Canada: When Is Holdback No Longer Holdback?

This article was originally published in LexisNexis Construction Law Letter, volume 31, number 1.

Holdback obligations under the Ontario Construction Lien Act [CLA] are stringent. Pursuant to s. 22 of the CLA,the owner is required to hold back 10 percent of the contract price from the contractor, plus the amount of any registered liens of which the owner has received notice, on behalf of subcontractors. In Ontario, this analysis also applies to contractor holdback, for the CLA requires contractors to retain holdback on behalf of sub-subcontractors, and so on. The owner can be personally liable in a lien action for these holdback obligations pursuant to s. 23. So when do these holdback obligations come to an end, and what happens when they do? This paper provides a general answer to these questions.

When do holdback obligations come to an end?

Since owners are required by statute to retain holdback, or risk personal liability for the amounts they failed to properly hold back (and risk paying twice, as the court ordered in Wellington Plumbing & Heating Ltd. v. Villa Nicolini Inc. as a result of the owner's improper payment of holdback to certain subcontractors), it is important to be clear about when holdback obligations end.

The general principle is that holdback obligations come to an end when subcontractors who have done work to improve a property can no longer make a lien claim against the property, and when any existing registered liens have been either satisfied or discharged with respect to the owner who has the holdback obligation.

It is important to recall that there are two kinds of holdback in Ontario, regular holdback (s. 22(1)) and "finishing" holdback (s. 22(2)). Regular holdback applies to subcontractors who performed work prior to substantial performance. Finishing holdback applies to subcontractors who performed work after substantial performance to total completion. According to s. 26 of the CLA:

26. Each payer upon the contract or a subcontract may, without jeopardy, make payment of the holdback the payer is required to retain by subsection 22 (1) (basic holdback), so as to discharge all claims in respect of that holdback, where all liens that may be claimed against that holdback have expired as provided in Part V, or have been satisfied, discharged or provided for under section 44.

In other words, regular holdback obligations come to an end when:

a) the period to register new liens has expired pursuant to s. 31 of the CLA, (i.e. 45 days have passed since the publication of the certificate of substantial performance), and

b) existing liens have been satisfied (paid, resolved in court, or finally settled), discharged with respect to the owner, which includes the common practice of the contractor paying security into court sufficient to cover the liens (bonding off) pursuant to s. 44 of the CLA, or vacated by the owner itself pursuant to s. 44.

Finishing holdback obligations come to an end pursuant to s. 27 of the CLA under the same conditions except that the expiry of the lien period (condition a) above) is 45 days after total completion of the project. If at any point, the project is abandoned, the expiry of the lien period is 45 days from the date that the project was abandoned.

Lastly, the holdback obligation can come to an end piecemeal by virtue of s. 25 of the CLA. If a subcontract is certified complete at the request of the contractor pursuant to s. 33, the owner is no longer obligated to retain holdback with respect to that subcontract if all liens with respect to that subcontract have expired (45 days have passed), or been satisfied, discharged or provided for pursuant to s. 44.

A Shift in Perspective

What happens next? Must the owner release the holdback funds to the contractor? What are the owner's continuing obligations with respect to these funds?

The first step to answering this question is a shift in the way we look at these funds. Holdback is a pure creation of statute, a mechanism designed by the provincial government to ensure that subcontractors and suppliers are paid for their work and materials. This means that once the owner no longer has holdback obligations under the statute, the funds are no longer "holdback," but simply funds owing to the contractor. More precisely, they are the notional profit component of the contract price that has been withheld from the contractor by statute and that now no longer needs to be withheld.

Legal Consequences

There are five important consequences of this transformation:

  1. The statutory liability of the owner to the subcontractor for lien claims under the CLA is eliminated.
  2. The owner has a contractual obligation to pay the contractor.
  3. The funds form part of the owner's trust for the benefit of the contractor (up to the amount certified as payable to the contractor).
  4. The owner has a right of set-off of any debts or claims it has against the contractor, whether related to the project or not.
  5. The owner has the ability to pay subcontractors directly.

We shall address each in turn.

