India: Infrastructure and Energy Quarterly - Vollume III: Issue IV - April/May, 2015

Last Updated: 9 October 2015
Article by DSK Legal

Engineering, Procurement and Construction:

Contemporary Challenges in Engineering, Procurement and Construction Arrangements

Engineering, Procurement and Construction (EPC) forms the soul of project development across various sectors, which is critical for sustaining the robust growth of the Indian economy. The success of any project is directly dependent on the successful implementation and completion of EPC. EPC contracts are the tool to achieve this purpose. In this article it is our endeavor to highlight some of the challenges involved in an EPC arrangement  from the perspective of the project developer and the contractor.

The two critical components of project development are time & cost. The parties would always seek to avoid delay in project completion and cost overrun.

The roles and responsibilities of the project developer and the contractor are agreed to in this context (i.e. cost and time) having due regard to the risks involved in a specific project. Thus, principally, the EPC contract is all about efficient risk management by the project developer and the contractor.

Risk management involves the following aspects:

a) Identification of risk – It is imperative to identify the risks under various categories that are associated with the specific project including by way of reference to and extensive analysis of the pre-feasibility and feasibility study/ies conducted for the said project.

b) Risk analysis – Determination of the nature of risk and its likely impact to enable the parties to decide on the party that is best suited to take the risk.

c) Risk allocation – Risk is allocated to create an efficient environment for the parties involved in the project such that the party who gains the maximum for taking the risk or is in the best position to manage the risk, will take the said risk.

d) Managing the Risk- Upon the risk being allocated to a party the said party has the ability to manage the risk appropriately by sharing the risk or the consequences of the risk with a third party.

Types of Risks

For the sake of brevity, we have categorized the contemporary risks that we intend to deal with in this article under the following heads: (a) Financial Risks; (b) Regulatory/Policy Risks; and (c) Other Risks.

Financial Risks

Interest Rate and Exchange Rate

Every project requires huge capital investment, bulk of which is raised in the form of debt where the interest rate has been spiraling up. According to recent market trends, many projects are being funded by way of external debt in foreign currency. Such external debts come at floating interest rate being benchmarked to the LIBOR, an acceptable benchmark under the ECB Regulations prescribed by the Reserve Bank of India. Further, the unprecedented change in exchange rate, more particularly the rising value of the United States Dollar against the Indian Rupee, has adversely impacted costs of such borrowing. The profitability of any project is impacted to a large extent by these factors. The commonly accepted method to address the interest rate and exchange rate fluctuation is entering into of hedging contracts by the party taking the risk on price of the project.

Inflation Rate

Another major financial risk is the rate of inflation which has a huge impact on the commercial dynamics of the project as it affects the pricing of the material inputs for the project. The rate of inflation in past few years has been growing in unwarranted manner. By way of illustration, the price of cement which is an essential raw material for most projects has risen sharply in past few years.

The different formulae linked with various indices are prescribed under the Model EPC Agreement for determination of price adjustment. However, it is essential to ascertain whether these formulae are close to the contractor's procurement model as prices may differ from region to region. Further, the indices used for benchmark prices may not be realistic thereby creating serious risks.

Regulatory/Policy Risks

The recent decision of the Supreme Court whereby the coal blocks allocations made since 1993 were cancelled has created a sense of fear amongst project developers that the project, after being awarded, could still be affected by the courts based on factors to which the contractor may not be privy. It is seen that such risks are not specifically identified and allocated in the EPC Agreements as these are project risks inherent to the role of the project developer. However, the implication of such risk does not remain confined to the project developer but has trickling effect on others including the contractor. These risks could be mitigated by the contractor inter alia by way of consequential loss insurance policy being obtained by the contractor or by seeking a security from the project developer. But for the project developer, the only practical risk mitigation remedy seems to be obtaining consequential loss insurance policy. Thus, it is important to assess if cancellation of the grant of the project of the impact on a project due to a court order/regulatory action can be insured under consequential loss insurance policy and the cost of premium for such policies as it has direct impact on the profit margin of the project developer.

As far as environmental clearances/consents are concerned it is always advisable to ensure that the project has received such clearances/consents before the commencement of EPC work. Further, in an EPC contract, the responsibility to obtain local permits and clearances are sought to be shifted to the contractor. The process for obtaining local permits and clearances may be cumbersome and may delay the project. EPC contractors should factor this risk and seek suitable protection by way of adjustment of time and price.

