As Ontarians turned off their air conditioners earlier this
month, the Ontario Power Authority (OPA) opened the gates to the
widely anticipated Feed-In-Tariff (FIT) Standard Offer Contract
Program. The FIT program was officially launched on October 1,
2009, finally allowing renewable-energy project developers to put
the FIT framework to the test. The OPA has stated it intends to
respond to project developers within sixty days of receiving a
complete application, although the anticipated high number of
applicants may cause delays to the expected execution of FIT
contracts.
Key features of the FIT program
- Generally, in order to be eligible, projects must be (a)
renewable generating facilities not already in existence; (b)
located in Ontario, provided they are not located in expressly
exempt areas; and (c) projects that do not have or have not had a
prior power purchase agreement, unless such agreement was
terminated prior to March 14, 2009 or more than twelve months
before the date of application.
- Solar projects with a contract capacity greater than 100 kW are not eligible if located on certain high-quality Class 1 or Class 2 agricultural lands, and, if located on Class 3 agricultural lands, are only eligible if located on identified lands.
Application
- Application fees under the FIT program range from a minimum of
$500 to a maximum of $5000, and the application security charge is
$20/kW for solar projects and $10/kW for all other projects.
- A complete application must also include evidence of access rights to the project location. Such evidence may be in the form of a lease, an option, a letter of intent, a memorandum of understanding or a conditional grant contingent on obtaining a FIT contract.
Domestic Content
- The domestic content of a project is calculated based on the
OPA's domestic content grid for each specified renewable energy
source and contract capacity. This grid allocates a qualifying
percentage to designated activities occurring within Ontario or
completed by Ontario residents. Designated activities include the
manufacturing and assembling of specified materials, certain
construction and on-site labour, and certain consulting
services.
- The following domestic content thresholds must be met:
-
- wind power projects with a contract capacity greater than 10kW:
(a) 25% for FIT contracts with a milestone commercial operation
date (COD) prior to January 1, 2012; and (b) 50% for FIT contracts
with a milestone COD on or after January 1, 2012;
- solar projects with a contract capacity greater than 10 kW: (a)
50% for FIT contracts with a milestone COD prior to January 1,
2011; and (b) 60% for FIT contracts with a milestone COD on or
after January 1, 2011;
- solar projects with a contract capacity less than 10 kW: (a) 40% for FIT contracts with a COD prior to January 1, 2011; and (b) 60% for FIT contracts with a COD on or after January 1, 2011;
- wind power projects with a contract capacity greater than 10kW:
(a) 25% for FIT contracts with a milestone commercial operation
date (COD) prior to January 1, 2012; and (b) 50% for FIT contracts
with a milestone COD on or after January 1, 2012;
- The OPA must be provided with a plan, in a prescribed form, setting out how the FIT program applicant intends to meet the minimum required domestic content level, no later than six months prior to the milestone COD.
Launch Applicants
- All eligible FIT contract applicants who apply during the first sixty days following the launch of the FIT program (prior to November 31, 2009) will be assigned a time stamp, allocated in priority based on (a) the applicant's commitment to reduce the number of days between the date of contract and the milestone COD; (b) the project's acceleration characteristics, including whether it is REA exempt or has an executed EPC agreement; and (c) the date access rights were granted.
Advanced RESOP Applicants
- A Project Developer with a Renewable Energy Standard Offer
Program (RESOP) contract can either: (a) retain the RESOP,
unamended; (b) amend the RESOP before October 31, 2009, through the
FIT program's Advanced RESOP FIT Amendment, where the RESOP is
in respect to a wind generation project that has been issued a
Certificate of Approval (Noise Emissions) from the Ministry of
Environment; (c) repudiate and terminate the RESOP by applying
through the FIT Program Launch, before November 31, 2009; or (d)
repudiate and terminate the RESOP and apply through the standard
FIT program after twelve months.
- The Advanced RESOP FIT Amendments include:
-
- a substitution of the contract price with 12.1¢/kWh,
comprised of a fixed portion of 9.68¢/kWh and an indexed
portion of 2.42¢/kWh;
- relief from the requirements of the RESOP to share with the OPA
payments the applicant may be able to obtain under the ecoENERGY
grant;
- a requirement to maintain the completion and performance
security, which will be returned on the COD; and
- a requirement that the facility achieve commercial operation no later than December 31, 2010, with liquidated damages payable for each day commercial operation is late, culminating in an event of default if the COD is after December 31, 2011.
- a substitution of the contract price with 12.1¢/kWh,
comprised of a fixed portion of 9.68¢/kWh and an indexed
portion of 2.42¢/kWh;
- Project developers who amend their RESOPs remain bound by the RESOP contract and are not subject to the terms of the FIT program, including domestic content requirements.
MicroFIT
- microFIT is a standard-offer program focused on homeowners and other micro-project developers. The rules and the governing contract have been simplified, but contain similar obligations regarding domestic content and environmental attributes. There are no application or security fees associated with contract application under the microFIT rules.
Renewable Energy Approvals
In addition to the commencement of the FIT program, the Ministry
of the Environment released key regulations on September 24, 2009
relating to the Renewable Energy Approval (REA) amendment under the
Environmental Protection Act.
A REA is required for all projects which were previously required
to seek certificates of approval under s. 9(1) and (7) of the EPA
(i.e. construction, altering, extending or replacing or operating
any plant, structure, equipment, apparatus, mechanism or thing that
may discharge or from which may be discharged a contaminant into
any part of the natural environment other than water), s. 27(1)
(waste management), and all those that generally were required by
regulation to seek an "approval, permit or other
instrument."
Prior to the EPA REA amendments, solar projects were not required
to undergo an environment assessment (EA). Wind projects may have
had to undergo an environmental impact study or potentially a full
EA, depending on the location and the project's generation
capacity. Certificates of Approval were required by regulation for
both wind and solar projects.
Projects are exempt from seeking a REA where:
- all approvals, permits and other instruments that are required
to construct, install, operate or use the facility were obtained
before May 14, 2009;
- no approvals, permits or other instruments listed above were
required to construct, install, operate or use the facility and the
construction or installation of the facility began before May 14,
2009;
- an EA Notice of Completion in respect of the facility was
issued prior to May 14, 2009 and the facility has a power purchase
agreement with the OPA;
- before May 14, 2009, (i) a power purchase agreement was entered into with the OPA; (ii) the use of the land at the project location was not prohibited by a zoning by-law or order under Part V of the Planning Act; and (iii) the facility was not an undertaking that was designated to be subject to the Environmental Assessment Act.
General REA obligations include:
- consultation with the public and aboriginal communities
surrounding the project, including at least two public
meetings;
- consideration of archaeological and heritage resources, where
applicable;
- specified setbacks for wind energy facilities;
- submission of a project's construction plan report, construction report, decommission plan report, design and operations report, noise study report (for non-rooftop solar facilities with a capacity greater than 10 kW), project description report, and wind turbine specifications report or off-shore wind facility report (where applicable).
Care should be taken when reviewing the various transition
provisions related to the RESOP and FIT programs and the REA
requirements.
Commentary
The Ontario government should be pleased with the level of
activity in the renewable sector these days. There is a flurry of
new entrants, particularly from the U.S. and Europe, who are
thoroughly investigating opportunities in Ontario, from both
development and equity investment perspectives. At the same time,
some organizations are suggesting that the FIT program needs to be
more user friendly. For example, the solar industry is concerned
about the restriction on the use of Class 1, 2 and 3 agricultural
lands and is looking for certain relief from those provisions , as
well as some loosening of the domestic content requirements. Those
same domestic content requirements, which while lower for wind
applicants, are also being raised as concerns by the wind industry.
Both solar and wind proponents note that the current capacity in
Ontario for meeting the domestic content requirements is seriously
constrained and more time than the government has allowed may be
necessary to meet the deadlines imposed. Finally, the great
unknown-issues relating to transmission capacity constraints-will
start to reveal themselves in the months to come, once the initial
round of FIT applications are reviewed and queues start to form for
new transmission development. Stay tuned for further word from the
OPA as they work through the first round of mature applications
that will be filed prior to the end of November 2009.
The launch of the FIT program and the commencement of the REA
represent the final pieces that complete the implementation of Bill
150, which was first introduced in February. Watch for further
guidance from both the OPA and the Ministry of Environment as these
new pieces are "fit" into place.
We will continue to keep you regularly informed as the FIT
marketplace develops and matures.
The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.