Nigeria: Nigeria's Power Privatisation Reaches Final Act

Last Updated: 21 February 2014
Article by Sola Arifayan and Chukwbuike Onwuzurumba

The privatisiation process, initiated in 1999 and reaching a definitive milestone in 2013, has been one of the most talked about developments and investment opportunities in the region. In placing all power generation and distribution infrastructure in private sector hands, the reforms hope to completely reshape the industry. Sola and Chukwubuike discuss the process, its success so far, remaining risks and what it might mean for Nigeria's diesel and petrol generator-dependent economy.

When did you begin working on power sector laws and regulations and how has your practice developed since then?

I started in 2000 with Arthur Andersen. Arthur Andersen was part of a group that was engaged by the government to do the work that resulted in the passage of the Electric Power Sector Reform Act (2005). I joined when that bit of work was running from 2000-02 and the Act was drafted as part of that exercise, although it did not get passed until March 2005.

By mid-2005, the Bureau of Public Enterprises (BPE), the entity largely responsible for driving the reforms, felt a need to fast track the reforms provided for in the Act. I think the background to that was that the end of the administration of former president Olusegun Obasanjo was approaching and BPE was under some pressure to implement the Act. This resulted in the legal work for the corporate restructuring of the PHCN (Power Holding Company of Nigeria), the legal drafting of the market rules for the sector (based on a draft prepared by BPE's market design consultant) and the legal work for the transfer of the assets of the PHCN. I led the engagement while at my former firm. This also led to my serving on a committee set up by the then Minister of Power and Steel to coordinate the initiation of the Transitional Stage of the competitive market in the NESI. I went into partnership at Ikeyi & Arifayan in February 2007 and I have since spent about 50% of my time doing legal work in the sector, advising various parties on sector rules and regulations, as well as contractual and other legal matters.

What's your evaluation of the power sector privatisation process so far? What stage is it at, has it achieved what you hoped it would?

I am somewhat surprised by how well the transactions have turned out. Starting in 2011, the government of Nigeria has been trying to privatise its entire power sector infrastructure apart from the transmission system, which is going to remain owned by the government through the Transmission Company of Nigeria Plc (TCN). Transmission here is defined as the conveyance of electricity at voltage levels equal to or more than 132kV. All assets for the generation and distribution of power below 132kV and delivery to customers are being privatised to strategic investors through a sale of majority shareholding. Nigeria's three hydroelectric dams are being concessioned.

Over the last year and a half the government has gone through the process of privatising, essentially offering up for sale as separate companies entities in the power sector that up to this date have operated as a single, integrated company. Although the successor companies that are being privatised were all registered in November 2005, they continued to operate as one "PHCN". The arrangements stipulated in the Market Rules for a shadow market were never implemented. It is not clear that the commercial and communication infrastructure required for these entities to operate independently in a functional power market are in place or have been adequately tested. Potential investors have raised many issues about the transactions and industry contracts and many of these issues remain unresolved. Yet on the February 21 2013, winning bidders for virtually all the companies offered for privatisation paid the initial 25% of the consideration. I find it surprising – if you had asked me three years ago if it was possible to privatise the system so quickly, I would have said no, we are not ready.

Hopefully the system will be able to accommodate the inevitable shock that will come from the transition from a vertically and geographically integrated monopoly to a sector with multiple players across various aspects of the value chain.

What measures did the government take to provide security to investors and incentivise bidders?

There are two aspects to that. On incentives, investments in power utilities attract what in Nigeria is called 'pioneer status'. This is a tax holiday for the first three years of a company commencing business renewable for up to five years. What that means is that essentially there should be no taxes to be paid by those companies for the first five years, including dividends paid out to shareholders. There are also other fiscal incentives for gas-fired generation and tax and duty exemptions for downstream gas-to-power generation.

