Australia: Epc Contracts For Wind Energy Projects - South African Re Ipp Programme - Lessons Learned From Phases 1 And 2 (October 2012) Part 1

Last Updated: 27 October 2012


Engineering, Procurement and Construction ("EPC") Contracts are the most common form of contract used to undertake construction works by the private sector on large scale and complex infrastructure projects . Under an EPC Contract, a contractor is obliged to deliver a complete Facility to a developer who need only 'turn a key' to start operating the Facility; hence EPC Contracts are sometimes called turnkey construction contracts. In addition to delivering a complete Facility, the contractor must deliver that Facility for a guaranteed price by a guaranteed date and it must perform to the guaranteed level. Failure to comply with any requirements will usually result in the contractor incurring monetary liabilities.

Due to the flexibility, the value and the certainty derived to sponsors and lenders, EPC Contracts are being used as the main form of construction contract by project sponsors bidding for projects under South Africa's Renewable Energy Independent Power Producer ("RE IPP") Procurement Programme.

This paper is set out in two parts. Part 1 outlines the current context of renewable energy policy and legislation in South Africa, lessons learned from the lenders' bankability requirements and other key issues arising in relation to EPC Contracts in the context of the RE IPP Programme. Part 2 sets out the key features of EPC Contracts in the context of renewable energy projects more broadly.

Although the RE IPP Programme covers a number of types of renewable energy technologies (discussed further over the page), this paper focuses specifically on wind energy and the key issues arising in EPC Contracts for wind projects.


Policy context

On 17 March 2011, the South African Government approved the Integrated Resource Plan 2010 ("IRP") for electricity. The IRP outlines the Government's plan to increase South Africa's total installed electricity capacity from 260 TWh in 2010 to 454 TWh in 2030, an increase of more than 170% over the 20 years. Of this amount, 42% of the new installed capacity is planned to be sourced from renewable energy. The Government's key policy mechanism for achieving the targeted amount of installed capacity of renewable energy is the RE IPP Programme.

RE IPP Programme - overview

Under the RE IPP Programme, Bidders submit Bid responses to construct and operate renewable energy projects and sell power to Eskom.

The renewable energy technologies comprising the RE IPP Programme, and their envisaged split, are set out below:

Technology Proposed amount Percentage allocation
Onshore wind 1850MW 49.7%
Concentrated Solar Power 200MW 5.3%
Solar Photovoltaic 1450MW 38.9%
Biomass 12,5MW 0.3%
Biogas 12,5MW 0.3%
Landfill gas 25MW 0.7%
Small hydro (<10MW) 75MW 2%
Small Projects IPP (max MAW) Total threshold of 100MW 2.8%
Total 3725MW

Each of the renewable energy technologies comprising the RE IPP Programme have a set minimum capacity and maximum installed capacity.

The RE IPP Programme is comprised of five phases, pending subscription by Bidders of the total allocation of MW for each technology. All allocations for each form of technology are made available during the each Bid submission phase. Where an allocation is undersubscribed, the remaining MW will be made available to Bidders in the following phase.

The First Bid Submission Date was 4 November 2011 and the first selection of 28 Preferred Bidders was announced at COP 17 in Durban on 7 December 2011. Preferred Bidders were initially required to finalise all of their contractual arrangements by 22 May 2012 and to reach financial close by 19 June 2012. However, the date for financial close has subsequently been extended and remains outstanding, with Preferred Bidders requested to extend their Bid validity period until the end of October 2012.

The Second Bid Submission Date was 5 March 2012, and 19 Preferred Bidders were announced on 21 May 2012. Preferred Bidders were initially required to reach financial close by December 2012, but this date has been extended to 18 - 28 March 2013. The Third Bid Submission Date has also been extended from 1 October 2012 to 7 May 2013.

RE IPP Programme - proposed update

It has been recently reported that the DOE is proposing to procure an additional 3200 MW of renewable energy capacity by 2020, over and above the 3725 MW being procured currently under the RE IPP Programme.

On 9 October 2012, Engineering News reported:

Addressing a South Africa-Spain Business Summit in Johannesburg, Department of Energy (DoE) acting chief director Thabang Audat said the proposal had been sent to the National Energy Regulator of South Africa (Nersa) for its concurrence on the additional allocation.

