On December 31, 2015, the Ministry of Energy ("SENER") published a call (the "Call") addressed parties interested in participating in the Wholesale Power Market, providing the schedule that the National Center for Energy Control ("CENACE") must observe to authorize the start of operations and the operations start-up statement of the Short-Term Market ("MCP"). The schedule for the beginning of operations of the MCP during 2016 is as follows:
1. Test Reports and Final Test Reports1
Event | Baja California System | National Interconnected System |
Registration System | January 5 | January 7 |
Offer System | January 5 | January 7 |
Market System | January 5 | January 7 |
Measuring System | January 6 | January 8 |
Billing and Settlement System | January 6 | January 8 |
Guarantees Management System | January 7 | January 8 |
2. General Schedule for the MCP operations start-up
Event | Date |
CENACE receives requests regarding market participant agreements | Starting from January 1 |
CENACE receives requests to register physical assets (Power Plants and Load Centers) to be included in the MCP | Starting from January 1 |
CENACE ensures that the registered physical assets are included in the MCP systems for its first day of operation | No later than January 19 |
3. Specific Schedule for the MCP operations start-up
Event | Baja California System | National Interconnected System | Baja California Sur Interconnected System |
CENACE receives purchase and sell offers for the MCP2 | Starting from January 20 | Starting from January 22 | Starting from January 3 |
SENER issues the statement that the markets included in the MCP may start operations | January 25 | January 27 | February 8 |
CENACE starts operations in the Day Ahead Market | January 26 | January 28 | February 9 |
CENACE starts operations in the Real Time Market | January 27 | January 29 | February 10 |
CENACE sends the initial statements regarding the first day of the MCP | February 2 | February 4 | February 16 |
SENER issues the operations entry statement, retroactive to the corresponding operations days2 | February 9 | February 11 | February 23 |
SENER may adjust the dates if required.
Our firm will maintain you informed regarding the development of this important issue.
Footnotes
[1] From January 11 up to January 22, CENACE will be testing all the systems and processes interactively with market participants.
[2] Operation Day for the MCP: For Baja California System: January 27. For the National Interconnected System: January 3. For the Baja California Sur Interconnected System: February 10.
The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.