Ontario's Ministry of Natural Resources is moving ahead to shift some Endangered Species Act permits to a "permit by rule"/ registration system, through  Ontario Regulation 176/13. This "Modernization of Approvals" initiative is modelled on the successful one already well underway in the Ministry of the Environment. It was supported by the report of the Endangered Species Act Panel, as one of its six themes.
I'm a strong supporter of the "Modernization of Approvals"/permit by rule concept: the idea that common, low risk, frequently permitted activities can be governed by a standard set of rules, instead of a bespoke permit. If the activities are well chosen and the rules are well designed, a registration/permit by rule system makes routine permits faster, more predictable and more uniform, without reducing species protection. Enforcement is essential, of course, but it should be easier to enforce standard rules than it is to enforce one-off permits bedevilled by  little variations. And reducing the number of routine permits should free up regulatory staff to focus on the more challenging applications, as has been happening at the Ministry of the Environment.

Please note that MNR is calling its approach "Rules in regulation", instead of the more common "permit by rule". The Ministry of Environment calls the same approach its "registry" or "EASR" system.

In a telling sign of the importance of Endangered Species Act protection, the Ministry received 10034 comments on its proposal: 9469 comments writing and 565 online. 90% were form letters, both for and against the proposal. As a result, a number of useful amendments were made to the proposal, now Ontario Regulation 176/13 (which amends O. Reg. 242/08)

Expert Panel Recommendations

Here is what the expert panel recommended:

The Ministry of Natural Resources should implement an approval continuum where a  "permit by rule" (PBR) approach is implemented for certain projects/activities, which must meet a prescribed standard set of implementation conditions instead of proceeding through the regular negotiated approvals process (Permit by Review). Projects/activities that would suit this approach are those which are common and repeated, where there is confidence in the mitigation and therefore a lower risk to the species / habitat and where acceptable implementation best management practices are followed / repeated, such as conservation projects where the purpose is habitat creation. Risk assessment criteria could be developed by MNR to determine what other types of projects/activities would be subject to this PBR standard condition approach. It is recommended that PRB will only be implemented in exceptional circumstances for a relatively small proportion of approval applications in cases where the risk to ESA species is demonstrably low.

Compliance would be enforced by focusing on self-regulation with random audits of activities, and charges being laid for non-compliance, as appropriate.

Public Comments and MNR response

Here is a summary of the public comments that were received on the concept, along with MNR's responses:

"1. The ESA should be strengthened, but the proposal weakens the Act and would lead to a degradation of habitat; the proposal does not meet MNR's mandate or the intent of the ESA

The regulatory amendments continue to maintain a high level of protection of species at risk and their habitat. MNR is changing the way its work is carried out to better serve those who rely on the ministry for programs and services in a way that is consistent with MNR's mandate. There are no changes to the Act, but rather to O. Reg. 242/08, which is a regulation enabled by the current legislation. The changes are consistent with the purposes of the ESA.

Some of the changes after consultation and engagement that strengthen the protection of species at risk required by the proposal are:

  • The regulation requires proponents to consider Aboriginal Traditional Knowledge (ATK) when preparing a mitigation plan, which will facilitate engagement at the community level.
  • Aquatic Species (s. 23.4) Conditions in the standardized approach were expanded to provide more options for taking actions to benefit affected species.
  • Ecosystem protection (s. 23.11)

Eligible proponents were restricted to legal entities such as municipalities, universities and not-for-profit groups that have among their primary objectives natural heritage conservation, ecological conservation or similar objectives. (See s. 23.11 for a full list.)
This section does not apply to activities in the following sensitive ecological community types: fen, bog, sand barren or dune, beach bar, alvar, cliff or talus.
" Newly-listed and transition species – development (s. 23.13)

species that are found on-site late in the activity process are not eligible for this provision and a permit would be required for this circumstance.

"newly-listed species" is restricted to species listed on the Species at Risk in Ontario List as an endangered or threatened species for the first time on January 24, 2013.

  • Newly-listed and transition species – development (s. 23.13) and Early exploration mining (s. 23.10) Proponents are prohibited from carrying out any part of the activity in an area that is being used, or has been used at any time in the previous three years, by woodland caribou (forest-dwelling boreal population) to carry out a life process related to reproduction, including rearing.
  • Pits and quarries (s. 23.14) The time period in which to complete a mitigation plan when a species first appears on a site was reduced from three to two years.
  • Safe harbour habitat (s. 23.16) The "safe harbour plan" concept was removed. The regulation now only allows eligible safe harbour habitat (i.e. temporary habitat for species at risk, that will be removed at a later date) to be created or enhanced in accordance with a permit or agreement issued by or entered into with the Minister. .
  • Species protection, recovery activities (s. 23.17) An animal care protocol is required for activities involving handling of certain types of species at risk, in order to minimize potential adverse effects on the species.
  • Threats to health and safety, not imminent (s. 23.18)

While comments received, including the ESA Panel recommendations, supported the concept of streamlining approvals for health and safety activities, some concern was expressed that the language in the proposal was too broad, allowing too many activities to be eligible for the amendment. The ministry changed the wording from "is unacceptable under the circumstance" to "is likely to have serious consequences in the short or long term if the activity is not carried out." in order to scope the activities and added sub categories of activities to further scope what activities would be eligible.
Eligibility for activities related to the maintenance, repair, removal, replacement, decommissioning or upgrade of an existing structure or infrastructure was restricted such that there can be no: increase in the area occupied by the structure or infrastructure (except in relation to culverts), change in its location or use/function of the infrastructure.
The removal and decommissioning of structures was added to the list of eligible activity types to reflect that in some cases repair may not be possible or that a safer course of action may be to remove or decommission an unsound structure or infrastructure.
Many large or complex projects now require a mitigation plan (e.g., removal or replacement of an entire structure or infrastructure, or decommissioning of a dam).
Activities related to a drainage work to which s. 23.9 (Drainage works) of the regulation applies are not eligible for s. 23.18

  • A number of species are excluded from specific sections of the regulation due to the potential risk the activities present to these particular species.

2. Administrative efficiencies are not addressing the needs of species at risk (SAR) but reflect economic needs of industry, and MNR budget cuts; it is not realistic to expect industry to follow rules in regulation without MNR oversight.

The administrative changes to the regulation (Trapping – incidental catch s. 23.19, Possession for educational purposes, etc. s. 23.15, and Commercial cultivation of vascular plants, etc. s. 12) do not alter species protections but rather help avoid duplication and integrate a number of approvals with other planning processes in place within MNR.

Under the "rules-in-regulation" model put in place by these regulatory amendments, proponents of activities that would otherwise have prohibited impacts on species at risk or their habitats must satisfy requirements set out in the regulation. In most case proponents are required to register their activities with the Ministry and take a number of steps to minimize adverse effects on protected species or habitat. MNR will continue to conduct education and outreach activities, monitoring, auditing, and where necessary enforcement actions for the purpose of protecting and recovering species in Ontario.

3. Need increased efficiencies and flexibility for industry (e.g., there should be a window of two years before mitigation of adverse effects is required, health and safety proposal should not have any excluded species)

The Ministry is providing greater flexibility to industry by proceeding with a "rules-in–regulation" regulatory model for eligible activities in a way that continues to protect species at risk. The Ministry is focusing its efforts and resources on responding to requests for ESA permits for activities not covered in this regulation that are likely to have greater potential to impact species at risk.

4. The Crown Forest Sustainability Act (CFSA) already provides for needs of SAR; the forest sector is required to continuously update their management practices to be consistent with provincial recovery strategies developed under the ESA; the forestry sector should be exempt from the ESA based on unnecessary duplication with CFSA.

The new provision dealing with forest operations sets out the conditions that persons conducting forest operations impacting species at risk or their habitats must comply with if not acting under an ESA permit. This provision will apply to forest operations conducted before July 1, 2018 (5 years), during which time the Ministry will establish a panel to review the linkages between the ESA and the CFSA. The panel will include members from Aboriginal communities, along with stakeholders from the forest industry, municipalities and environmental organizations.

5. Recommendation to charge fees for permits as a means to offset budget cuts and avoid exemptions

Implementing a full cost recovery system for permitting is under consideration, but is out of scope for the current regulatory amendments.

6. General concern that registration and "rules-in-regulation" are intended to replace permitting; new SAR on sites should be addressed through overall benefit permits.

Where appropriate, MNR is shifting from a "review and approval" model to a registration and "rules–in-regulation" model. The rules set out in the regulation are comparable to permit conditions and include requirements such as: registering with MNR; taking reasonable steps to minimize adverse effects on the species; developing mitigation plans using expert advice and the best available information; monitoring and reporting on the effectiveness of mitigation measures and beneficial actions (where applicable); and, reporting of sightings to MNR. Some activities are eligible only if linked to existing instruments or approvals. In some instances, higher risk activities, species, community types or sensitive time periods for species have been excluded from the applicability of the regulation.

Permits will continue to be required where an activity is not eligible for one of the provisions of the regulation, or the requirements of the regulation cannot be met.

In addition, overall benefit permits would still be required for the development or construction phases of many activities that impact species at risk or their habitat. For existing operations, newly found species must be protected as soon as they are found by avoiding and minimizing adverse effects, followed by the development and implementation of a longer term mitigation plan.

7. Registration must be mandatory for all proposals; registration will not provide enough information for MNR to monitor when exemptions are being used, or the cumulative effects resulting from activities occurring under the exemptions.

All of the new regulatory provisions require the proponent to comply with rules laid out in the regulation. All but two of the eighteen provisions require registration; activities, locations and species will be recorded in the registration. The Ministry will be aware of activities that are occurring under the regulation, where they are taking place on the landscape, and which species are affected; this will facilitate analysis of cumulative effects.

Two of the regulatory provisions (Commercial cultivation of vascular plants, etc. s. 12 and Forest operations in Crown forests s. 22.1) do not require the proponent to register with the Ministry before undertaking a specified type of activity. The amendments to s. 12 (Commercial cultivation of vascular plants etc.) leave that section largely unchanged, though cultivators will no longer be required to give notice to MNR.

Forest operations carried out under approved forest management plans would not require an ESA permit provided the proponent complies with the rules set out in regulation. MNR is responsible for approving forest management plans under the Crown Forest Sustainability Act. The regulatory scheme in place under that Act already includes requirements to address impacts to species at risk; it also requires reports that will assist the Ministry with assessing the cumulative disturbance of forestry operations. Additional conditions in the regulation include direction consistent with the Caribou Conservation Plan related to forest management planning.

8. Comments and questions about consultation, the amount of information in the first posting and the makeup of the ESA Panel

This proposal notice about the ESA regulatory amendments was originally posted on the Environmental Registry (ER) for a 45 day comment period on December 5, 2013. The comment period for this notice was subsequently extended, and the notice was updated with a ten page document containing additional information on January 24, 2013, for a total of 82 days. MNR continued to consult with stakeholders during the development of the regulation.

The ESA Panel was developed to deliver advice to the ministry on improving the implementation of the ESA and represented a range of interests and expertise.

9. Concerns about the scope of "transition" for activities that are already approved or planned.

  • To be eligible for the "transition" provision (Newly-listed and transition species – development s. 23.13) there are a number of conditions that must be followed for activities that were approved or planned prior to dates specified in the regulation. These include conditions that require proponents to protect individual members of species at risk carrying out critical life processes such as reproduction and hibernation. Conditions also require proponents to take steps to avoid or minimize adverse effects on species or habitat; monitor and prepare a report on the effectiveness of these actions annually; develop and implement a mitigation plan for affected species at risk, carrying out habitat restoration or enhancement activities; and report observations of species identified to MNR.
  • The ER notice dated December 5, 2012 included a number of potential sectors that might be included in the "transition provision". The document that was added on January 24, 2013 providing additional detail included a list of specific activities; other sectors that felt they might be eligible for this provision were invited to provide comments to MNR. Activities that have been added to the "transition" provision as a result of comments received by the Ministry are:

Constructing drainage works under an agreement filed under s. 2 (2) of the Drainage Act, or in respect of which an engineer's report was adopted under s. 45 (1) of the Drainage Act
Carrying out a transit project, as defined in s. 1 (1) of Ontario Regulation 231/08 (Transit Projects and Metrolinx Undertakings) made under the Environmental Assessment Act, in respect of which the Minister has given a notice to proceed with the transit project under O. Reg. 231/08
Construction of Solar Facilities less than three or four hectares in area (An activity described in s. 3 of O. Reg. 350/12 for the purposes of s. 20.21 of the Environmental Protection Act)
Advanced exploration carried out under Part VII of the Mining Act provided certain criteria are met (including written receipt of a closure plan by the Director of Mine Rehabilitation)
Mine production carried out under Part VII of the Mining Act provided certain criteria are met (including written receipt of a closure plan by the Director of Mine Rehabilitation)
Rehabilitation of a mine hazard/Voluntary rehabilitation of a mine hazard provided certain criteria are met

  • Clarification was requested regarding eligibility under an existing transition regulatory provision for development and infrastructure affecting Redside Dace. Clarification regarding eligibility under s. 23.1 has been added to the regulation.

10. In response to requests by two industry sectors, the Ministry added two provisions to apply to the operation of wind facilities, and early mineral exploration. They are:

  • Wind facilities (s. 23.20 ) This section applies to a person who is engaged in the operation of a wind facility within the meaning of Ontario Regulation 359/09 (Renewable Energy Approvals under Part V.0.1 of the Act) made under the Environmental Protection Act.
  • Early exploration mining (s. 23.10) This section applies with respect to certain mining activities that constitute early exploration as defined in s. 1 (1) of Ontario Regulation 308/12 (Exploration Plans and Exploration Permits) made under the Mining Act.


Butternut (s. 23.7) The ER proposal states that individuals would register their activities affecting Butternut with MNR at least 30 days prior to removal of any retainable Butternut tree. However, rather than registering ahead of time, individuals must submit a Butternut Health Assessor's report to the appropriate MNR District Manager at least 30 days before completing the registration and the start of the proposed activity that will impact Butternut."

Improving the speed and predictability of Endangered Species Act permits has reportedly been a major request of the business community. Now that they are getting some of that, will enforcement be beefed up to ensure that the new system works?

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

Dianne Saxe
In association with
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.