Beyond the incentives, the government also tried to put together a credit support or risk mitigation package, particularly for IPPs and power generation companies. The government set up the Nigerian Bulk Electricity Trading Company Plc (NBET) to purchase power generated by the privatised generation companies, what we call the 'Gencos', as well as IPPs. NBET will buy power from the generation companies and sell to the distribution companies (Discos). Government has made efforts to mitigate risk of payment defaults (by NBET and Discos) by arranging for a Partial Risk Guarantee (PRG) with the World Bank. The initial plan was for the PRG package to be ready and in place for the privatisation. I am not aware of any company or investor for which the PRG is in place at this time and investors have been told to approach the World Bank and negotiate PRG's directly. The process is likely to take about 18 months at the minimum.

What are the issues that private investors in the power sector or in any other project might run into?

Generally, if you are developing a new project or for the privatised entities, you are expanding capacity (and this applies to other energy investments) then you have to get the relevant regulators to approve your investment programme or issue the necessary permits. As expected, bureaucracy can get in the way. Regarding the power sector, NERC's processes have improved significantly but we still find that the licensing process may take more than the six month statutory limit. The regulator's view of this is that most delays are attributable to incomplete or deficient documentation by applicants.

Beyond that, when we come to the power sector specifically, I think, and let me be colloquial, that the elephant in the room that hasn't been addressed is transmission. Right now, we have less than 4,000MW of power on the national grid system and everybody agrees that that's way too small for the power needs of Nigeria. The government is currently in the process of completing ten power plants, comprising what is called the National Integrated Power Projects (NIPP). Those ten power plants have a cumulative capacity of about 4,770MW. Add to that the various Greenfield IPPs (independent power producers) being promoted as well as brownfield expansion of newly privatised plants and we are going to see generation almost triple over the next few years. On the distribution side also we are seeing private investors coming in to ensure that the power delivered into the distribution system is delivered to the consumer, but what of the transmission system that remains owned by the government of Nigeria? The Roadmap for Power Sector Reform issued by government in 2010 indicated that transmission capacity just about matched existing generating capacity. Right now, we're about to see anything from double to triple generation capacity through the system. So my view is that this is one key risk factor in the industry.

We've already mentioned the credit enhancement for investment in the sector on the generation side. There is a lot of uncertainty as to how it will work. And then there is the issue of fuel for power generation. Most of Nigeria's power generation capacity is natural gas based. There's been some talk about more hydropower plants (government has actually recently contracted for the 750MW Zungeru Power Plant) and also there are one or two coal-fired power plants that have been discussed, but by far the majority of new power generation is gas based. While Nigeria is a very gas rich territory – we have the eighth biggest reserves of natural gas in the world – not a lot of work has been done to develop the gas fields, particularly for domestic use. The petroleum companies are refusing to sign gas sale agreements with a term that exceeds ten years. The argument is that if they are going to sign gas supply agreements for longer than ten years, they need to take investment decisions as regards drilling, exploring and exploiting of additional fields. Many IOCs are not making such assurances because of all the uncertainty relating to the passage or non-passage of the Petroleum Industry Bill (PIB) that is meant to reform the petroleum sector.

Is there any indication on when the PIB might be passed?

Last year the new executive bill was introduced and that appears to have been making its way through the National Assembly, slowly. If we go by what we hear from government it does look to me as if there is an indication that it will actually be passed into law sometime over the next few months. But it has been that imminent in the past.

[Chukwubuike]: Yes, and I think what you find now is that it appears to be getting even more complicated because of what you might call a north-south divide right now in the National Assembly as far as the PIB is concerned. It appears that opposition to the bill is coming from the northern part of Nigeria and that may well be a major issue, given the balance of the Nigerian political system.

Is there any room for renewable energy in power generation?

It's not a question that's easy to answer. First, regarding hydro, it is renewable energy but it's so conventional that very often when we think of renewables we don't think of hydro. The good thing about hydro that I would mention is that right now about a quarter to a third of Nigeria's power comes from the three large hydro plants. Government is building another large plant and is talking about numerous small hydro plants.

