Australia: Projects Disputes In Australia: Recent Cases - June 2017

Last Updated: 19 June 2017
Article by Steven W. Fleming and James Ebert

Since late last year, there have been several major decisions from Australia's highest courts on important issues for stakeholders in the construction, mining and infrastructure industries. Below, we provide a summary. Some of the decisions bring welcome clarity, while others leave open important issues which stakeholders should be wary of.

High Court of Australia

Case: Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd [2016] HCA 52

In its first decision on Security of Payment legislation (in this case, on the "East Coast" model), the High Court has ruled that a payment claim (and consequent adjudication) can be set aside as invalid where there is no reference date for the payment claim.

Southern Han Breakfast Point Pty Ltd ("Southern Han") contracted with Lewence Construction Pty Ltd ("Lewence") to construct an apartment block. During construction, Southern Han gave a notice to show cause to Lewence, followed by a notice of intention to remove the work from Lewence and suspend payment. Lewence treated the second notice as a repudiation of the contract and purported to accept the repudiation and terminate the contract. Lewence then submitted a payment claim to Southern Han, which did not nominate a reference date. Southern Han served a payment schedule in response, indicating the amount to be paid was nil. Lewence then made an adjudication application, which was opposed by Southern Han on the basis that the adjudicator had no jurisdiction. The adjudicator determined the adjudication in favour of Lewence.

Southern Han sought a declaration that the adjudicator's order was void, arguing that no right to a progress payment could have arisen to enliven the adjudicator's jurisdiction because the payment claim submitted by Lewence did not include a reference date. The NSW Supreme Court held that the Building and Construction Industry Security of Payment Act 1999 (NSW) ("NSW Act") required a reference date under the relevant construction contract as a precondition to the making of a valid payment claim, and it granted the declaration sought by Southern Han on that basis. However, the NSW Court of Appeal overturned that decision.

Southern Han appealed to the High Court of Australia, where the Court upheld the appeal and confirmed that the existence of a reference date is a precondition to the making of a valid payment claim. The Court also held that in this case, no reference date could exist because the relevant reference date would have occurred only after the termination of the construction contract such that no right to payment under the NSW Act had accrued prior to that termination.

The High Court's first decision on Security of Payment legislation is a significant one for the industry. It underscores the importance of strict compliance with the statutory requirements to make a valid payment claim—in this case, the requirement for a reference date. It also explains that the existence of a right to make a payment claim under Security of Payment legislation is not an accrued right that survives termination of a contract unless the contract provides otherwise.

New South Wales

Case: Shade Systems Pty Ltd v Probuild Constructions (Aust) Pty Ltd (No 2) [2016] NSWCA 379

Notwithstanding this Court of Appeal decision, uncertainty remains as to the extent of the Court's power to review an adjudication under Security of Payment legislation for nonjurisdictional errors of law.

Earlier in 2016, the NSW Supreme Court created uncertainty as to the scope of the Court's jurisdiction to review an adjudication decision pursuant to Security of Payment legislation, having held that the Court's jurisdiction extended to any error of law on the face of the record and was not confined to jurisdictional error. The NSW Court of Appeal has now unanimously overturned that finding and confirmed that the Court's review power is confined to jurisdictional error.

The decisions concern a contract between Shade Systems ("Shade") and Probuild Constructions ("Probuild"), under which Shade agreed to supply and install external louvers to the facade of an apartment complex. Shade issued a payment claim for $324,334 under the NSW Act, but Probuild rejected the claim in its payment schedule on the basis that it was entitled to liquidated damages of $1,089,900 from Shade. An adjudicator awarded $277,755 to Shade and rejected Probuild's liquidated damages claim.

Probuild challenged the decision in the NSW Supreme Court and was successful on its alternative argument that although there was no jurisdictional error, the decision should be quashed because the rejection of the liquidated damages claim involved an error of law on the face of the record. The Court held that the adjudicator had wrongly assumed that the onus was on Probuild to demonstrate that Shade was at fault for the failure to achieve practical completion on time.

In the Court of Appeal, Shade argued that the Court had erred at first instance because its finding was contrary to binding authority in the decisions in Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421 and Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393. Probuild contended that those authorities were not binding on the point, and in the alternative sought to reopen them. While an appeal is typically heard by only three judges, given the importance of the issue in this case, the Court of Appeal was constituted by a special five-judge bench, which unanimously overturned the decision of the Court below.

While the unanimous decision from five judges of the Court of Appeal is a powerful indicator that the Court's power to review an adjudication decision is confined to jurisdictional errors, uncertainty remains because Probuild has been granted special leave to appeal to the High Court. Special leave also has been granted for the High Court to hear an appeal against a decision of the South Australian Court of Appeal (in Maxcon Constructions Pty Ltd v Vadasz & Ors [2017] SASCFC 2), which followed the NSW Court of Appeal's decision. While the South Australian Court of Appeal followed the NSW Court of Appeal decision on the basis that it was "not plainly wrong", his Honour Justice Blue expressed some doubt as to whether the decision was correct.