1. No More Statutory Owner-Subcontractor Liability for Liens

Assuming that the security in court for any registered liens has been posted by someone other than the owner (typically, the contractor) which discharges the lien with respect to the owner, the owner no longer has the liability to subcontractors for liens that is imposed by the CLA.

There are several cases stating that in these circumstances, the owner is no longer a proper party to a subcontractor lien action. See, for example, Benny Haulage Ltd. v. Carosi Construction Ltd. and Dominion Bridge-Ontario v. Stephens Sura (Canada) Ltd., and Concord Carriers Ltd. v. Alnet Holdings Ltd.

There are, nevertheless, some important obligations to the subcontractor under the CLA that remain for the owner – in particular, the obligation to respond to requests for information pursuant to s. 39 of the CLA. Upon the subcontractor's written request, the owner must provide, within 21 days, the names of the parties to the contract, the contract price, the state of accounts between the owner and the contractor, a copy of the labour and material payment bond posted by the contractor, and a statement of whether the contract provides in writing that liens shall arise and expire on a lot-by-lot basis.

2. The Owner Is Bound to Pay the Contractor

The funds are owing under the contract, which binds the owner to pay them out to the contractor. The contract price for all contracts comes due when the contract is completely performed. In addition, most contracts will provide for progress payments, which come due at various intervals throughout the life of the project. When the holdback obligation is lifted, and the funds become funds owing to the contractor, there is no longer that restriction on paying the funds out under the CLA.

As explained in the recent case of Crina General Construction Ltd. v. Carrington Homes Ltd., failure to pay the contractor is not necessarily a breach of trust, but the owner is likely to incur liability if payment is not made within a reasonable time. In Salit Steel v. Mondiale Development Ltd., the owner was ordered to pay significant pre-judgment interest, in excess of $600,000, for failing to release the funds as of the 45 days after substantial completion.

Although presently off the table, Bill 69, Prompt Payment Act, 2014 that would have, if enacted, legislated a requirement for owners to pay these funds promptly (within one day after the owner is no longer required to retain the holdback under the CLA). Nevertheless, to date, there has been no legislation enacted requiring payment to be made within any particular time frame.

In the absence of a statutory requirement to pay the former holdback funds promptly, contractors may wish to give thought to including a clause in the construction contract dealing with timing issues with respect to this payment once the owner's holdback obligations come to an end.

3. The Funds Become Trust Funds

Once the holdback funds become funds owing to the contractor, they also become trust funds as required by s. 7 of the CLA (up to the amount certified as payable to the contractor). Subsection 7(2) of the CLA states:

7(2)  Where amounts become payable under a contract to a contractor by the owner on a certificate of a payment certifier, an amount that is equal to an amount so certified that is in the owner's hands or received by the owner at any time thereafter constitutes a trust fund for the benefit of the contractor.

The CLA trust obligation requires the trustee and beneficiary to have privity of contract (i.e., they must have contracted with one another). The trust obligation of the owner is, therefore, to the contractor only, not the subcontractors. This principle was outlined in Tri-Tec Drywall Services Ltd. v. Wilson Memorial General Hospital, where s. 8 of the CLA was at issue (the contractor's analogous trust obligation to the subcontractor), and the court found that the contractor did not have a trust obligation to everyone down the construction supply chain. Thus, by analogy, the owner does not have a trust obligation to the subcontractor.

To avoid falling afoul of the trust requirements of the CLA, it is advisable for owners to retain these funds in trust if the owner is not paying them out to the contractor (discharging the trust), rather than using them for other purposes such as the rectification of deficiencies or the satisfaction of other claims against the owner. The owner may incur personal liability if the trust funds are misappropriated.

4. The Owner Can Set Off

As the Superior Court commented in Man-Shield (NOW) Construction Inc. v. Rainy River District School Board, while the funds remain holdback, the owner may not set off any outstanding debts, claims, or damages that the owner might have against the contractor because the holdback is being retained for the benefit of the subcontractor. Once the funds are no longer holdback, however, the owner may set off any outstanding debts, claims, or damages, whether or not related to the improvement, and deduct these amounts from the amount that it releases to the contractor. This right of set-off applies, according to s. 12 of the CLA,even though the funds are held in trust for the benefit of the contractor.

5. The Owner Can Pay Subcontractors Itself

Funds paid by the owner to the contractor, when the contractor owes money to the subcontractors for services or materials, automatically become trust funds for the benefit of the subcontractors pursuant to s. 8 of the CLA. Thus, there is typically no reason for the owner to pay the subcontractors directly.

However, there is provision within the CLA for the owner to pay these funds directly to subcontractors, bypassing the contractor. Pursuant to s. 28 of the CLA,if the owner gives written notice of this payment to the contractor, this payment to the subcontractors is deemed to be a payment to the contractor itself. Thus, the amount that the owner pays to the subcontractors is subtracted from the amount that the owner owes to the contractor. The payment also discharges the subcontractors' liens by the amount paid. This provision specifically states that such a payment cannot reduce the owner's holdback obligations, so it makes much more sense for the owner to take advantage of it, if it is necessary to bypass the contractor and pay the subcontractors directly, once the owner no longer has holdback obligations.


To sum up the takeaway points of this analysis:

Holdback is no longer holdback and becomes funds contractually owing to the contractor when

  • the period for subcontractors to register new liens has expired, and
  • existing liens have been satisfied or discharged with respect to the owner.

Once holdback is no longer holdback

  • the statutory liability of the owner to the subcontractor for lien claims under the CLA is eliminated,
  • the owner has a contractual obligation to pay the contractor,
  • the funds form part of the owner's trust for the benefit of the contractor,
  • the owner acquires a right of set-off of any debts or claims it has against the contractor, and
  • the owner has the ability to pay subcontractors directly.

Simply put, it is useful to stop thinking of funds held back pursuant to section 22 of the Ontario Construction Lien Act as "holdback" once the statutory holdback obligations of the owner have come to an end. Instead, they become trust funds contractually owing to the contractor once again.

Cases Cited

Benny Haulage Ltd. v. Carosi Construction Ltd., 1996 CarswellOnt 5328 (S.C.J. Master) (WL)

Concord Carriers Ltd. v. Alnet Holdings Ltd., [2005] O.J. No. 3748, 46 C.L.R. (3d) 313 (S.C.J.) (QL)

Crina General Construction Ltd. v. Carrington Homes Ltd., 2013 ONSC 4303, [2013] O.J. No. 2944 (S.C.J.) (QL)

Dominion Bridge-Ontario v. Stephens Sura (Canada) Ltd., [1997] O.J. No. 3023, 35 C.L.R. (2d) 1 (Gen. Div.) (QL)

Man-Shield (NOW) Construction Inc. v. Rainy River District School Board, 2012 ONSC 323, [2012] O.J. No. 556 (S.C.J.) (QL)

Salit Steel v. Mondiale Development Ltd., [2009] O.J. No. 958; 78 C.L.R. (3d) 54 (S.C.J. Master) (QL)

Tri-Tec Drywall Services Ltd. v. Wilson Memorial General Hospital, [2005] O.J. No. 3405, 45 C.L.R. (3d) 314 (S.C.J.) (QL)

Wellington Plumbing & Heating Ltd. v. Villa Nicolini Inc., 2012 ONSC 5444, [2012] O.J. No. 4745 (S.C.J.) (QL)

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

Events from this Firm
8 Nov 2016, Seminar, Ottawa, Canada

The prospect of an internal investigation raises many thorny issues. This presentation will canvass some of the potential triggering events, and discuss how to structure an investigation, retain forensic assistance and manage the inevitable ethical issues that will arise.

22 Nov 2016, Seminar, Ottawa, Canada

From the boardroom to the shop floor, effective organizations recognize the value of having a diverse workplace. This presentation will explore effective strategies to promote diversity, defeat bias and encourage a broader community outlook.

7 Dec 2016, Seminar, Ottawa, Canada

Staying local but going global presents its challenges. Gowling WLG lawyers offer an international roundtable on doing business in the U.K., France, Germany, China and Russia. This three-hour session will videoconference in lawyers from around the world to discuss business and intellectual property hurdles.

In association with
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.