I. MP High Court on foreign seated arbitration

The division bench of the Madhya Pradesh High Court upheld an arbitration agreement which mandated two Indian Parties to take recourse to a foreign seated arbitration while applying foreign substantive law.

The Appellant, Sasan Power Limited ("Sasan Power"), which is a wholly owned subsidiary of Reliance Power Ltd. and the Respondent, North American Coal Corporation India ("NACC-India") a company incorporated in India, had entered into an association agreement for mine development and operation. NACC-India is a subsidiary of North America Coal Corporation, U.S., which had originally signed an Memorandum of Understanding with Reliance Power Ltd. The original agreement inter alia, provided for resolution of disputes by way of arbitration to be administered by ICC in London, England, under laws of the United Kingdom. In 2011, NACC-US vide an assignment agreement assigned all its rights, liabilities and obligations under the original association agreement to NACC-India.

In 2014, NACC-India terminated the agreement and filed a request for arbitration claiming compensation. Sasan Power objected to the request for arbitration and filed a suit seeking an anti-arbitration injunction before the District Court, which was subsequently granted. NACC-US filed another request for arbitration before the ICC. Sasan Power filed a second suit inter alia challenging the request for arbitration as filed by NACC-US. NACC-India filed applications requesting the District Court to reject the plaint under Order VII Rule 11 of the Code of Civil Procedure, 1908 and invoked Section 45 of the Arbitration and Conciliation Act, 1996. NACC - India also requested the Court for vacation of the anti-arbitration injunction. The District Court allowed this and dismissed the suit filed by Sasan Power. Sasan Power subsequently challenged the order of the District Court in an appeal to the High Court. A variety of issues were put before the court, but one with utmost importance was whether two Indian Parties could choose a foreign seat of arbitration applying foreign substantive law.

The High Court relied on the judgment in, Atlas Exports Industries v. Kodak and Company("Atlas Exports") where it was held that Section 28 read with Exception 1 of the section, does not have the application of putting a bar on foreign seated arbitration and therefore, the agreement in the present case is not void. The court also said that in a case where two Indian parties freely enter into an agreement which provides for arbitration at a foreign seat as the means of dispute resolution, this does not render the agreement void or make it opposed to public policy as held in TDM Infrastructure (P) Ltd. Vs. UE Development India (P) Limited.

The court refused to rely on TDM Infrastructure judgment on the grounds that Atlas Exports was delivered by a larger bench and that the scope of TDM Infrastructure was limited to Section 11 of the Arbitration and Conciliation Act, 1996, which was clarified by the Supreme Court by means of an Official Corrigendum. The court also held that the scheme of the Arbitration and Conciliation Act, 1996 indicated that for classifying arbitration proceeding as an international commercial arbitration depends only on the nationality of the parties which is relevant only for the appointment of arbitrator(s) under Section 11 of the Act. The court was of the view that the nationality of the parties would not influence the applicability of Part II of the Act as it depends only on the seat of arbitration. The High Court further observed that where the parties had agreed to resolve their disputes using arbitration, it is the duty of the courts to give effect to the intention of the parties to the agreement and interference would be appropriate only in cases where the agreement was found to be null, void or inoperative. The Court finally observed that, when the parties have decided to resolve their disputes by arbitration and chose to have a foreign-seated arbitration i.e., arbitration in foreign country, then Part I of the Act would not be applicable. Further, in cases where the agreement in question fulfils the requirements under Section 44 of the Act, Part II of the Act would be applicable.

Source: First Appeal 310 of 2015, Madhya Pradesh High Court

VA View

The judgment does aid many foreign subsidiary companies, incorporated in India, who would want to arbitrate issues in a foreign country especially issues that are not arbitrable in India. However, till such time this issue is finally decided by the Supreme Court of India, one needs to proceed with caution in deciding whether two Indian parties can agree to have a foreign seated arbitration.

