This article was written for the Texas Contractor and first appeared here.
It is a common occurrence for a contractor or subcontractor to encounter a situation where they are ordered to perform extra work without a signed change order. There may be the promise of a change order to come, or simply a unilateral change directive. This may or may not cite contract provisions, but almost every contract we see includes a provision allowing the owner to issue unilateral work directives. These provisions are intended to keep the work moving despite changes. However, this growth in scope places the contractor or subcontractor in a difficult position when a properly executed change order is not provided.
Those contracts also typically require the contractor to proceed with directed work even if a dispute over scope or pricing exists. You should expect that a court will enforce such provisions in most cases. The contractor and subcontractor are now financing the job with little or no leverage to expedite that change order and the ability to collect payment for the work.
Savvy contractors have been seeking limits on such directed changes in contract negotiations. In 2023, the Texas Legislature followed suit, giving contractors and subcontractors a tool to limit directed changes. Two new statutes, Texas Government Code Section 2251.0521 and Texas Property Code Section 28.0091, which apply to contracts entered into on or after September 1, 2023, function to limit the right of owners and contractors to impose substantial changes in scope upon a contractor or subcontractor without their consent. We'll discuss the statute applying to public and private work separately, but they are largely the same: if the contractor (or subcontractor) receives a directive and the value of that change plus other unresolved directives totals 10 percent or more of the original contract value, the contractor (or subcontractor) can decline the work.
Public Project Protections
Under Texas Government Code Section 2251.0521, a contractor for a public project, which is defined as a vendor under the Texas Government Code, may elect not to proceed with additional work directed by a governmental entity under a public work contract if the following occurs: the vendor has not received a written, fully executed change order for the governmental entity-directed additional work; and the total actual or anticipated value of the additional work under the vendor's contract terms, plus any previous governmental entity-directed additional work for which the vendor has not received a written, fully executed change order exceeds 10 percent of the vendor's original public work contract amount.
Similarly, a subcontractor for a public project may elect not to proceed with additional work directed by a vendor under a subcontract if: the subcontractor has not received a written, fully executed change order for the governmental entity-directed additional work from the vendor; and the total actual or anticipated value of the additional work under the subcontractor's subcontract terms, plus any previous governmental entity-directed additional work for which the subcontractor has not received a written, fully executed change order exceeds 10 percent of the subcontractor's subcontract amount. Ultimately, a vendor or subcontractor who elects not to proceed with additional work as provided by this section is not responsible for damages associated with the election not to proceed.
Private Project Protections
Under Texas Property Code Section 28.0091, a contractor or subcontractor for a private project may elect not to proceed with additional work directed by an owner if: the contractor or subcontractor has not received a written, fully executed change order for the owner-directed additional work; and the total actual or anticipated value of the additional work, plus any previous owner-directed additional work for which the contractor or subcontractor has not received a written, fully executed change order exceeds 10 percent of the contractor's or subcontractor's original contract amount. A contractor or subcontractor who elects not to proceed with additional work as provided by this section is not responsible for damages associated with the election not to proceed.
Navigating the Statutes
In each statute it matters not whether the total of 10 percent of the original contract value comes from the new directed change or the aggregate of all unresolved directed changes. Once that threshold has been met, the contractor or subcontractor may refuse to proceed with the new additional directed work without a signed change order.
It is important to note that these new statutes do not extend beyond that new change directive. The contractor and subcontractors remain responsible for performing their originally contracted scope of work. The purpose of these new statutes is to prevent an owner or contractor from requiring a contractor or subcontractor to add significant additional work to their scope without the assurance of a properly executed change order, thereby, removing much of the risk from the performing contractor or subcontractor.
The statutes do not explicitly state the method of providing notice of a contractor's or subcontractor's election to not perform additional work pursuant to one of the statutes. However, the performing party should:
Comply with requirements in original contract documents
Make the election not to perform in writing as soon as possible after receipt of the direction to perform additional work
Include possible consequences in the notice, including delay to the work
Ask if the owner would like you to continue with the work that would be changed by the directive in question
Clearly lay out the basis for the election in the notice by identifying the additional work that exceeds 10 percent of the contract price, or in the instance that the minimum 10 percent of the contract price was reached cumulatively through the aggregate of multiple past and present unsigned change orders, then a summary of all additional work relied on to reach the minimum should be included
Clearly indicate in the notice that this election not to perform is made pursuant to either the private or public statute, as applicable to each project
Considering the Challenges
Contractors and subcontractors should begin tracking the current value of unresolved directed changes, and contractors should consider some potential practical problems.
The statutes allow subcontractors to refuse to do work after that 10 percent threshold has been met. What if the contractor wants to do the work (or would agree to perform because it wants to keep the relationship going), but a subcontractor might be in a position to refuse the change? The contractor should be consulting with the affected subcontractor(s) and might consider if and when it will have to get parallel pricing from another subcontractor in order to protect its position with the owner.
Also, consider that the legislation does not prohibit waiver of the new statutory rights by contract. Watch for such waivers in future contracts. And for that matter, the statute doesn't prohibit contractors from negotiating lower threshold percentages in a contract.
Practical project developments have pushed more of the project finance burden onto contractors and subcontractors. The new statutes offer contractors and subcontractors some protection from further financing pressure. Additionally, they provide an opportunity for collaboration; owners now have an incentive to resolve outstanding change directives, even if their incentive is to be able to issue more. Consider scheduling regular meetings with the owner, in order to avoid any limitation on future directed changes.
The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.