Another important policy risk is uncertainty with regards to fiscal incentives offered by the Government (Central, State and local). Many projects across different sectors enjoy various fiscal incentives pertaining to income tax, excise duties, custom duties, stamp duties etc. These are fiscal policies of the Government and are subject to change in future on account of the social, economic and political conditions prevailing at the relevant time. Withdrawal of such incentives has bearing on the cost of development of the project. Therefore, the price for the project should factor all incentives that can be categorically identified and variation in these incentives should be allowed as factor for price adjustment.

Other Risks

There has been a rising trend of consortium bidding. Consortium bidding was considered beneficial from taxation point of view as supply of capital goods by foreign bidder to the owner, being import of equipment was not considered to give rise to payment of income tax by foreign supplier under Income-Tax Act, 1961. However, Income Tax Act applies to income derived by an association of persons in India. Recent rulings on the subject suggest that such consortium will be treated as an association of persons and therefore, income from offshore supply becomes taxable in India. The Authority for Advance Rulings (AAR) in its ruling in 'Alstom Transport SA' on June 7, 2012 applying the 'look at' approach of Supreme Court in Vodafone case, held that a contract for design, manufacture, supply, installation, testing and commissioning of signaling/train control and communications systems is a composite contract and income from offshore supply was taxable in India, even though property in such goods was transferred outside India. Earlier in the case of 'Linde AG' on March 20, 2012 in case of consortium bidding, AAR had reached a similar conclusion based on facts of that case. Therefore, it is imperative that due care is exercised in structuring the EPC contracts in case of consortium bidding, taking the potential tax exposures into consideration.

Different governing laws and jurisdictions in different contracts for same project may pose unnecessary risks for a project. For example, in case of consortium bidding, the consortium partners enter into a consortium agreement to govern their inter-se relationship. If the consortium agreement is governed by laws of a foreign country and EPC contract is governed by Indian laws, this may cause serious problem as to interpretation of responsibilities of partners and enforcement of contract.

Further, while it is common to have mediation mechanism being resorted to before invoking arbitration, creation of multi-layered structure for dispute resolution in pre-arbitration stage may cause substantial delay. Further, institutional arbitration is expected to scores better than leaving appointment of arbitrator to the discretion of parties under an ad-hoc mechanism. Qualification of arbitrator and their integrity is essential for an efficient and fair adjudication. Selection of arbitrator in an ad-hoc manner may adversely affect this process. Therefore, parties should consider opting for institutional arbitration wherein arbitrators are to be selected from a panel of arbitrators.


In view of the above, it is important to upfront identify and suitably address all the risks so identified in relation to a specific project with prudent risk management and appropriately worded contracts. It is in this context one may note that the disputes in relation to EPC contracts currently pending are reported to involve Rs. 1 Lakh Crores.

Augmenting Grid Connected Solar Power Capacity in India:

Scheme for addition of 15,000 MW Grid Connected Solar PV Power Capacity under the National Solar Mission

The first phase of India's National Solar Mission (2010 – 2013) had set a target of adding 1100 MW grid-connected solar power generation capacity. However, a total of 1685 MW grid-connected solar power generation capacity was added during this time under various schemes in India. To further augment and tap solar power in India, the Government of India had laid down a scheme for setting up of 15,000 MW grid-connected solar PV power projects in India under the National Solar Mission.

The Ministry of New and Renewable Energy (Grid Solar Power Division) vide its Notification dated March 5, 2015 has notified the assent of the President of India for the implementation of the scheme (Scheme) for setting up of 15,000 MW of grid connected solar photovoltaic power plants (Project) under the National Solar Mission (Solar Mission). The aforesaid grid connected solar photovoltaic power plants are proposed to be set up under the Solar Mission through project developers from the private and/ or public sector over a period of 5 (five) years from the financial year 2014-15 to 2018-19 and the National Thermal Power Corporation Limited and the NTPC Vidyut Vyapar Nigam Limited shall be implementing agency for the Scheme.

The Scheme proposes to achieve the said capacity augmentation in 3 (three) tranches as under:

(1) Tranche I (2014-15 to 2016-17): 3000 MW under mechanism of bundling with unallocated coal based thermal power and fixed levellised tariffs;

(2) Tranche II (2015-16 to 2017-18): 5,000 MW with some support from the Government to be decided after getting some experience while implementing Tranche – I; and

(3) Tranche III (2016-17 to 2018-19): Balance 7,000 MW without any financial support from the Government.

