Canada: Wind Development In Ontario And The Green Energy And Green Economy Act, 2009: The New Rules Of Engagement

Last Updated: October 13 2009
Article by Helen T. Newland and Sven Thorsten Hombach

The Green Energy and Green Economy Act, 2009 (the Act), which introduces a new feed-in tariff (FIT) for renewable energy projects and streamlines the regulatory approval process, became law in July 2009. However, amendments to several existing statutes, including the Environmental Protection Act, Environmental Assessment Act, and the Planning Act, were not proclaimed into force when the Act passed into law, as the underlying regulatory regime had yet to be developed.

These amendments became effective as of Thursday, September 24, 2009. Following a public announcement by Minister of Energy George Smitherman, new environmental regulations that underpin the Act were introduced and the Ontario Power Authority (OPA) announced that it will accept FIT applications as of October 1, 2009.

The impact of the regulatory changes on projects currently in the development phase in Ontario will be profound. All wind industry members should therefore be aware of the legislative and regulatory changes, and the milestones that determine whether a project proceeds under the old rules or the new rules. This newsletter is designed to provide you with a high-level overview of the changes and the applicable transition rules.

Highlights of the Green Energy and Green Economy Act, 2009

The Act introduces five primary changes applicable to wind developments in Ontario:

  1. European-style feed-in tariff granted for a 20-year period, but dependent on domestic content requirements.
  2. Right to connect and priority access to the grid for renewable energy.
  3. Municipal zoning override.
  4. Renewable Energy Approvals ("REA") which are tied to specific setbacks and which replace the conventional environmental assessment and approvals process.
  5. Limited grounds on which environmental approvals can be appealed to the Environmental Review Tribunal.

1. European-Style Feed-In Tariff

The Act creates a European-style FIT system for various renewable energy sources. In order to obtain the benefits of the FIT, developers need to sign a 20-year contract with the OPA. The FIT contract is available on the OPA's web site, along with detailed rules setting out the requirements for FIT applications. The OPA will start accepting applications on October 1, 2009.


The FIT pricing structure for wind power is as follows:


Proposed Size

Proposed ¢/kWh


Any size



Any size


Aboriginal Surcharge (depends on percentage of ownership

Any Size

Up to 1.5 cents

Community Surcharge (depends on percentage of ownership)

Any Size

Up to 1.0 cents

The standard FIT contract provides that if a proponent applies for the ecoENERGY credit, half of the credit must be signed over to the OPA. All environmental attributes, such as future carbon offsets, must be signed over to the OPA in their entirety.

Projects that are subject to an existing standard offer contract (i.e., RESOP) and have already obtained their environmental Certificate of Approval may be eligible for an "advanced RESOP FIT amendment" that increases the standard offer contract price to 12.1 cents/kWh, with a portion of that price tied to the consumer price index. The deadline for rescinding a RESOP contract and applying under FIT is 30 days after the program launch.

Price settlement for Independent Electricity System Operator (IESO) market participants will take place on a monthly basis based on the difference between the FIT price and the spot price. However, the FIT rules provide an alternate system for non-market participants that is more flexibile.

Domestic Content Requirements

To qualify for FIT, applicants need to meet the following domestic content requirements:

  • 25 percent domestic content if the project has an expected in-service date prior to January 1, 2012.
  • 50 percent domestic content if the project has an expected in-service date of January 1, 2012 or later.

The domestic content calculation, which is set out in Table 1 of Exhibit D of the standard FIT contract, works on a points-based system, with different components being allocated different percentages. For example, it is possible to gain 16 percent domestic content simply by casting the wind turbine blades in Ontario, while only two percent are allocated to the winding of pad mount transformers in Ontario.

Importantly, "domestic" in the context of FIT refers to Ontario content, not Canadian content.

Program Launch

For 60 days after October 1, 2009, special launch rules apply. Applications submitted during this period will be time-stamped and prioritized in order of expected commercial operations date rather than in order of submission. Deficient applications will be returned and not be eligible for re-submission until the first transmission availability test (see below) under the program has been conducted. After the expiry of the launch period, applications will be prioritized in order of submission.

The FIT rules contain a number of criteria specific to launch applications that should be reviewed carefully prior to submitting an application, especially in light of the temporary loss of eligibility of deficient applications.

Eligibility Requirements

FIT applications will only be considered if the applicant has secured the necessary land rights (i.e. option agreements or, in the case of Crown land, confirmed "Applicant of Record" status).

Filing fees depend on the proposed capacity of the facility. Applicants cannot roll over an existing power purchase agreement into FIT. Any existing power purchase agreement must have been terminated prior to March 14, 2009, or at least 12 months before the FIT Application is submitted, subject to the "advanced RESOP FIT amendment" discussed above. Any existing system impact assessment or connection impact assessment must be rescinded when applying under FIT.

Unless the application applies to a capacity allocation exempt facility, the OPA and IESO will determine if the relevant transmission system has sufficient capacity by conducting a transmission availability test. If capacity is insufficient, the applicant, together with any other applicants trying to connect to the same transmission system, will be placed into the "economic connection test" process, which will take place at least once every six months. The economic connection test process assesses whether the cost to ratepayers of building additional transmission infrastructure would be reasonable in light of the circumstances (see comments on the "right to connect" below).

An assignment of a FIT contract or change of control of the applicant requires the consent of the OPA, which the OPA is not allowed to unreasonably withhold. However, no assignment or change of control is allowed in any case until one year after the application was submitted, and no assignment or change of control is allowed once the OPA has provided an Offer Notice. Developers intending to create a single-purpose vehicle to own and operate a facility once it is built should take notice of this restriction.

2. Right to Connect and Priority Access

Wind power developers have traditionally been subject to substantial delays in connecting proposed generation facilities to Ontario's transmission or distribution grid, and occasionally have been refused connection entirely by the transmitter for economic reasons. New amendments to the Electricity Act, 1998 legislate a "right to connect," although there remains an underlying proportionality requirement.

More importantly, the amendments legislate priority access to the grid for renewables. Once a renewable project enters the IESO's committed generation queue, it jumps ahead of non-renewable projects in the queue. However, no relative priority is allocated amongst renewable energy sources; for example, wind shares priority with other sources such as hydroelectric power, solar photovoltaic and biomass.

3. Municipal Zoning Override

All Canadian municipalities derive their power from provincial laws. A significant part of this power is the ability to enact zoning by-laws. Highly vocal local opposition has frequently resulted in municipalities using restrictive zoning to prevent otherwise meritorious wind power developments. The Act contains an amendment to the Planning Act that creates a provincial override and requires project opponents to become involved at the provincial approvals level rather than interfere at the municipal level. As of September 24, 2009, proponents no longer require municipal zoning amendments, and, more importantly, will no longer be subject to potential appeals to the Ontario Municipal Board.

When first proposed, this amendment led to a number of complaints by municipalities and grassroots organizations across Ontario. In an effort to address these concerns, the final version of the Act contains an amendment requiring the Act to be administered, "in a manner that promotes community consultation." This consultation requirement is reflected in the REA process set out below.

The municipal zoning override is not contingent on projects proceeding under the REA process, as there are no transition provisions to mirror those set out in the REA Regulation described below. It is possible for a project to be subject to the municipal zoning override while still proceeding under the old environmental approvals regime.

4. Renewable Energy Approvals and the New Setback Requirements

The new REA process is intended to streamline the approvals process by reducing them to a single regulatory review process. O. Reg. 359/09 sets out the requirements for REA applications (the REA Regulation).

Transition Rules

The following transition rules apply to wind projects currently under development (see section 9 of the REA Regulation). For each rule, the target date is the date the amendments to the Environmental Protection Act came into force, i.e. September 24, 2009.