Beyond hydro, we could look at wind and then solar which have generated some discussion in Nigeria. The problem is that there is no special tariff or regulatory framework for such renewables in Nigeria. The regulator, NERC, has a unit responsible for renewables, but it does not appear very active. We have not seen a major move towards creating a space for renewables. About two years ago, the regulator licensed a (5MW) solar plant in a northern state in Nigeria but I'm not quite sure how that project has gone... the sense we get is that NERC is more concerned now about getting some stability into the system before focusing on renewables. Around 2000, the government engaged a German firm, Lahmeyer, to undertake wind mapping and preliminary studies across Nigeria to determine optimal locations for wind generation projects. But as we speak there is no special regime that has been put in place to ensure those projects get developed and right now everyone is focused on getting the system stabilised through conventional projects.

Why is reform of the power sector so important to the Nigerian economy?

Nigeria's per capita consumption of electricity is one of the lowest in Africa. Industrialisation is impossible without power. We're not quite sure how any significant economic activity can take place in an organised manner without proper supply of electricity. Most businesses run on petrol or diesel generators, which is not efficient for the economy. Between 1979, when the most recent power plants were built, and the year 2000, when the AES Barge Project in Lagos was started, there wasn't any significant investment in power infrastructure in Nigeria. Our population has almost doubled in that period. Even the existing systems weren't properly maintained.

An example I can give is in a different industry: telecommunications. In the early 1980s through to the 1990s if you wanted a telephone line you applied and queued up at the national monopoly provider, but in 1999-2000 we liberalised the system and now Nigeria is probably the largest telecoms market in Africa. We are going to see this kind of explosion in power but it will be in a different way, because the fundamentals are different. We are already beginning to see a lot of innovation. Now we are seeing innovation in terms of small decentralised plants that take gas and deliver power literally next door. So I think that without a doubt the sector could grow in a tremendous way and I think there is sufficient space for that growth.

[Chukwubuike]: And similar to what you had in telecoms, beyond the evolution that you see in the sector itself there will also be in the future some kind of spill-over effect, if you like, in professional services, even in all kinds of support businesses. The potential is great.

On your website you mention that you provide "innovative practical solutions". Could you elaborate on what that means in the Nigerian context?

There are two aspects to that – one is that we do more than just pick up the law and read it. Because of our knowledge of the industries in which we practice, we're able to find solutions that fit within the law but also push the envelope to accommodate the peculiar circumstances of the client. We're also able to hold the conversations that are needed to clarify legal and regulatory uncertainties in new areas. Because of our multidisciplinary backgrounds and practical knowledge of what regulators and other counterparts think, we are able to innovate and to help design new structures beyond traditional ways of thinking.

And what is the main piece of advice you would give to prospective investor in the power sector or in any other sector?

I think it is similar to what we would say to anyone looking to invest in Nigeria generally, you need to do a rigorous due diligence of the asset you are looking to invest in as well as of your partners. It goes without saying that you have to understand the sector and the rules that guide it and more importantly understand the asset you are investing in and understand the people you are looking to partner with locally to make the investment. For a power generation project you need to be sure of the source and the reliability of gas supply and related to that issue, that you are sourcing gas in a manner that allows you to enjoy the optimal price for power generation. It also goes without saying that you need to look at your funding sources and confirm that with your technology and the pricing that the economics of your transaction works. So essentially, look before you leap and do as much due diligence as possible on your asset and on your partners.

Previously published by IFLR.com

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
 
In association with
Related Topics
 
Related Articles
 
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert for
This service is completely free. Access 250,000 archived articles from 100+ countries and get a personalised email twice a week covering developments (and yes, our lawyers like to think you’ve read our Disclaimer).
 
Email Address
Company Name
Password
Confirm Password
Position
Mondaq Topics -- Select your Interests
 Accounting
 Anti-trust
 Commercial
 Compliance
 Consumer
 Criminal
 Employment
 Energy
 Environment
 Family
 Finance
 Government
 Healthcare
 Immigration
 Insolvency
 Insurance
 International
 IP
 Law Performance
 Law Practice
 Litigation
 Media & IT
 Privacy
 Real Estate
 Strategy
 Tax
 Technology
 Transport
 Wealth Mgt
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates
Registration (you must scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions