Australia: Queensland’s strategic cropping land policy - implications for mining and petroleum projects


On 23 August 2010, the Queensland Department of Environment and Resource Management (DERM) issued a paper titled 'Protecting Queensland's strategic cropping land: A policy framework' (SCL Policy). The SCL Policy outlined the government's approach to protecting Queensland's best cropping land, which it terms "strategic cropping land" (SCL). Significantly, the SCL Policy foreshadows that resource projects will be assessed to determine their impact on SCL under new legislation to be enacted in late 2011 (Proposed SCL Legislation). If the project is assessed as having the effect of 'permanently alienating' SCL, then it will not be approved, except in very limited 'exceptional circumstances'. The SCL Policy signifies a rebalancing of power between competing land uses in Queensland.

On 31 May 2011, DERM released further information about the SCL Policy and the Proposed SCL Legislation, including:

  1. a paper titled 'Protecting Queensland's strategic cropping land: Regulatory Assessment Statement' (SCL RAS) for public comment
  2. finalised trigger maps identifying the location of SCL in Queensland (Trigger Maps), and
  3. information about transitional arrangements for resource projects that will be included in the Proposed SCL Legislation.

The announcement complimented the release by DERM on 14 April 2011 of proposed criteria to assist the on ground assessment of SCL. Significantly, last week's announcement makes some important changes to the SCL framework that was detailed in the SCL Policy released in August 2010.

Key points for mining and petroleum developers

Key points for developers to note from this last week's announcement are:

  1. development that is not eligible for the transitional arrangements and is located on land assessed as SCL and forming part of a Strategic Cropping Protection Area, will not be approved if such development 'permanently alienates' the land, except in 'exceptional circumstances'
  2. development, that is not eligible for the transitional arrangements and is located on land assessed as SCL, which also has a demonstrated history of cropping and forms part of a Strategic Cropping Management Area, will need to be assessed to ensure that it avoids, minimises and mitigates any impact on SCL
  3. SCL (as identified in the Trigger Maps) will be implemented through two separate and distinct areas of SCL in Queensland, Strategic Cropping Protection Areas (of which there are two) and a Strategic Cropping Management Area
  4. from 31 May 2011, transitional arrangements will apply to existing resource projects that have reached certain eligibility milestones in the project approval process, allowing development to proceed on land identified as SCL (and developers are able to seek clarification from DERM to confirm their project's eligibility)
  5. further information has been provided about key concepts to be included in the SCL Legislation, including what are 'exceptional circumstances' and 'permanent alienation' (however uncertainty remains and developers should consider engaging with key stakeholders to ensure their views are considered in the development of the Proposed SCL Legislation)
  6. pasture land for grazing is not captured by the SCL Policy, and
  7. proponents will have an opportunity to make submissions in relation to the SCL RAS.

Transitional arrangements

Transitional arrangements will apply to 'undecided' coal, mineral, gas and petroleum tenure applications that have met the following eligibility milestones in their assessment:

  1. for resource production projects that require or have voluntarily undertaken an Environmental Impact Statement (EIS):
    1. if a mining lease application—the project had, by 31 May 2011, finalised EIS Terms of Reference (TOR) and there was also a certificate of application under section 252 of the Mineral Resources Act 1989 (Qld) (MRA)
    2. if a petroleum lease application—the project had, by 31 May 2011, finalised EIS TOR and an application had been lodged under the Petroleum Act 1923 (Petroleum Act) or Petroleum and Gas (Production and Safety) Act 2004 (Qld) (PGPSA) and accepted by the relevant administering authority, or
    3. for a future petroleum lease application lodged after 31 May 2011 under the Petroleum Act or PGPSA —the project had, by 31 May 2011, finalised EIS TOR and an existing Authority to Prospect (ATP) where the ATP area was part of the project covered by the finalised EIS TOR.
  2. for resource production projects not requiring an EIS — there is a draft Environmental Authority (EA) under the Environmental Protection Act 1994 (Qld) (EP Act) granted by 31 May 2011, or
  3. for projects that relate to expansion of existing mines under the MRA – the proponent must hold exploration permits or mineral development licences which are contiguous with the existing production tenure as at 23 August 2010 and a certificate of application under section 252 of the MRA is obtained by August 2012.
    These transitional arrangements will be reflected in the Proposed SCL Legislation and take effect from 31 May 2011. Projects that meet the eligibility milestones will be allowed to proceed on land identified as SCL (however projects that do not have final environmental approvals will still be required to avoid, minimise and mitigate any impact on SCL). Meanwhile, resource projects that do not meet the criteria of the transitional arrangements will be subject to the full effect of the Proposed SCL Legislation (set out below).

Strategic Cropping Protection Areas and Strategic Cropping Management Areas

SCL will now be implemented in Queensland through two separate and distinct areas of:

  1. Strategic Cropping Protection Area (SCPA), and
  2. Strategic Cropping Management Area (SCMA).

The location and boundaries of the SCPA and SCMA are indentified in the new Trigger Maps. The Trigger Maps are designed to be used as a starting point for developers in determining whether an area is SCL. The Trigger Maps are not definitive and SCL will ultimately be defined by on-ground assessment in accordance with the proposed criteria for the identifying SCL. Guidelines are expected to be released shortly by DERM which will assist with on-ground assessment.

Importantly, the introduction of SCPA and SCMA means resource development encroaching on SCL is to be assessed differently depending on what area the development falls within. These differences are explained in further detail below.

(a) Strategic Cropping Protection Areas

SCPAs are large aggregations of best cropping land under intense and imminent development pressure. The Trigger Maps identify the location of two SCPAs in Queensland:

  1. an area near Emerald in Central Queensland (Central Protection Area), and
  2. an area including the Darling Downs, Lockyer Valley, Granite Belt and South Burnett in Southern Queensland (Southern Protection Area).

Under the Proposed SCL Legislation, development that is not eligible for the transitional arrangements and encroaches on land confirmed as SCL and forming part of the Central Protection Area or Southern Protection Area, will not be allowed to proceed if it 'permanently alienates' the land, except in demonstrated 'exceptional circumstances'.

(b) Strategic Cropping Management Areas

Land identified as SCL within a SCMA must have a demonstrated history of productive cropping. Broadly this will be satisfied by land that has been cropped at least three times between 1 January 1999 and 31 December 2010 (noting guidelines are currently being developed for this requirement).

Under the Proposed SCL Legislation, development that is not eligible for the transitional arrangements, is located on land confirmed as SCL, has a demonstrated history of cropping and forms part of the SCMA, will be assessed to ensure:

  1. that the development avoids encroaching on SCL to the maximum extent possible
  2. where the development is not able to avoid SCL, its impacts must be minimised, and
  3. where the development is not able to avoid SCL, its impacts must be minimised.

The introduction of SCMA represents a stripping back of the intent of the original SCL Policy, which proposed to prohibit permanent alienation on any SCL. DERM has also developed a number of principles to guide how the mitigation requirements will be implemented under the Proposed SCL Legislation.

Further information about key concepts for mining and petroleum developers

DERM has also provided some clarification in relation to a number of key concepts to be included in the Proposed SCL Legislation, as follows.

(a) Permanent alienation

As mentioned above, projects which result in permanent alienation of SCL will not be allowed to proceed, unless exceptional circumstances apply. Therefore, the key concern for developers is what types of activities will be considered to 'permanently alienate' SCL.

The Proposed SCL Legislation will set out the types of resource activities that will be deemed to permanently alienate SCL. However, DERM has stated that permanent alienation will occur when a use located on or near SCL will endure for 50 years or more (and prevents cropping occurring at that time or in the future). Examples of permanent alienation, as provided by DERM, include:

  1. where a legal impediment, such as resource extraction activities for longer than 50 years, prevents land from being used for cropping, or
  2. where long lasting impacts caused by resource extraction activities, such as contaminated land, subsidence, major excavation and changes to soil structure, mean the land cannot be restored to SCL.

Based on these examples, it remains to be seen what types of resource activities will be deemed to permanently alienate SCL, particularly considering the majority of resource developments have a project life less than 50 years. It also remains unclear whether activities which do not involve large disturbances to the surface of the land (such as petroleum projects and underground mining) will be assessed as permanently alienating the SCL.

DERM mentions that well-designed CSG operations may be able to be accommodated under Proposed SCL Legislation without permanently alienating the land, because gas wells and pipelines are usually considered to have a temporary impact as the land can be restored back to SCL at the end of the development. However, DERM has stated that high-impact CSG infrastructure such as water storage ponds and gas compression stations may permanently impact on SCL and a proponent would not be able to undertake these activities in SCPAs, except in limited 'exceptional circumstances'.