II. Government passes ordinance to reform arbitration laws

On October 23, 2015, the President of India has promulgated the Arbitration and Conciliation (Amendment) Ordinance, 2015 to amend the provisions of Arbitration and Conciliation Act, 1996. Some of significant changes are as follows:

  1. The provisions of Section 9 (interim measures by court), 27 (court assistance in taking evidence) and 37 (1)(a) (appeal from order granting or refusing interim measure by courts or setting aside or refusing to set aside and arbitral award under Section 34) and 37(3) (no second appeal to lie from an order passed in appeal) will apply to international commercial arbitration even if the place of arbitration is outside India and the arbitral award made or to be made is enforceable under Part II of the Arbitration and Conciliation Act, 1996.
  2. If, under Section 9 of the Arbitration and Conciliation Act, 1996 the court passes any interim measure of protection then, the arbitral proceedings must commence within 90 days of the court doing so or within such further time as the court may determine.
  3. Once the arbitral tribunal is constituted, the court shall not entertain an application for interim measures under sub-section (1) of Section 9 unless the court finds that circumstances exists which may not render the remedy provided under section 17 efficacious.
  4. The orders passed by the arbitral tribunal under Section 17 is deemed to be an order of the court for all purposes and shall be enforceable under the Code of Civil Procedure, 1908 in the same manner as if it were an order of the court.
  5. Section 29A provides that an award shall be made by the arbitral tribunal within the period of twelve months from the date the arbitral tribunal enters upon the reference. This period may be extended for a period not exceeding six months with the consent of the parties.
  6. If the award is not made within 12 months or within the extended period as specified, the mandate of the arbitrator(s) shall terminate unless the court has either prior to or after the expiry of the period so specified, extended the period. However, if the court finds that the arbitral proceedings have been delayed for reasons attributable to the arbitral tribunal then the court may order reduction of fees of arbitrator(s) by not exceeding 5% for each month of such delay. Further, it is open to the court to substitute one or all of the arbitrators while extending the period to complete the arbitration proceedings. It is clarified that the when the court substitutes one or all of the arbitrators then the arbitral proceedings shall continue from the stage already reached and on the basis of the evidence and material already on record, and the arbitrator(s) appointed under this section shall be deemed to have received the evidence and material.
  7. Section 29B provides that the parties to an arbitration agreement, may, at any stage either before or at any time of appointment of the arbitral tribunal, agree in writing to have their dispute resolved by fast track procedure which include among others that the arbitral tribunal may decide the dispute on the basis of written pleadings, documents and submissions filed by the parties without any oral hearing.
  8. An arbitral award will be in conflict with the public policy of India, only if

    1. The making of the award was induced or affected by fraud or corruption or was in violation of Section 75 (Confidentiality) or Section 81 (Admissibility of evidence in other proceedings); or
    2. It is in contravention with the fundamental policy of Indian law; or
    3. It is in conflict with the most basic notions of morality or justice.
    An arbitral award arising out of arbitrations, other than international commercial arbitrations, may also be set aside by the court, if the court finds that the award is vitiated by patent illegality appearing on the face of the award provided it shall not be set aside merely on the ground of an erroneous application of law or by reappreciation of evidence.

The Ordinance clarifies that the test as to whether there is a contravention with the fundamental policy of India law shall not entail a review on the merits of the dispute.


VA View

The Ordinance will have to be placed as a Bill before parliament and only if approved will be converted into an Act. However, if the Bill is not approved by the parliament then the Government of India can re-promulgate the Ordinance. The Ordinance reflects the intent of the Government of India to ensure that there is a quick redressal of the dispute and this is evident from the fact that specific timelines are specified in the Ordinance with respect to initiation of the arbitral proceeding and the time by which the arbitral proceeding should conclude. Also, there is emphasis to ensure that spiralling costs of arbitration should not deter parties to resort to arbitration as a means of dispute resolution therefore this intent is seen by introducing a Model Fee Schedule in the Fourth Schedule of the Ordinance.

III. IRDA guidelines for Indian-owned and controlled insurance companies

The Insurance Laws (Amendment) Act, 2015, passed during Parliament's budget session, allowed insurance companies to raise their foreign ownership from 26% to 49%, with the requirement that the company be Indian owned and controlled. Indian ownership is defined by way of Indian Insurance Companies (Foreign Investment) Rules, 2015. This was subsequently amended by Indian Insurance Companies (Foreign Investment) Amendment Rules, 2015. Control can be exercised by the virtue of (a) Shareholding; or (b) Management rights; or (c) Shareholders agreements; or (d)Voting agreements; or (e) Any other manner as per applicable laws.

Now, the insurance regulator IRDA has brought a new set of rules to define "Indian control" on insurance companies in India. These rules, framed as Guidelines for "Indian Owned and Controlled" insurance companies, were notified by IRDA on October 19, 2015 ("Control Guidelines").

