imposed on licensed generators. These generators do not have to establish a legal entity in order to operate. However, they must still obtain approval from the distribution company in the rele­vant region for grid connection and system usage and secure land use rights and environmental clearance. As far as these formalities are concerned, the renewable energy law does not distinguish between very small-scale unlicensed projects and larger projects, for example, one-megawatt projects.

Although the increase to one megawatt has been a positive development, Turkey has a long way to go to reach the level of distributed solar generation in other countries like the United States and Japan. Each unlicensed facility is required by law to be connected to a consumption unit, and any excess power not consumed in this unit can be sold to the grid. It is not clear whether the same generator may set up multiple facilities (for instance 10 facilities each having an installed capacity of one megawatt) within the same region, and sell the excess power to the grid. Normally a generator planning an installed capacity bigger than one megawatt would have to secure a license from EMRA. The legislation neither allows nor prohibits such structure. However, the legislation itself provides that, as a general rule, license-exempted generation must be used by consumers to meet their own power needs and not primarily for trading. Therefore, the structure involving multiple facilities with a maximum of one megawatt of installed capacity may be viewed by the authorities as circumventing the rules for licensed genera­tion, and the structure has yet to be tested.

Power generated by an unlicensed facility and not consumed in the consumption unit can be sold to the grid, and this excess power will benefit from the feed-in rate and domestic compo­nent incentives, if applicable.

Unlicensed facilities may be transferred after provisional acceptance. A step-in right, as described earlier for licensed gen­eration, is also possible for banks and other financial institutions that have provided limited or non-recourse project financing to the unlicensed generator.

What Lies Ahead?

Those who keep abreast of Turkish solar power are no strangers to government targets announced in multiple gigawatts to be reached by 2023, the centenary of the Turkish Republic.

The latest of these targets was announced in Turkey's first National Renewable Energy Action Plan prepared in line with the European Union's Renewable Energy Directive on the Promotion of the Use of Energy from Renewable Sources (Directive 2009/28/EC (1)), with support from the European Bank for Reconstruction and Development. According to the Turkish action plan, Turkey pledges to install 60 gigawatts in renewable energy capacity by 2023, five gigawatts of which will be solar.

It seems that Turkey's solar potential will finally be tapped. Turkey has an average annual total sunshine duration of 2,640 hours; a total of 7.2 hours per day, which gives Turkey the biggest potential among European countries after Spain.

Once the first pre-licenses are granted, the authorities are expected to launch a new round of license applications, and this time without the countrywide limit and with a faster process.

The real hurdle ahead for solar power is not the investment costs (which have been decreasing due to advancement of pho­tovoltaic technology), but the 600-megawatt countrywide limit. The local manufacturing sector is also expected to grow after the pre-licenses are granted and investors have a clearer view of the solar power market in Turkey.

Growth in rooftop solar installations is expected to continue. It is still not clear whether the regulators will require aggrega­tion of multiple small generating facilities with a single owner in the same general location for purposes of limiting access to net metering where excess generation is sold to the grid. However, more investment (both domestic and international) is expected.

Article by Ekin Inal, with the Bilgiç Attorney Partnership in Istanbul.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.