Tranche I of the Project, which will comprise of Batch II of Phase II of National Solar Mission, is envisaged to augment 3,000 MW solar photovoltaic power capacity to the national solar grid. Tranche I of the Project is proposed to be based on bundling of solar power with unallocated thermal power in the ratio 2:1. The 1,500 MW of unallocated thermal power which shall be required for this purpose has already been made available by the Ministry of Power. The solar power projects under Tranche I shall be developed by private and/or public companies selected through international competitive e-bidding. Under Tranche I, the solar power plants shall have a minimum capacity of 10 MW.

Out of the total 3,000 MW capacity under Tranche I, 1,000 MW capacity solar power projects shall be developed in the State of Andhra Pradesh, where land has already been identified for the purpose of setting up of a solar park.

While the Ministry of New and Renewable Energy's Notification dated March 5, 2015 sets out the mechanism to be adopted for the setting up of solar power projects under Tranche I, the mechanism for the Tranche II and Tranche III of the Scheme has not been devised yet. The Ministry of New and Renewable Energy proposes to devise suitable mechanisms for the Tranche II and Tranche III of the Scheme, in which minimum support will be provided to the project developers by the Government, after gaining experience from the implementation of the Tranche I of the Scheme.

Other aspects of the Scheme:

(1) Like the previous projects under the National Solar Mission, the Projects to be developed under the Scheme shall have certain portion of the total capacity earmarked to be set up using Domestic Content Requirement (DCR).

(2) The DCR shall be technology agnostic and shall be applied to both crystalline silicon technology and thin film SPV cells/ modules technology.

(3) State nodal agencies appointed for the purpose shall be responsible for: (a) grid connectivity; (b) land acquisition; (c) water availability; (d) monitoring of progress of projects; (e) commissioning; and (f) related activities.

Ensuring bankability of the Power Purchase Agreements (PPAs): A payment security mechanism/ working capital fund has been proposed to be set up with a total estimated corpus of Rs. 2,300 Crore for ensuring 3 (three) month's payment for the bundled capacity of 4,500 MW (3,000 MW solar power capacity together with 1,500 MW coal based thermal power). The aforesaid fund shall ensure the bankability of the PPAs which shall be entered into for the Projects under the Scheme.

The Mines and Minerals (Development and Regulation) (Amendment) Act, 2015

Removing discretion in grant of mineral concessions and making auction the sole method for allotment

The Mines and Minerals (Development and Regulation) (Amendment) Act, 2015 (MMDR Act, 2015) which amends certain key provisions of the Mines and Minerals (Development and Regulation) Act, 1957 (MMDR Act, 1957) has finally been passed by both the houses of the Parliament.

Amending the MMDR Act, 1957 was imperative in light of the various problems which the mining industry was facing and in light of the Supreme Court of India's judgment dated September 24, 2014 in the matter of Manohar Lal Sharma v. The Principle Secretary and Ors. To address and resolve the issue the Government of India had already taken the ordinance route and had passed the Mines and Minerals (Development and Regulation) Amendment Ordinance, 2015 on January 12, 2015. Now with the MMDR Act, 2015 being passed, the mining industry should be regularized and the much required transparency in the allotment process of the mining concessions will be brought about.

The key changes brought about by way of the amendments in the MMDR Act, 2015 are as under:

(1) One of the key purposes of the MMDR Act, 2015 was removal of discretion from the process of allotment of the mining concessions. The MMDR Act, 2015 has addressed the issue and it stipulates that all mineral concessions are to be granted only by way of auctions. This shall not only remove discretion from the process of grant of mining concessions but will also make the entire process more transparent, which should attract more private players in the mining industry and will eventually augment the growth of the capital intensive mining and minerals sector.

(2) The tenure of the mining concessions to be granted under the MMDR Act, 2015 has been increased from 30 (thirty) years to 50 (fifty) years. However, the MMDR Act, 2015 prohibits any renewal of the mining concessions granted under the MMDR Act, 2015 after the said tenure of 50 (fifty) years. Under the MMDR Act, 1957, the mining concessions were granted for an initial tenure of 30 (thirty) years after the expiry of which the concessions were further renewable. Therefore, under the MMDR Act, 2015 after the expiry of the term of 50 (fifty) years, there shall be no renewal of any mining concession and the same shall be put up for auction.

(3) The pendency of applications for renewals of the mining concessions granted under the MMDR Act, 1957 had greatly affected the mining industries and its output. The MMDR Act, 2015 addressed this issue under Section 8A(5) and Section 8A(6) by extending the tenure of all: (1) mining (captive) concessions granted under the MMDR Act, 1957 up to March 31, 2030 or until the completion of the period of renewal already granted, whichever is later; and (2) mining (non-captive) concessions granted under the MMDR Act, 1957 up to March 31, 2020 or until the completion of the period of renewal already granted, whichever is later.