A project is subject to the old environmental approval regime unless one of the following milestones have been reached by the date the amendments came into force:

  • All environmental Certificates of Approval had been obtained.
  • No Certificates of Approval are required and construction or installation has begun.
  • The project has received a Notice of Completion under the Environmental Assessment Act and is subject to a signed power purchase agreement with the OPA.
  • The project is subject to a power purchase agreement with the OPA, the proposed land use is not prohibited under Part V of the Planning Act or a municipal by-law, and the project is not subject to an environmental screening, review or assessment under the Environmental Assessment Act.

If the project does not fall under any of the above-mentioned exceptions, it is subject to the new REA regime.

Turbine and Substation Setback Rules

The streamlined REA process comes at a price, payable in the form of more stringent turbine and substation setbacks. Unless a proponent is prepared to conduct a noise study, the following minimum mandatory setbacks apply to turbines and transformer substations:

Number of Wind Turbines

Setback in metres (m) from the closed Point of Reception corresponding to wind turbine Sound Power Levels in decibels (dBA)

102 dBA

103-104 dBA

105 dBA

106-107 dBA

> 107 dBA

1-5 Turbines

550 m

600 m

850 m

950 m

Noise Study Required

6-10 Turbines

650 m

700 m

1,000 m

1,200 m

11-25 Turbines

750 m

850 m

1,250 m

1,500 m

26+ Turbines

Noise Study Required


Noise Study Required

Transformer Substations without Noise Abatement

1,000 m

Transformer Substations with Noise Abatement

500 m

In addition to the Point of Reception Setbacks outlined above, section 38 of the REA Regulation requires minimum setbacks from various natural features, such as significant wetlands, areas of natural and scientific interest, significant woodlands, significant wildlife habitat, provincial parks, and certain lakes. The Greenbelt and the Oak Ridges Moraine have their own setback rules.

"Table 1" Reports

Any proponent applying for an REA must complete the reports specified in Table 1 of the REA Regulation. Table 1 enumerates detailed requirements for construction plan reports, consultation reports, decommissioning plan reports, design and operations reports, noise studies, wind turbine specifications reports, and other requirements. Reports will not be accepted by the Ministry until the requirements are met. Archaeological and natural heritage studies will continue to be required under the new REA regime as well.


Consultation that previously took place under the auspices of the Environmental Assessment Act will now take place under the REA process, which contains an extensive but streamlined list of requirements. Proponents will be required to publish a notice and serve landowners, aboriginal communities, municipalities, roads and local services boards, among others. Each renewable energy project will require at least two public consultation meetings. Additional specific consultation requirements are set out with respect to municipalities and aboriginal communities.

5. Limited Grounds for Appeal

Concurrent with the creation of the new REA process, the Environmental Protection Act has been amended to limit the available grounds to appeal such an approval to the Environmental Review Tribunal (the Tribunal). A decision granting an REA can only be appealed on the basis that, "engaging in the renewable energy project in accordance with the renewable energy approval will cause serious and irreversible harm to plant life, animal life, human health or safety, or the natural environment."

Impact on Current and Future Wind Projects

For projects currently in the development phase, September 24, 2009 constitutes an important milestone. Depending on project specifics, proponents may prefer to continue under the existing regime to avoid being caught by the new setback requirements, or to continue under the new approvals regime which provides a more streamlined process. Most proponents have addressed and continue to address this issue in direct consultation with the Ministry of the Environment.

For new projects, the FIT and REA regimes provide a powerful incentive to invest in Ontario that is somewhat marred by the strict domestic content requirements that accompany it. The wind turbine manufacturing industry in Ontario is still in its infancy, which will impact the ability to meet the 25 percent and 50 percent domestic content thresholds. However, if and when a solid manufacturing base is developed in Ontario, this will be one of the most competitive jurisdictions in North America for wind power.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

Events from this Firm
25 Nov 2016, Seminar, Toronto, Canada

On Thursday, September 22, 2016, Dentons hosted a panel discussion about the management of liabilities and risks associated with environmental crises, including potential liabilities for directors and officers and provided insight into risk and liability techniques associated with environmental crisis management.

In association with
Related Video
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.