Australia: The final design of the Emissions Reduction Fund? The ERF White Paper answers some key questions

Key Points:

While the detail of the operational and administrative aspects of the Emissions Reductions Fund still require further work, some areas are much clearer.

Although the Emissions Reductions Fund (ERF) White Paper, released on 24 April 2014, states that it contains the Government's "final design" for the ERF, it is clear that there remains considerable work to be done to finalise both the ERF and the proposed Safeguard Mechanism.

In the lead-up to the release of the White Paper, we posed eight questions it needed to answer to give industry investment certainty and to explain how the Direct Action Plan (DAP) will meet Australia's international emission abatement commitments.

The White Paper largely answers these questions, but some of the specifics of this final design will not be revealed until the release of the draft legislation and the auction guidelines, especially in relation to the conduct of auctions and to the duration of contracts.

It also remains unclear how the ERF will achieve sufficient levels of abatement to reach Australia's international ambition targets.

This article will explain the main elements of the ERF as detailed in the White Paper:

  • administrative bodies;
  • allocated funding;
  • crediting processes;
  • purchasing processes;
  • safeguard mechanism;
  • complimentary measures;
  • transition for Carbon Farming Initiative (CFI) projects; and
  • timing of the ERF review.

Expected timeframe for implementation

The Government has outlined an ambitious timeline for implementation of the ERF:

  • By June 2014: exposure draft legislation ERF released;
  • From July 2014: crediting and purchasing elements commence (subject to repeal of the carbon price);
  • By March 2015: exposure draft legislation for the Safeguard Mechanism;
  • 1 July 2015: Safeguard Mechanism commences;
  • End of 2015: review of ERF.


The Clean Energy Regulator (CER) will administer the ERF. Its functions will include conducting the auctions, issuing Australian Carbon Credit Units (ACCUs), contracting and making payments, administering reporting and managing compliance.

The White Paper announces the creation of a new body, the Emissions Reduction Assurance Committee, which will replace the existing Domestic Offsets Integrity Committee of the CFI and take on an expanded version of its functions. These largely relate to the assessment of both facility- and activity-based methods and the additionality of abatement achieved by proposed methods.



The crediting and purchasing elements of the ERF will commence "on the repeal of the carbon tax". The Government is no longer assuming that this will occur on 1 July 2014, as has been its previous position.


In order for a project to participate in the ERF there must first be a relevant approved method applying to that project, and the project must be registered by the CER.

Technical working groups will be set up to develop a range of ERF methods, building on those CFI land sector methods that are already in operation. These methods will also utilise any State- or Territory-based direct action programs that are currently in operation (such as energy efficiency schemes).

However, as approved methods are to be legislated instruments, given experience with similar exercises internationally, the production of appropriate methods could be a lengthy process. The White Paper makes clear that the Government will prioritise the development of new methods which have the potential to deliver large volumes of abatement, and for which there is likely to be market demand.

The process for calculating "additionality" (that is, the additional emissions that would otherwise have occurred in the absence of the ERF) will be incorporated into the ERF methods. Aside from existing CFI projects that will be transferred to the ERF, only new projects that achieve abatement going beyond common practice will be eligible for funding under the ERF.

After estimating the likely emissions from a proposed project using an approved method, a project proponent will then register their project with the CER. Only registered projects can participate in an ERF auction. Registration effectively provides for pre-qualification of projects as the CER will conduct due diligence on each project and proponent to ensure that the projects can meet contractual obligations for funding.

Eligible projects

Projects will be eligible to receive ACCUs for the duration of the individual project's crediting period. The standard crediting period for projects will be seven years, although the ERF will have flexibility to provide for longer and shorter crediting periods. For example, the soil carbon methodology that is currently being developed will have a 15 year crediting period.

The Government is maintaining its policy that it will not issue ACCUs until abatement is actually achieved, despite receiving submissions of the deterrent effect this may have on small projects that require upfront funding. This is to ensure that payment is only made for actual abatement. However, this presents a large upfront cost to all project proponents (except perhaps those with large-scale projects).

Special terms for large-scale projects

The White Paper indicates that under the ERF, the Government will have the discretion to enter into out-of-auction contracts with projects that are likely to deliver more than 250 000 tCO2-e of emission reductions a year, or 1.25mtCO2-e over a contract period, independent of the standard ERF auction process.

This means that these large-scale projects will not have to meet the requirements of a specific approved method, but can adopt a tailored project-specific method.

Reporting and verification

Projects must report emissions reductions to the CER. Emissions reductions must be independently verified by an auditor registered under NGERS. The CER will apply a risk-based approach to determining frequency and content of these verification reports. The White Paper indicates that the ERF will apply flexible reporting periods to assist project cash flows


Auction process

While the detail of the operation and procedures of the ERF auctions will be presented in CER Guidelines that are yet to be published, we know that there will be four auctions a year and participants will be required to submit a sealed bid for a minimum size of 2000 tonnes. To encourage competition, the Government will only purchase 80% of the emissions reductions that are below the unrevealed benchmark price set by the Government.

The Green Paper indicated that the benchmark auction prices would not be disclosed prior to the auction. The White Paper, acknowledging that this may discourage early participation in auctions, provides that prior to the first auction, the CER will have the discretion to publish the benchmark price. The Government has not, however, committed to this course. The CER will publish the weighted average price of the successful bids following each auction on the Emissions Reduction Fund Register.


The Government will enter into standard form contracts with successful bidders. The contract will guarantee purchase of emissions from the project proponent for the duration of the contract. Following the announcement of the five-year contract period in the Green Paper, there was concern that this would deter projects where abatement is achieved over a longer period. Although the Government has said that it will conduct market testing by a commercial consultant in relation to the issue of contract length prior to the first auction, it maintains its preference for five-year contracts.