(4) The MMDR Act, 2015 requires the setting up of a District Mineral Foundation (DMF) in every district where mining activities are carried out. This provision has been included in the MMDR Act, 2015 for safeguarding the interests of the people affected in the areas on account of the mining activities. The MMDR Act, 2015 also requires the State Governments, while framing the rules for giving effect to the DMF, to conform to the provisions of Panchayats (Extensions to Scheduled Areas) Act, 1996, Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 and the provisions of the Fifth and Sixth Schedules of the Constitution of India.

(5) In order to address the inadequacy of mining explorations, the MMDR Act, 2015 has proposed to establish a National Mineral Exploration Trust (NMET), a dedicated fund for undertaking mining exploration projects. The NMET is envisaged to be created out of contributions received from the mining lease holders.

(6) Under the MMDR Act, 1957, the State Governments were mandatorily required to obtain prior approval of the Central Government before grant of any mineral concessions with respect to the 10 (ten) minerals listed under Part C of the First Schedule of the MMDR Act, 1957 which included iron ore, manganese, bauxite, copper, gold, etc. However, the MMDR Act, 2015 has removed this requirement of prior approval from the Central Government. Therefore, under the MMDR Act, 2015 now the State Governments shall not be required to obtain a prior approval from the Central Government for granting the mining concessions.

(7) In order to curb the ever increasing problem of illegal mining, the MMDR Act, 2015 has made the provisions pertaining to offenses and punishments more stringent. All offences under the MMDR Act, 2015 shall be subject to a maximum punishment of 5 years' imprisonment or fine of Rs. 5 Lakhs per hectare. The State Governments are also empowered under the MMDR Act, 2015 to set up special courts for speedy trial of offences under the MMDR Act, 2015.


The Ministry of Shipping has proposed to initiate a scheme, viz., Scheme for Incentivizing Modal Shift of Cargo (Cargo Transportation Scheme), for providing certain monetary incentives for transporting certain identified commodities, containerized cargo and automobiles through coastal shipping/ inland waterways routes. The Cargo Transportation Scheme will not only decongest the roadways/ highways and railroads, through which the cargos are generally transported, but will also minimize the environmental impacts of such road and rail transportation. The Cargo Transportation Scheme has been proposed to be implemented initially during the period from April 1, 2015 up to March 31, 2017.

The Cargo Transportation Scheme can be availed by any transporter, if the identified categories of cargo are transported through coastal shipping or inland waterway routes or both. However, for availing the benefits under the Cargo Transportation Scheme, the identified cargos must be transported in vessels with Indian flag, river sea vessels or barges and the coastal shipping or inland waterway routes through which the such cargo is transported must pass through at least one major port, designated non-major port or Inland Waterways Authority of India terminal/jetty at the point of loading or discharge. The Cargo Transportation Scheme is proposed to be implemented using the Port Community System and such transporters who are eligible for grant of the incentives under the Cargo Transportation Scheme must register under the Port Community System with the Indian Ports Association.


The Atomic Energy Regulatory Board has, with effect from February 28, 2015, implemented the web-based approval/ licensing system – eLORA (e-Licensing of Radiation Applications) for granting approval/ license for transportation, export and disposal of atomic wastes. The online process will not only simplify and fast tract the licensing process but will also make the process more transparent.


The Integrated Regulatory Review Service Mission of International Atomic Energy Agency (IAEA) reviewed the regulatory framework in place in India with respect to nuclear safety, during March 16, 2015 to March 27, 2015. The review was focused on Atomic Energy Regulatory Board's (AERB) regulatory frameworks with respect to nuclear power plants and projects and was carried out by comparison with IAEA safety standards, which are recognized as international benchmark for atomic safety.

The review mission acknowledged that AERB continues to strengthen its regulatory frameworks regularly for regulating nuclear safety, by reinforcing the safety measures of existing nuclear facilities, monitoring ageing and decommissioning old facilities, and also by overseeing the construction, commissioning and operation of new nuclear power plants. However, the mission also identified certain areas which require improvements, such as: policy for radioactive waste management, regulatory independence of AERB, enhancing routine inspections at nuclear power plants. IAEA shall be submitting its final report to the Government of India later this quarter.


