Australia: Today's solution to yesterday's deal: managing difficult contracts, part 1

Clayton Utz Insights

Key Points:

Some problems with a contract can be caught before they even happen, and can be managed proactively to keep the project on track.

As governments and private companies look at more outsourcing and service contracts, their performance becomes more dependent upon the performance of their contractors. This is, however, old hat for the construction industry, where managing contracts has long been crucial to the success of a project.

In this two-part article, we'll first set out what we've learnt from our years in major projects about managing contracts actively and effectively – and then look at what you can do when things have gone beyond the point where ordinary management is going to work.

The first rule for managing difficult contracts is to solve small problems before they turn into big ones.

If you wait until the problem has run up a million dollars in cost overruns, both sides will be afraid of admitting any fault for fear of being stuck with the whole liability. At the front end, it is much easier to have honest, objective and productive discussions with the contractor.

That's easily said, but how do you catch small problems before they grow?

Understand the contract

Some problems can be caught before they even happen.

If you have managed any similar contracts before, and even if you haven't, there will be some areas of the contract that you can anticipate will potentially cause problems. Friction often arises at the interfaces between you and the contractor.

Submissions for approval are the most obvious, but there are many other possible interfaces: you may be rolling out software at different locations, carrying out community consultations for multiple worksites, accepting regular deliveries of particular product. Any process that will be repeated many times will cause a lot of trouble if you get it wrong.

One very common scenario in project contracts is for the contractor to be required to submit plans and designs for approval before it can get on with construction. On a large project there may be dozens or even hundreds of submissions. If there are a hundred submissions and each one takes a week longer to approve than was in the plan, that is two years' worth of delayed activity. While submissions will to a greater or lesser extent be delivered in parallel, the cumulative delay is likely to push the project into trouble.

Don't even wait for the first submission. Sit down with the contractor and agree to run the first submission as a pilot, and then set up a continuous improvement process. Good collaboration doesn't happen by accident – you need to work at it.

Doing this early in the process means it's much easier for both parties to be honest with each other. There will quite likely be faults on both sides. It is always important to give serious consideration to the possibility that the principal might be the one at fault. If your own house isn't in order it is really difficult to hold the contractor to account.

Use the governance framework

Where both parties are actively involved, it is easy to see what is happening and pick up on problems early. When only the contractor is aware of potential issues, however, it can be much harder to get visibility. This is why you should make use of the governance provisions in the contract, which can include:

  • regular meetings with the contractor;
  • regular reports;
  • a right for you or a third party to conduct audits of their project accounts and/or activities;
  • a right to demand a cure plan if there is a breach of contract.

If you are active in managing the contract you can often secure all of these things, even without a specific provision in the contract.


Meetings are important. When the parties don't communicate, trouble ensues. But you do have to prepare for them.

Have an objective for each meeting and start the meeting by agreeing that objective with the contractor: "today we want to identify the root causes of problem x".

Then stop the discussion just before the agreed closing time and ask "have we achieved our objective and if not, what will be done about it?" If you just let the meeting run on until people leave, not only have you not solved the problem, you don't have an agreed set of next steps.

Often the problem is that the contractor's project director is under so much pressure from their superiors to stick to a budget that they don't want to ask for the extra resources it would take to do the job properly. They may not want to admit to problems because of the personal consequences, or they are just too junior to be heard.

In this situation you must take the meetings to a higher level of seniority. Quite often a contract will provide for CEO one-on-ones as part of the dispute resolution mechanism, or the CEO might want to keep it on a more informal basis.

CEO meetings won't solve the problem if the contractor's CEO is being given a false picture by their own project team. To change the behaviour you need facts and evidence. Use your other governance tools of reports and audits to find the facts, then give your CEO the ammunition to present in a way that can't be ignored.

Do not fall into the trap of minimising your own part in the problem by concealing your own failings. If your CEO is confronted in the meeting by unexpected evidence that you are at fault, even if only partially, you will not only have a very unhappy CEO, you will lose all traction in managing the contractor.


The contract will give you rights to receive reports. These should be in a format that will be informative while not requiring an enormous effort in production.

The most useful reports do not merely tell you what is happening, but also show the gap between what has been achieved and what was supposed to have been achieved during the period. Visual representations can be very powerful: one useful tool is the S-curve.