He was unable to provide details as to how the new allocation would be divided between the various renewables technologies, but said this breakdown would be provided in a Ministerial determination, which would be published in Government Gazette within seven working days of Nersa's concurrence.

The new renewables allocation meant that there would now be more than 4 360 MW of capacity available for future bidding rounds, with the next round scheduled to close in May, 2013.

Prior to this extension only 1 165.6 MW of capacity remained unallocated under the REIPPP, following two bidding rounds during which a total of 47 projects were named as preferred bidders.

Wind Farm Projects

A wind farm typically comprises a series of wind turbines, a substation, cabling (to connect the wind turbines and substation to the electricity grid), wind monitoring equipment and temporary and permanent access tracks. The wind turbines used in commercial wind farms are generally large slowly rotating, 3 bladed machines that typically produce between 1.5 MW and 3 MW of output. Each wind turbine is comprised of a rotor, nacelle, tower and footings. The height of a tower varies with the size of the generator but can be as high as 100m. The number of turbines depends on the location of the wind farm and capacity of the turbines.

The amount of power a wind generator can produce is dependent on wind availability and speed. The term "capacity factor" is used to describe the actual output of a wind energy Facility as the percentage of time it would be operating at maximum power output.

Wind farms need to be located on sites that have strong, steady winds throughout the year, good road access and proximity to the electricity grid.

Contractual structure for projects under the RE IPP Programme

An overview of the typical contractual structure for a project financed renewable energy project is set out in Part 2. The outline below relates specifically to the contractual structure used under the RE IPP Programme. Under the RE IPP Programme, Bidders are also required to submit as part of their Bid the detailed heads of terms of the contracts that they would enter into with their contractors, equipment suppliers and other subcontractors if selected as a Preferred Bidder. In most cases this will be comprised of a detailed heads of terms for an EPC Contract and an Operating and Maintenance ("O&M") Contract.

If a Bidder is selected as a Preferred Bidder, it will negotiate and prepare fully termed EPC and O&M Contracts based on the detailed heads of terms submitted as part of their Bid.

Preferred Bidders will be required to enter, as project company, into the following non-negotiable agreements with the relevant counterparties in order to reach financial close and develop the Facility:

  • Power Purchase Agreement ("PPA") with Eskom;
  • Implementation Agreement ("IA") with the Department of Energy ("DoE");
  • Transmission Agreement or Distribution Agreement (as relevant, depending on which network the Facility will connect to); and
  • Direct Agreement,

(together "the Project Documents").

Key issues and 'lessons learned' under the RE IPP Programme to date


We have set out below some of the key requirements that Preferred Bidders will be required to meet as the project company under the Project Documents, including our experience of the lenders' bankability requirements from Phase 1 and Phase 2 of the RE IPP Programme, and consider the effect of these requirements and how they may be flowed through to the relevant contractors. The terms "Buyer" and "Seller" are used below in relation to obligations set out in the Project Documents, referring to Eskom and the project company respectively. The capitalised terms used in this section relate to defined terms from the Project Documents.

Overriding pass-through of obligations from the Project Documents

To limit gaps in liability and minimise the need for additional sponsor support, project companies will seek to ensure that the EPC Contracts used in respect of RE IPP Programme projects are bankable, in particular the obligations, risks and liabilities under the PPA and other Project Documents must be passed through to the contractor to the fullest extent that is possible and commercially feasible. The overriding "pass through" principle is that the contractor must take account of the PPA and other Project Documents in performing the EPC Contract and must not put the project company in breach of those documents. The EPC Contract should provide for an acknowledgement of pass through and assumption of risks by the EPC Contractor. We recommend that the following clause be included:

"The Contractor has reviewed the terms of the Power Purchase Agreement, Implementation Agreement, [Distribution Agreement or Transmission Agreement] and Direct Agreement (Project Documents) and, subject to specific limitations agreed in this Contract; assumes those risks relevant to the Works which are assumed by the Owner under the Project Documents; will perform its obligations under the Contract in such manner as to allow the Owner to comply with its obligations under the Project Documents regarding completion of the Facility; and must not do anything to prevent or interfere with the Owner's performance of its corresponding obligations under the Project Documents."