As indicated in the Green Paper, contracts will contain make good provisions that will apply in circumstances where a proponent is unable to deliver the contracted emissions reductions. The White Paper confirms that this will consist of buying domestic ACCUs, although liquidated damages could be payable if the make-good requirements are not met. The CER will be able to vary contractual obligations if a project is affected by special circumstances outside the control of the project proponent, although a risk reversal buffer will continue to be applied to deal with natural events that impact on bio-sequestration projects.

The contract period will in most cases be shorter than the crediting period for the project. ACCUs generated but not purchased by the Government under the ERF process can be used in the voluntary market, or potentially be available to meet any make good obligations.

Safeguard Mechanism

Despite the importance of the Safeguard Mechanism in ensuring that emitters do not exceed historical baseline emissions after the commencement of the ERF, much of the detail of the operation of the Safeguard Mechanism is yet to developed.

The White Paper confirms that the task of designing the Safeguard Mechanism, which will provide baselines and (possible) sanctions for facilities that exceed their baselines, has been separated from the main ERF legislation and will be the subject of discrete legislation to be released by March 2015. The Safeguard Mechanism is due to commence on 1 July 2015.

The White Paper indicates that the Safeguard Mechanism will only apply to direct (scope 1) emissions and to facilities with direct emissions of more than 100,000 tCO2-e per year, including new investments. This threshold is considerably higher than the 25,000 tCO2-e pa under the Carbon Price Mechanism. In practice, this means that only Australia's top 130 emitters will be covered by the Safeguard Mechanism, equivalent to about 52% of Australia's emissions. The Government has also left open the question whether the electricity sector should be subject to the Safeguard Mechanism. If the electricity sector was to be exempted, this would significantly reduce the amount of Australia's covered emissions.

The White Paper makes clear that baselines under the Safeguard Mechanism will be based on absolute emissions and not emissions intensity factors. The baseline will be set on the highest level of emissions for a facility over the period 2009-2014 – not an average of those emissions, or a rolling average which would permit the baseline to be revised over time. Essentially, the baselines will be set at a historical maximum.

There is presently no proposal to allow baselines to be revised in order to achieve any emissions abatement target. This means that the heavy lifting to achieve Australia's current 5% target, or any post 2020 emissions abatement target, will only come through the ERF and any complementary measures that might remain.

For new or significant expansions of existing facilities, baselines will be set to reflect industry "best practice". What and how industry best practice is to be determined will be subject to further consultation.

The Government also proposes to employ a range of flexible compliance options where baseline emissions are exceeded. These include the option of multi-year compliance periods, and the purchase of credits. It is assumed that any make good for exceeding an emissions baseline will be limited to domestic ACCU's, consistent with the stated policy position for the ERF contract make good provisions.

Complementary measures

The Government has indicated that one way the ERF will meet Australia's abatement targets is for it to work in co-operation with other DAP policies to meet Australia's international emissions reductions obligations. The Green Paper requested submissions on complementary measures to assist in meeting these obligations. The White Paper states that the future 2014 Energy White Paper will include consideration of these complementary measures.

Transitioning from the CFI

The White Paper provides some detail on how land sector projects currently operating under the CFI will transition to the ERF. Essentially, it is expected that CFI projects will participate in the early ERF auctions. The ERF will amend the CFI project start dates to align with ERF projects. CFI methodologies will continue to apply, in a simplified form, under the ERF methods.

New rules relating to the ownership structure of forestry and soil carbon projects are aimed at encouraging aggregation of projects. Under the CFI, these projects can only be approved if the project developer owns the land or has another relevant property right. Under the ERF, the project developer will only have to demonstrate that they have the agreement of the landowner to participate in the ERF.

The White Paper also provides proponents of bio-sequestration projects the option to select a lesser period of permanence than currently exists under CFI. Instead of assuming a 100 year permanence obligation, a proponent can opt for a 25 year permanence period and receive 75% of the credits generated over that period.


The White Paper confirms that the ERF will be reviewed at the end of 2015, after the Government is required to make its international commitments regarding post 2020 ambition. To address market concerns about potential uncertainty arising from a review so early in the life of the ERF, the review will focus on the operational elements of the conduct of the auctions and method development, not the fundamental design of the ERF.


The White Paper has now provided some clearer answers on the design of the ERF mechanism. While the detail of the operational and administrative aspects of the scheme still require further work, some areas are much clearer.

For example, the Government's stated desire to prioritise development of methods which are capable of delivering large-scale abatement and for which there is market appetite means that projects that can deliver abatement quickly to meet the immediate imperative of the 5% 2020 abatement target – such as those in the land fill waste, waste to energy and energy efficiency (industrial and commercial) sectors – are likely to have the advantage in obtaining ERF funding.

Where there continues to remain considerable policy uncertainty is in respect of the Safeguard Mechanism – essential to ensure that any abatement purchased under the ERF is not undermined by increases in overall emissions. Initial indications in the White Paper are that baselines set are likely to err on the side of generosity, and not be subject to review.

However, draft exposure legislation for the Safeguard Mechanism is not expected for another 12 months. Given the centrality of the Safeguard Mechanism to the DAP, and the need for further consultation in relation to aspects of that mechanism, a further White Paper may ultimately be necessary.

You might also be interested in...

Clayton Utz communications are intended to provide commentary and general information. They should not be relied upon as legal advice. Formal legal advice should be sought in particular transactions or on matters of interest arising from this bulletin. Persons listed may not be admitted in all states and territories.

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Mondaq Advice Centre (MACs)
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.