COVID-19 – Impact On The Performance Of Contracts

GS
Goldman Sloan Nash & Haber LLP

Contributor

Goldman Sloan Nash & Haber LLP logo
For more than 40 years, Goldman Sloan Nash & Haber (GSNH) LLP has helped leading businesses, entrepreneurs and individuals successfully navigate the maze of corporate & commercial law to help protect and grow their businesses. Our mid-sized law firm is based in downtown Toronto and provides advice across all major practice 
A force majeure clause in a construction contract temporarily excuses a party from performing its obligations under the contract where an unexpected event prevents performance.
Canada Coronavirus (COVID-19)
To print this article, all you need is to be registered or login on Mondaq.com.

A force majeure clause in a construction contract temporarily excuses a party from performing its obligations under the contract where an unexpected event prevents performance. Force majeure is distinct from the legal doctrine of frustration which has a higher threshold and releases the parties from all future obligations under the contract.

In order for a force majeure clause to apply to the current COVID-19 pandemic, the invoking party must show that:

  1. COVID-19 is a force majeure event within the meaning of the particular contract entered into by the parties; and
  2. COVID-19 was directly responsible for any delay in the performance of the contract, including the possibility of temporarily preventing any performance from continuing until the impacting event subsides.

The Government of Ontario released a List of Essential Workplaces (the "List"). Section 28 of the List includes construction work and services, including demolition services, in the industrial, commercial, institutional and residential sectors. The complete List is available here. Accordingly, a party must carefully review the contractual terms to determine whether to invoke a force majeure clause.

Parties should also review their contract to determine if another delay clause may be used to extend the period to perform the contract with or without additional compensation and ensure that proper timely notice of any delay due to COVID-19 is provided. For example, section GC 6.5.3 of a standard CCDC-2 2008 contract may permit a contractor to extend the time to complete the contract due to delay caused by COVID-19 on the basis that it is a "cause beyond the Contractor's control".

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More