The Indian insurance company shall ensure the following:

  1. Majority of the directors excluding independent directors should be nominated by the Indian promoter(s) / Indian investor(s);
  2. Appointment of key management person including Chief Executive Officer/ Managing Director /Principal officer should be through the Board of Directors or by the Indian promoter (s) and / or Indian investor (s). However, key management person(s) excluding CEO may be nominated by the foreign investor provided that the appointment of such key management person is approved by the Board of Directors, wherein majority of the directors excluding independent directors are the nominees of Indian promoter(s) / Indian investor(s).
  3. The Indian shareholder(s) of Indian insurance companies must have control over the formulation of significant policies of the insurance company and the overall management of the company, subject to approval of the Board of Directors, provided that the constitution of the Board is compliant with para (I) above.
  4. Where the Chairman of the Board is having a casting vote, such Chairman should be nominated by the Indian promoter(s) and / or Indian investor(s);
  5. Quorum shall mean and include presence of majority of the Indian directors irrespective of whether a foreign investor's nominee is present or not. The right of a foreign investor's nominee to constitute valid quorum for meetings is only a protective right and to that extent would not amount to control as long as the presence of nominees of Indian Promoter(s)/ Investor(s) are also mandatorily taken into account for the purposes of quorum. The provisions of Companies Act, 2013 shall come into force in case of an adjournment.

In order to ensure that the Indian insurance companies are in compliance with the Control Guidelines, IRDA has come out with an additional requirement of filing an undertaking duly signed by CEO and CCO. Such undertaking needs to be appended with a CTC of board resolution and amended certified copy of agreement/ JV agreement, if applicable. Companies existing prior to issuance of Control Guidelines are required to comply within a period of 3 months and companies existing post issuance of Control Guidelines are required to comply before grant of certificate of registration.

Source: =1

VA View

In view of the requirements of the Control Guidelines, existing shareholder agreements in Indian insurance companies will need to be reviewed carefully in respect of shareholder and other rights of foreign investors and will need to be structured appropriately to ensure that such rights are not in contravention of the IRDA Control Guidelines.

IV. Apex Court's decision on arbitration clauses in insurance dispute

In the dispute between Essar Steel India Limited ("ESIL") and New India Assurance Company (NIAC), the Supreme Court has ordered the insurance company to honor the arbitration clause in the agreement and appoint an arbitrator to adjudicate the dispute between the parties.

The facts of the dispute lie in the Naxal attacks on a pipeline of ESIL in 2010. ESIL had an insurance cover of Rs 19,000 crore on the pipeline, covering the business loss in case of any such disruption. ESIL claimed a total property loss of Rs. 9.79 crore and a business interruption loss of ` 881 crore.

But NIAC turned down the claim saying that there was an earlier Naxalite attack on the company site which it did not disclose while taking the policy. The company then approached the Bombay High Court and argued that it had a natural calamity policy which was rejected by the insurance company, citing the incidence of terrorism and directed it to buy a specific terrorism cover. The Bombay High Court ruled in favor of ESIL and directed both parties to appoint arbitrators. The insurance company then challenged the high court order in the apex court, which was also of the view that it would be open to the arbitrators to decide all issues, including the issues regarding the alleged fraud. The apex court dismissed the plea filed by NIAC.

VA View

The ruling is likely to set a precedent in similar cases where insurance companies are refusing to consider the arbitration clause, citing various reasons for not honouring claims even after collecting huge premium.

V. Liberalization of FDI in White Label ATM companies

White-label ATM operators are non-bank companies who own and run ATMs as a business. Their revenue is mainly from inter-change fee and advertisements. White Label ATM operators are authorized under Payment & Settlement Systems Act, 2007 by the Reserve Bank of India.

The government has allowed 100 per cent foreign direct investment (FDI) under the automatic route for white-label ATM companies. The 100 per cent FDI under the automatic route is subject to the condition that any non-bank entity planning to set up white-label ATM should have a minimum net worth of ` 100 crore, maintainable at all times. In the case of entities operating in any other 18 non-banking finance companies (NBFC) activities, foreign investment in white-label ATMs should comply with the sectoral minimum capitalization norms.


© 2015, Vaish Associates, Advocates,
All rights reserved with Vaish Associates, Advocates, 10, Hailey Road, Flat No. 5-7, New Delhi-110001, India.

The content of this article is intended to provide a general guide to the subject matter. Specialist professional advice should be sought about your specific circumstances. The views expressed in this article are solely of the authors of this article.

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

In association with
Related Video
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.