ARTICLE
3 August 2010

Ontario Energy Board Staff issue Compliance Bulletin on Renewable Electricity Generation by Electricity Distributors

BL
Borden Ladner Gervais LLP

Contributor

BLG is a leading, national, full-service Canadian law firm focusing on business law, commercial litigation, and intellectual property solutions for our clients. BLG is one of the country’s largest law firms with more than 750 lawyers, intellectual property agents and other professionals in five cities across Canada.
Section 71 of the "Ontario Energy Board Act, 1998" (the "OEB Act"), sets out various permitted activities for Ontario's licensed electricity transmitters and distributors.
Canada Energy and Natural Resources

Introduction:

Section 71 of the Ontario Energy Board Act, 1998 (the "OEB Act"), sets out various permitted activities for Ontario's licensed electricity transmitters and distributors. With certain limited exceptions, transmitters and distributors are prohibited from carrying on any business activities other than electricity transmission and distribution except through an affiliate. The prohibition had included electricity generation.

Section 71 of the OEB Act was recently amended by the Green Energy and Green Economy Act, 2009 (the "GEGEA"). The GEGEA added a new subsection 71(3), which permits distributors to own and operate certain renewable generation projects. Subsection 71(3) provides:

Exception

(3) Despite subsection (1), a distributor may own and operate,

  1. a renewable energy generation facility that does not exceed 10 megawatts or such other capacity as may be prescribed by regulation and meets the criteria prescribed by regulation;
  2. a generation facility that uses technology that produces power and thermal energy from a single source that meets the criteria prescribed by regulation; or
  3. an energy storage facility that meets the criteria prescribed by regulation.

Board Staff Compliance Bulletin on Distributor-Owned Generation: Application of Section 71(3) of the Ontario Energy Board Act, 1998

On July 7, 2010, Ontario Energy Board (the "Board") staff issued a Compliance Bulletin in which they provide guidance in relation to certain issues associated with the application of subsection 71(3) "regarding the ownership and operation of generation and energy storage facilities by electricity distributors."

The Bulletin reflects Board staff views on various questions that have arisen in respect of subsection 71(3) of the OEB Act. As is typical of Compliance Bulletins, staff confirmed that the Bulletin reflects the views of Board staff and is not binding on the Board. Key elements of the Bulletin are as follows:

  • Staff are not limiting their concept of ownership of generation or other facilities addressed in the subsection to 100% ownership by the distributor – staff believe that a controlling interest in a corporation (where the distributor holds voting shares carrying more than 50% of the votes for the election of directors; and where those votes are sufficient to elect a majority of the board of directors, consistent with the concept of control in the Ontario Business Corporations Act, referred to here as the "OBCA") is sufficient to constitute ownership, as is the control of management and key decision-making in a partnership;
  • Staff do not believe that distributors should be able to act simply as operators of generation for third parties. A distributor may contract out operations of its facilities to third parties provided that the distributor ultimately remains responsible and accountable to the Board for all applicable legal and regulatory requirements relating to the operation of the facility. However, the distributor cannot simply act as a service provider – staff feel that this would be inconsistent with the "own AND operate" wording of subsection 71(3), and that had the legislature's intention been that distributors could act as service providers, the wording would have been "own OR operate";
  • Staff do not have a concern with distributors owning multiple facilities – this approach is consistent with the government's policy of promoting the use and generation of electricity from renewable energy sources;
  • Facilities outside a licensed distributor's service area are acceptable, subject to any applicable generator licensing requirements; and
  • Notwithstanding the addition of renewable generation (within the limits set out in the subsection) to the activities that may be carried on by an electricity distributor, Section 80 of the OEB Act continues to apply.

OEB Act Section 80 Requirements:

Section 80 of the OEB Act provides that no transmitter or distributor or affiliate of a transmitter or distributor shall acquire an interest in a generation facility in Ontario, construct a generation facility in Ontario or purchase shares of a corporation that owns a generation facility in Ontario unless it has first given notice of its proposal to do so to the Board and the Board (a) has not issued a notice of review of the proposal within 60 days of the filing of the notice; or (b) has approved the proposal following a review. If the Board determines that a review is necessary, the OEB Act requires it to approve a proposal described in section 80 if it determines that (a) the impact of the proposal would not adversely affect the development and maintenance of a competitive market; or (b) the proposal is required to maintain the reliability of the transmission or distribution system of the relevant transmitter or distributor.

As noted above, this notice requirement applies not only to distributors themselves, but also to their affiliates (as that term is defined in the OBCA). In the context of a local electricity distribution company, affiliates will typically include (among others) the parent holding company; the municipality that in turn owns the shares of the holding company; and other competitive (generation and/or other services) companies controlled by the holding company and/or municipal shareholder.

The "Preliminary Filing Requirements" for Section 80 and 81 proceedings (Section 81 relates to situations in which generators intend to construct or acquire distribution and/or transmission systems) are available on the Board's web site. The form requires the proponent(s) to identify itself (themselves), other corporate family members, and the nature of the project that is the subject of the notice. Proponents must provide information about the anticipated capacity of the generation project(s) and how that capacity compares to Ontario's overall generation capacity (this relates to the concern for the maintenance of a competitive market). While not in the form at this time, distributors and their affiliates considering development of renewable generation should be prepared to provide information on whether capacity also exists on the distribution system to accommodate other parties' anticipated renewable generation projects. This is again related to concerns about the maintenance of a competitive market. Board Staff indicate in the Compliance Bulletin that revisions to the Section 80/81 Preliminary Filing Requirements are being developed and will be issued in the near future.