In order to counter China's inexorable reach over the Indian Ocean, and to strategically strengthen its presence in the Indian Ocean region, the Government of India has proposed to substantially invest and develop the maritime infrastructure in the island state of Sri Lanka.

It has been proposed to restart the ferry services between India and Sri Lanka. The Government of India has also proposed that Indian and Sri Lankan companies should work together for developing oil tank facilities in Trincomalee for refueling ships at the port and in order to make Trincomalee a regional petroleum hub.

It is pertinent to note that by way of investing in and developing Sri Lanka's maritime infrastructure and regional connectivity, India is strategically strengthening its own security aspects.


In order to boost the air transport infrastructure in India, the Airports Authority of India (AAI) has undertaken the construction of five small airports during 2014-2015, located at Hubli and Belgaum in Karnataka, Kishangarh in Rajasthan, Jharsuguda in Odisha and Tezu in Arunachal Pradesh.

A Task Force has also been constituted for identifying certain other locations where such small airports should be developed, based on broad criteria viz., minimum population of 10 lakhs, tourism potential, commercial viability, details of the flight movements in past, social obligations etc. The Government of India proposes to develop these small airports in the Tier-II and Tier-III cities with private participation.


In order to boost energy efficiency and reduce fuel consumption by thermal power plants the Government of India has identified 144 thermal power plants under the Perform, Achieve and Trade (PAT) Scheme of the Ministry of Power which is being implemented by the Bureau of Energy Efficiency.

In order to give the necessary impetus for boosting the energy efficiency and for improving the demand supply management, various steps are being taken by the Government of India, viz. (i) advanced planning with respect to power generation projects to be taken up during the 12th Five Year Plan in detail and perspective planning with respect to power generation projects to be taken up during the 13th Five Year Plan; (ii) projects which are in the execution stage are monitored at the highest level for resolving bottlenecks with respect to the project and for ensuring that the projects are timely commissioned.

In addition to the aforesaid, the following steps are also being adopted with respect

to the designing and operation of power plants:

(1) Renovation and modernization and life extension of existing thermal power stations are being done for improving the performance of the power plant.

(2) The Central Electricity Authority has notified the Technical Standards for Construction of Electric Plants and Electric Lines Regulations, 2010 which sets out the requisite energy efficiency criteria to be complied with.

(3) Old and inefficient thermal power plants are being closed down in a phased manner. Supercritical technology is being adopted for enhancing the efficiency of coal fired thermal power generation and for reducing the coal consumption required for the power generation.


The Ministry of Shipping has approved of a new incentive scheme (Scheme) on March 10, 2015 for the purpose of giving the necessary impetus to the major ports to become green ports. Green ports shall be such major ports which set up green projects within the port area, viz., waste water treatment, renewable energy generation, using of bio-diesel and provision of shore power.

The Scheme proposes that the Government of India shall provide each of the major port a financial grant of up to Rs.25 Crore for undertaking these green projects within the port premises for the purpose of making th port a green port.


The Silk Road Project which is being undertaken by China comprises of a Silk Road and a Maritime Silk Route. Although the main intent of the Silk Road is to connect China with Europe through Central Asia, the Silk Road also connects Bangladesh, China, India and Myanmar (BCIM) and the Pakistan-China Economic Corridor through the Pakistan occupied Kashmir. In addition, the Maritime Silk Route (MSR) proposes to connect China's ports with the ports in Vietnam, Malaysia, Indonesia, India, Sri Lanka, Greece and Kenya.

Therefore it is evident that the US$ 40 Billion Silk Road Project not only connects India with rest of Asia but the project will also boost trade and commerce between India and the other connected neighboring countries. However, although India is participating in the BCIM segment of the Silk Road, India shall not be participating in the Maritime Silk Route project on account of India's strategic concerns over China's dominion over the Indian Ocean.


The Cabinet Committee on Economic Affairs has, at its meeting held on March 31, 2015, approved the amendment in the definition of a 'Private Sector Company' in the guidelines for providing financial support to public private partnerships in the infrastructure sector under the Viability Gap Funding Scheme (VGF Scheme).

The definition of 'Public Sector Company' has been approved to be amended in order to remove any ambiguity in the interpretation of the term and for the purpose of aligning the definition with the definition of a 'Government Company' as defined under Section 2(45) of the Companies Act, 2013.

Further, approval has also been accorded for the definition of 'Private Sector Company' being amended. The amended definition of a 'Private Sector Company' under the PPP guidelines shall include a company which is not a 'Government Company', where Government Company is defined under Section 2(45) of the Companies Act, 2013. 

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

In association with
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.