There are three categories of obligations, risks and liabilities that should be passed through to the contractor:

  • explicit obligations;
  • risks or potential liabilities, but no specific obligations; and
  • requirements to take certain action to allow the project and the project company to comply with the requirements of the Project Documents.

If a particular risk cannot be passed through to the contractor, the risk will need to be mitigated by some other means, such as through insurance and/or by the provision of some additional form of sponsor support.

'Pass through' and linked entitlements

Where any entitlements of the contractor arise as a result of the project company being entitled to relief under the Project Documents, including in relation to events of Force Majeure, as well as for Compensation Events, System Events or Unforeseeable Conduct, to avoid gaps in liability under the Project Documents and the need to provide additional sponsor support, the contractor's entitlement under the EPC Contract should be linked to, and limited by, reference to what the project company (as the Seller) receives under the Project Documents, rather than what the project company is or may be entitled to. We recommend that the following clause be included, subject to the project company being required to comply with the process for claiming relief under the Project Documents:

"the Contractor agrees to accept in full and final satisfaction of any Pass Through Claim, the amount agreed or determined as payable under the Project Documents."

Force Majeure

The definition of 'Force Majeure' under the PPA is an exclusive and relatively restrictive definition. For further discussion about force majeure clauses generally, please refer to the force majeure section in this paper below.

To minimise the risk of the project company being required to grant an extension of time to the contractor when the project company is not able to obtain relief under the PPA, the definition of force majeure in the EPC Contract should be back to back with the definition in the PPA.

In addition, given that the PPA does not provide a right to terminate for an extended force majeure, lenders will generally require that no such right to terminate is provided in the EPC Contract or, if such right is provided, that additional sponsor support is also provided.

If an event of Force Majeure occurs prior to the Scheduled COD, the PPA allows for an extension of time by postponing the Scheduled COD for 'such time as shall be reasonable for such a Force Majeure event, taking into account the likely effect of the delay' (clause 16.5).

The Seller will also be entitled to relief if, during any 12 month period, the cumulative duration of Force Majeure events or their consequences (each of which event must last 24 hours or longer) exceeds 60 or more days and the Seller is not entitled to bring a claim under any insurance policy is required to hold under the PPA in respect of those Force Majeure events. In such circumstances, clause 16.9 of the PPA provides the Seller with an entitlement to an extension of the Term and/or other relief from the Buyer to 'place the Seller in the same overall economic position as it would have been in but for such Force Majeure event', provided that any compensation must not be in monetary form and the total extension of the Term must not exceed ten years.

To avoid any gaps in liability arising, the project company should ensure as far as possible that the relief available under the EPC Contract for a Force Majeure event is back to back with the provisions of the PPA.

We recognise that this may be difficult to achieve in practice given the relatively narrow definition of Force Majeure in the PPA and the Self Build Agreement (to be discussed later in this paper).

Compensation Event

The definition of 'Compensation Event' under the PPA includes material breaches by the Buyer of obligations under the PPA, including failure to make payments at the relevant time.

Under clause 15.3 of the PPA, the Seller will be entitled to both an extension of time and additional costs (either additional cost incurred by the Seller before the Commercial Operation Date or capital expenditure at any time) for a Compensation Event. Relief under the EPC Contract for a Compensation Event should be back to back with this.

Under clause 15.3.2 of the PPA, the Buyer has the option to make payments for additional costs in respect of a Compensation Event in either a lump sum or by instalments. If the Buyer chooses to pay the amount in instalments, lenders will need to consider how the increased costs during construction or the additional capital costs after the Commercial Operation Date will be financed. To address this issue, we recommend that the following clause be included:

"Subject to the Contractor complying with the notice and other requirements under this Contract, to the extent that the Owner is entitled to claim relief under the Project Documents for any System Event, Compensation Event, Force Majeure and Unforeseeable Conduct, the Contractor is entitled to claim corresponding relief under the Contract mutatis mutandis, irrespective of whether or not the Owner actually claims such relief under the Project Documents, provided that where a payment must be made by the Owner to the Contractor similar to the payment contemplated in clause 15.3.2 or 17.6 of the PPA, the Owner will make payment in the manner contemplated in clause or 17.6.1 of the PPA (as the case may be), and not in the manner contemplated in clause or 17.6.2 of the PPA (as the case may be). Accordingly, the Owner will not be relieved from its obligations due to its failure to comply with the notice and other requirements under the Project Documents, or its failure to claim relief under the Project Documents."

System Event

Under clause 14.1 of the PPA, the Seller will be entitled to relief for a 'System Event', defined as delays in connecting the Facility to the grid and the unavailability of the grid. The definition of 'System Event' specifically excludes circumstances 'caused by any natural force or event'. However, the PPA does not provide any definition of the term 'natural force or event'. In addition, under clause 14.1 of the PPA, the Seller is not entitled to bring a claim in relation to a System Event unless the time that the System Event(s) have endured is greater than the Allowed Grid Unavailability Period for a Contract Year or the period that the Commercial Operation Date is delayed beyond the Scheduled COD.

Given that the duration of the 'Allowed Grid Unavailability Period' is not insignificant, representing 2% of the total hours available in a year, this may be a material issue and may not be able to be fully passed through to the contractor. If the contractor will not accept a full pass through of risks relating to the Allowed Grid Unavailability Period and the exemption for a 'natural force or event', the project company may be required to provide some form of sponsor support.

Under clause 14.1 of the PPA, the Seller will be entitled to both postponement of the Last COD and/or a Deemed Energy Payment for a System Event. 'Deemed Energy Payments' are defined under the PPA as an amount payable by the Buyer to the Seller in respect of Energy Output that would otherwise be available to the Buyer, but for a System Event or a Compensation Event, calculated in accordance with Schedule 6 of the PPA with reference to the Commercial Energy Rate and dependant on the period in respect of which such payment is due and payable.

The method by which the amount of the Deemed Energy Payment is determined is set out in Schedule 6 of the PPA. To the extent that this amount will not cover the contractor's delay costs during a System Event, this will become a risk to the project company which would require appropriate sponsor support.

Unforeseeable Conduct

The term 'Unforeseeable Conduct' under the PPA is broadly equivalent to change in law risk. Like Force Majeure, the matters included in the definition of Unforeseeable Conduct are narrower than would generally be expected and, for example, do not extend to changes in law or tax that are not discriminatory to the project. The EPC Contract should be back to back with this definition.

Under clause 17.5 of the PPA, the Seller will be entitled to compensation or relief from the Buyer to restore the general economic position of the Seller but for the Unforeseeable Conduct. This may take the form of monetary compensation or an extension of time. Note also that if the Seller benefits as a result of the Unforeseeable Conduct, the Seller will be required to pay the value of any such benefit to the Buyer.

As with a Compensation Event, the PPA provides the Buyer with the option under clause 17.6 to pay monetary compensation for Unforeseeable Conduct as either a lump sum payment or in equal monthly instalments for the remainder of the Term. Please refer to our suggested clause above in the context of Compensation Events that addresses this issue.

Scheduled COD

Under clause 4.6 of the PPA, for every day that the Commercial Operation Date is delayed beyond the Scheduled COD (unless the delay is due to an event of Force Majeure, System Event, Compensation Event or Unforeseeable Conduct), the Operating Period will be reduced by an additional day and the Expiry Date will be brought forward by one day. As a result, the Seller will effectively lose 2 days for each day that the Commercial Operation Date is delayed beyond the Scheduled COD.

The quantum of delay liquidated damages in the EPC Contract must factor in the total loss or revenue to the project due to the reduced number of days, and should also be reviewed by the project technical advisors.

© DLA Piper

This publication is intended as a general overview and discussion of the subjects dealt with. It is not intended to be, and should not used as, a substitute for taking legal advice in any specific situation. DLA Piper Australia will accept no responsibility for any actions taken or not taken on the basis of this publication.

DLA Piper Australia is part of DLA Piper, a global law firm, operating through various separate and distinct legal entities. For further information, please refer to

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Mondaq Advice Centre (MACs)
Related Video
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.