Accordingly, the scope of the Court's power to review adjudications remains uncertain until the High Court hears those appeals later this year, which is not likely to be before August.

Case: Walker Group Constructions Pty Ltd v Tzaneros Investments Pty Ltd [2017] NSWCA 27

The NSW Court of Appeal upheld a finding that the benefit of a defect warranty had been assigned to a third party notwithstanding that the relevant defect had arisen prior to the assignment.

Walker Group Constructions Pty Ltd ("WGC") performed a contract with P&O Trans Australia Holdings Limited ("P&O") for the design and construction of a container terminal at Port Botany in NSW. After the terminal was built, P&O assigned its leasehold interest to a subsidiary, which in turn assigned it to Tzaneros Investments Pty Ltd ("Tzaneros") through an assignment deed ("Assignment Deed").

In breach of certain "fitness for purpose" and design life warranties in the original contract, pavement in the terminal began to show cracking and spalling soon after it was laid by WGC, and before the assignment to Tzaneros. Tzaneros had known of the defective paving at the time of receiving the assignment and subsequently sued WGC for the cost of replacing it, on the basis of the fitness for purpose and design life warranties in the original contract. Tzaneros claimed the benefit of those warranties through a term in the Assignment Deed that granted it "absolutely all of the benefit of the Building Warranties" originally given by WGC.

The key question on appeal was whether the term assigning "absolutely all of the benefit of the Building Warranties" extended to the right to sue for the defective paving where the cause of action had accrued prior to the assignment. Both at first instance and on the appeal, the Court held that it did. In the course of the Court of Appeal's decision, it confirmed the fundamental importance of the "ordinary and natural" meaning of the words in interpreting the contract and provided guidance on limited circumstances in which prior negotiations will be relevant.

For the construction and projects sectors, the decision serves as a simple reminder of two points. First, it is important to consider carefully the scope of defect warranties and liability periods, and to make express in the contract any desired limitation on them in respect of their assignment as well as their duration. Second, notwithstanding the technical complexity of the work typically dealt with in a construction contract, the decision highlights the power of using plain language in the contract—arguably, it is unsurprising that the phrase "absolutely all" was held to mean exactly that.

Victoria

Case: Facade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd [2016] VSCA 247

The Victorian Court of Appeal has determined that a contractor can no longer claim payment under the Victorian Security of Payment legislation once it is placed into liquidation.

Facade Treatment Engineering Pty Ltd ("Facade"), contracted to design, supply and install facade and curtain works for Brookfield Multiplex Constructions Pty Ltd ("Brookfield"). Facade submitted payment claims pursuant to the Building and Construction Industry Security of Payment Act 2002 (Vic) ("Victorian Act") in August and September 2012. The first of these was not paid in full and the second was not paid at all, and in both instances Brookfield did not serve a payment schedule in respect of the amounts not paid. Facade was then placed into liquidation, and the liquidator commenced proceedings in the Supreme Court of Victoria to recover the amounts due under the payment claims pursuant to section 16 of the Victorian Act. Section 16 allows a party to obtain summary judgment if a respondent has failed to pay an amount claimed by a payment claim under the Victorian Act after having failed to serve any payment schedule, and it does not permit a respondent to bring a cross-claim or make a defence. Brookfield counterclaimed, arguing that the subcontractor was liable for compensation costs and liquidated damages under the subcontract.

The Victorian Supreme Court dismissed the liquidator's application, holding that the subcontractor had no entitlement to payment pursuant to section 16 of the Victorian Act. On appeal, three judges of the Victorian Court of Appeal unanimously upheld most aspects of that decision. Most importantly, the Court held that once a winding-up order had been made in respect of Facade, it was no longer a "claimant" for the purposes of the Victorian Act because it continued to exist only for the purposes of the winding-up. In coming to this decision, the Court had regard to the purpose of the Victorian Act—namely, to provide cash flow to persons who carry out construction work—and concluded that the benefits of the section are thus available only to a person who continues to perform construction work (or supply related goods and services).

That finding was sufficient to determine the matter, but in obiter, the Court of Appeal also noted that there was inconsistency between section 16 of the Victorian Act and section 553C of the Corporations Act 2001 (Cth) because section 553C establishes a right to set off debts owed by a company in liquidation against amounts owed to the company in liquidation. On that basis, the Court remarked that section 16 of the Victorian Act would be invalid to the extent it would otherwise allow a company in liquidation to recover payments while avoiding any set-off or counterclaim.

This decision brings further clarity to the position of insolvent contractors under the Victorian Act, but it also raises questions as to how the same issue will ultimately be treated in other States where a similar outcome has been reached but through a very different approach. Relatively recently, in Hamersley Iron Pty Limited v James [2015] WASC 10, the Western Australian Supreme Court considered the same issues in relation to the WA Security of Payment legislation (Construction Contracts Act 2004 (WA)). In that case, a similar practical outcome was achieved because the Court refused leave to an insolvent contractor that sought to enforce an adjudication determination against the principal. However, in that case, the Court recognised a discretion as to whether to enforce an adjudication determination, whereas the decision in the Victorian Court of Appeal suggests that as a matter of course, the right to rely on Security of Payment legislation is lost upon insolvency. If the question is one of discretion, this might allow courts to take into account whether or not a principal in fact prosecutes or proves any counterclaims it could have under s553C of the Corporations Act, whereas the approach in Victoria suggests that the actual merits of the counterclaim may not be relevant. The Victorian approach also appears to be more consistent with the approach adopted in NSW to date, including the decision in Brodyn Pty Limited v Dasein Constructions [2004] NSWSC 1230 (which the Victorian Court of Appeal considered in the course of its judgment), where the NSW Supreme Court held that the NSW Act ceased to apply once a contractor enters insolvency (though it should be noted that in that case, the Court was satisfied that the principal had established the asserted counterclaims).

While some ambiguity may remain as to precise approach in other States, in practical terms, insolvent contractors are unlikely to be able to rely on Security of Payment legislation in a way that would avoid the set-off rights of s553C of the Corporations Act.

Western Australia

Case: Apache Oil Australia Pty Ltd v Santos Offshore Pty Ltd [2016] WASCA 213

The Western Australian Supreme Court has narrowly interpreted a joint venture agreement in order to minimise limits sought to be imposed on activities that could be undertaken by the joint venture operator.

The Western Australian Supreme Court of Appeal has narrowly interpreted an exclusive operation clause in a joint venture agreement so as to permit work undertaken by one party in preparation for the joint venture. The decision highlights the importance of specificity in joint venture agreements on large construction and infrastructure projects, and the importance of accurately planning for all activities that might need to be undertaken by the joint venture in such projects.

In 2010, Apache Oil and a number of related entities ("Apache Parties") entered into a joint venture agreement ("JVA") with Santos Offshore to develop oil reserves in Western Australia. The agreement included the purchase by the Apache parties of a 55 percent interest in a retention title and certain materials listed for use in joint operations.

Under the JVA, Apache Oil was the Operator of the Joint Venture. The JVA provided that if the Operator committed a material breach of the agreement, the Operations Committee could remove them as the Operator. It also provided that operations under the agreement could be conducted only as "Joint Operations" or "Exclusive Operations". "Joint Operations" were those which were chargeable to all the parties, and "Exclusive Operations" were those which were chargeable to fewer than all the parties. The JVA prohibited all Exclusive Operations except where the proposed conduct had been proposed as a Joint Operation to the Operations Committee but had not been approved.

Santos Offshore alleged that the Apache Parties breached the JVA by undertaking certain work in preparation for development of the oil reserves. They alleged that the work was an Exclusive Operation and was a material breach. The activity undertaken by the Apache Parties included: the completion of front-end design; evaluation and investigation into items of subsea infrastructure with long lead times between order and delivery for use in the proposed work; and the entering into contracts with certain suppliers for the procurement of certain long lead time items of equipment. The development to which this activity was directed was ultimately approved by the Operating Committee in 2013.

The WA Supreme Court held that the JVA extended to "activities and operations" directed to the development of the oil reserves and not merely to physical steps taken within the area of the retention title. His Honour also held that the breach was a material breach as "unauthorised development breaches" were material breaches of the object of the JVA, namely, that "the overall control of the development of the Operating Committee was fundamental to the operation of the JVA, and the unauthorised work breaches circumvented that overall supervision."

However, the WA Court of Appeal overturned the decision in favour of the Apache Parties. The Court determined that the activity undertaken was not a breach of the JVA because the agreement did not prohibit activities outside the purpose of the JVA. The purpose of the JVA was to establish the party's respective rights and obligations with regard to operations under the retention title, including the joint exploration for, and appraisal, development and production of, petroleum. The activities undertaken by the Apache Parties in this regard were not inconsistent with this purpose.

While the focus is typically on "getting the deal done" and assuming a cooperative spirit when a joint venture agreement is negotiated, the narrow interpretation of the JVA in this decision emphasises the importance for participants to carefully craft the scope of the joint venture (and to be wary of "standard forms"), particularly in large construction and infrastructure projects where the scope of potential activities is both immense and complex.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Steven W. Fleming
 
Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.