DERM has not provided certainty on the concept of 'permanent alienation' and the land rehabilitation standards required to enable the crop productivity of land to be restored. It is therefore possible that developers who are able to demonstrate that they can avoid permanent alienation by fully reinstating land to its previous productive capacity may comply with the Proposed SCL Legislation. Other jurisdictions have successfully dealt with mine rehabilitation to restore crop productivity (for example in the United States), thereby allowing competing agricultural and mining interests to co-exist. Therefore in practice, it may be that the Proposed SCL Legislation will not bar future mining and petroleum development on cropping land but rather place a greater emphasis on the rehabilitation and restoration requirements of a project. The SCL Policy has indicated that conditions for restoration and other environmental matters will continue to be addressed under the EP Act.

While DERM's most recent announcement provides some clarification, in the absence of the Proposed SCL Legislation, developers will not be in a position to make a definitive determination as to whether their projects proposed activities will be deemed to permanently alienate SCL. This uncertainty means that the development of the concept of permanent alienation by DERM leading up to the introduction of the Proposed SCL Legislation is likely to remain a priority issue for resource developers.

DERM has indicated that it will be responsible for assessing and determining 'permanent alienation', as the authority responsible for administering the Proposed SCL Legislation.

(b) Exceptional circumstances

To satisfy the 'exceptional circumstances' exemption for projects causing permanent alienation, resource developers will need to demonstrate that:

  1. there is no alternative site and the resource does not exist anywhere else in Queensland which is not on SCL (i.e. a rare mineral only found in certain parts of the State), and
  2. a significant community benefit is provided to the State by the development.

DERM's most recent announcement suggests that a significant benefit to the State may include a social or community service, or an economic benefit to the State that overrides the need to protect SCL from permanent alienation (although the economic benefit cannot be the sole consideration). Satisfaction of the exemption is however expected to be a 'rare and uncommon'.

Regulatory assessment statement

The SCL RAS aims to:

  1. evaluate the cost recovery options in terms of the impacts of the implementation of the SCL Policy on business, communities and the government, and
  2. identify the most efficient and fair way to recover those costs.

The closing date for mining and petroleum developers to comment on the RAS is 5 pm, Wednesday 29 June 2011.

Practical considerations

Mining and petroleum developers have no doubt already taken steps to consider whether their project will be subject to the Proposed SCL Legislation by firstly, considering whether part or all of their project's land is located on areas identified in the Trigger Maps as SCL and, if so, considering whether the project is eligible for the transitional arrangements (and seeking clarification with DERM to confirm the same). Developers and investors of resource projects are also likely to be attempting to evaluate and quantify (where possible) the likely costs and delays that the implementation of the Proposed SCL Legislation may have on their projects.

Mining and petroleum developers should also consider the implications of the SCL Policy in progressing their resource projects. This may include:

  1. reconsidering the nature and location of the activities proposed by their current project (where possible, disturbance of SCL should be avoided)
  2. where the project land includes SCL, applying to have the project land excluded from the Trigger Maps where they can show the land does not satisfy the proposed criteria for on-ground assessment of SCL, and
  3. entering arrangements with landowners that provides access to the project land to undertake necessary on-ground assessment to confirm whether the land is SCL, according to the proposed criteria.

Next steps

DERM has indicated that it will continue to develop the SCL Policy in consultation with the SCL Stakeholder Advisory Committee and feedback received through public consultation. The next key step for mining and petroleum developers will be the release of the Proposed SCL Legislation (which will follow the release of a Draft State Planning Policy (SPP) for public consultation).

The proposed SCL Legislation will provide greater clarity and certainty for developers, particularly with regards to what types of resource development will be deemed to 'permanently alienate' SCL. Developers should consider engaging with stakeholders in the SCL Stakeholder Advisory Committee to ensure their views are considered in the development of the Proposed SCL Legislation.

Please contact us if you would like further information or advice on the implications of the Proposed SCL Legislation on your resource project.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on

Click to Login as an existing user or Register so you can print this article.

Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Mondaq Advice Centre (MACs)
Up-coming Events Search
Font Size:
Mondaq on Twitter
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
Email Address
Company Name
Confirm Password
Mondaq Topics -- Select your Interests
 Law Performance
 Law Practice
 Media & IT
 Real Estate
 Wealth Mgt
Asia Pacific
European Union
Latin America
Middle East
United States
Worldwide Updates
Check to state you have read and
agree to our Terms and Conditions

Terms & Conditions and Privacy Statement (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.


Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.


Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.


A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.


This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.


If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.


This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at and we will use commercially reasonable efforts to determine and correct the problem promptly.