Suppose there are 16 activities that need to be completed by the contractor (the activities don't have to cover the whole contract activity, and with large contracts often it's better if they don't). The plan says it will take two weeks to do each of the first two, then they'll be done at the rate of one a week, except for the last one, which will take three weeks.

These charts can be about activities completed, or money spent, or milestones achieved. Theoretically, if the contractor doesn't do anything different, then each day's delay pushes the line a day to the right, but in practice reports typically show the same end point but a steeper line on the graph.

In the illustration shown, the contractor is, at Week 16, suggesting that activities originally programmed to take 13 weeks will take just four – highly implausible. But if the S-curve is being examined regularly, the gap between forecast and actual is already visible ten weeks earlier. This offers an opportunity to ask the contractor what it will do differently to close the gap, increasing the chance of the problem being solved before it gets out of hand.

The contractor may point to contingency in the schedule, or propose additional measures such as putting in a shift on Saturdays or recruiting an extra work team. That allows you to consider how plausible those proposals are and gives an objective basis for starting productive discussions.


Independent audit reports can be very effective. When the relationship has essentially broken down, it is often easier for the parties to discuss a third party report than to accept representations from the other, particularly when the contractor refuses to admit there is a problem.

One of the authors (Louise Hart) has personal experience of a contractor who kept insisting that there were no problems with delivery: some things were "a bit late", but they were able to adjust the schedule for that, and so on. Eventually an independent third party was sent in to audit the schedule.

The audit report showed the project was so far behind that the final delivery date was now further away than it had been on the day the parties signed the contract. The independent report forced the contractor to admit the problem.

So, if you suspect there is a problem, think about sending in auditors. Look for objective, measurable facts that you can confront the contractor with.

Audit reports also help with your own stakeholders. Some of the more radical remedies discussed in Part 2 often require permission from senior management, and an independent audit is much more convincing than a mere complaint.

Cure plans

Contracts will often oblige a contractor to provide a cure plan when it is in default.

Cure plans do not have to be formal. In the schedule audit example above, a formal cure plan was not demanded from the contractor as it was arguable there was technically no default at that point. Instead, the contractor was asked what it proposed to do to remedy the situation.

Sometimes this is enough to get some action. Sometimes it isn't. In that case the contractor produced a list of things it wanted the principal to do differently. Conspicuous by its absence was any proposal involving action by the contractor.

In response, the principal wrote a strong 'letter before action' to the contractor's chief executive, which resulted in the contractor's project director being replaced by a more co-operative individual, enabling a negotiated solution to be reached.

Changing a project director is not necessarily the solution – any project which has had more than two project directors is normally a project in trouble – but if the director is the problem, they should be removed.

A less drastic course of action to encourage cooperation from an uncooperative contractor is to set up a workshop or series of workshops with a third party facilitator.

This became part of the way forward on Louise's difficult contract, but only after the project director was replaced. Key members of the project teams went on an awayday with a third party facilitator and came up with various ways of improving collaboration between the parties without altering the contractual rights and obligations.

There is an important caveat. While third party facilitation can be effective with the right facilitator, one who properly understands the contract and has the trust of the parties, but the wrong facilitator may be worse than useless.

It is too easy for a third party to look at a situation and decide that life would be simpler if the contractor didn't have to comply with the contract. Working collaboratively does not have to mean giving up your contractual rights.

Beating a jinx

Some projects are just ill-fated. If you get caught in one of those, the only solution is extreme micromanagement. Prepare every detail, agree actions, give instructions, assume that nothing will be done properly unless you check everything, every time, every day.

That includes your own team, not just the contractor. A contractor in trouble will do their best to deflect blame to you and you must avoid giving them grounds to do so. If you have to respond to something in five working days, check on progress every day, not just day five.

You must be absolutely relentless, with your own team and with the contractor. If the contract is jinxed, you have to take action every single day.

And if none of that works, there's always a legal remedy.

You might also be interested in...

Clayton Utz communications are intended to provide commentary and general information. They should not be relied upon as legal advice. Formal legal advice should be sought in particular transactions or on matters of interest arising from this bulletin. Persons listed may not be admitted in all states and territories.

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Mondaq Advice Centre (MACs)
Related Video
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.