Executive Summary

Geological sequestration is just one tool for companies and governments to use to achieve carbon neutrality. Our Environment, Land Use & Natural Resources Group explores the hurdles California is discovering as its legislature seeks to make carbon capture an integral part of its emission-reduction strategy.

  • Permitting of CCS projects is infrequent and expensive
  • The uncertainty of post-injection site care and long-term liability
  • Pathways forward

A bill pending before the California State Senate could boost support for carbon capture and sequestration projects. The California Climate Crisis Act (AB 1395), which has already passed the Assembly, sets a state policy to achieve net-zero greenhouse gas emissions as soon as possible, and no later than 2045. The bill recognizes the need for a variety of carbon capture and storage (CCS) technologies to achieve these dramatic reductions. Gov. Gavin Newsom recently directed the California Air Resources Board and other agencies to devise plans to meet the neutrality target 10 years earlier, by 2035.

Carbon capture removes carbon dioxide from an emissions stream at a power plant or industrial facility. New technology also allows for the removal of carbon dioxide directly from the air. Once removed, this captured carbon can be permanently stored by the injection of carbon dioxide via a well into deep rock formations for long-term storage. "Beyond carbon stored in plants and soils through natural solutions, putting the captured carbon away involves storing it permanently and safely thousands of feet underground as CO2, in porous rock of the same kind that makes up California's oil and gas fields."

In order to meet the state's ambitious goals of net carbon neutrality, the current language of AB 1395 recognizes that CCS will play a critical role in climate mitigation by reducing emissions in the atmosphere. The federal government is likewise encouraging the implementation of CCS projects. Congress has enacted the Section 45Q tax credit, which provides up to $50 per metric ton of sequestered CO2. The current language of the infrastructure bill pending in Congress also allocates over $12 billion for CCS projects. These significant investments signal the importance of CCS to the country's climate change strategy.

While CCS will play a significant role in achieving carbon reductions, substantial permitting and regulatory hurdles must be surmounted for these projects to be developed and implemented at the scale contemplated by California's aggressive policies. 

Permitting of CCS Projects Is Infrequent and Expensive

The EPA regulates geological sequestration through its Underground Injection Control (UIC) Class VI permit. To ensure the safety of underground sources of drinking water, the Class VI rule includes stringent requirements for all phases of a project. States, however, can apply for primacy to take over management responsibilities from the EPA. Only North Dakota and Wyoming have obtained primacy for Class VI wells so far, but more states may seek primacy as geological sequestration becomes a more viable and popular undertaking. Facilitating geological sequestration projects will require recognition of its challenges and cooperation among industry leaders, policymakers, and other stakeholders to navigate the complex regulatory landscape. 

Despite the benefits of geological sequestration in reducing carbon emissions, the EPA has issued only six Class VI permits to date, four of which expired without any well construction. The small number of these permits can largely be attributed to the complicated and relatively new permitting process. Streamlining this process is essential to the nation's long-term climate mitigation strategy-the United States has enough geological storage capacity for hundreds of years of CO2 emissions. California, in particular, has significant opportunities for geological sequestration, with 90% of natural gas power plants, cement plants, and refineries reportedly located within 50 km of a potential sequestration site.

The Class VI rules, which were modeled after the Class I Industrial and Municipal Waste Disposal Wells rules, adopt a very precautionary approach. The application requirements are therefore extremely onerous, iterative, and time intensive, with an average of six years to receive approval for a permit. If the state intends to meet its ambitious goals, it may need to obtain primacy over the program to adopt a more risk- and performance-based approach. This change will accelerate the permitting process to meet the recommended goals of issuing a permit to drill within six months of application and a permit to inject within six months of receiving a well completion report. 

The Uncertainty of Post-Injection Site Care and Long-Term Liability

Site operators are typically liable for damages caused by the storage site during all phases of the project, including monitoring, mitigation, and remediation of health or environmental impacts. After injection operations are complete, the operator generally remains liable. The Class VI rules set a 50-year default post-injection site care period, though it can be adjusted at the discretion of the EPA administrator. However, under California's Low-Carbon Fuel Standard (LCFS) CCS Protocol, project operators must monitor sites for 100 years to receive LCFS credits. These long-term liabilities and responsibilities increase costs and discourage project development. 

Some states, such as Montana, North Dakota, and Louisiana, allow liability for stored CO2 to be transferred to the state upon meeting certain criteria. For example, Montana would assume liability after a 30-year post-injection site monitoring period. State assumption of liability from the beginning of a project would further incentivize early-mover projects. Similarly, Texas and Mississippi established trust funds that can be used for monitoring and remediation after the state assumes liability. 

These types of programs would encourage investment and reduce uncertainty for companies seeking to implement CCS projects. 

Ownership of Pore-Space Rights

Many property documents do not define who owns the pore-space rights on a site, which makes acquiring carbon storage rights difficult for CCS project developers. Only a few states have addressed the issue, with Montana, Wyoming, and North Dakota defining subsurface pore space as the property of the surface owner. To inject CO2, a project developer would therefore need to either own the pore-space rights or receive permission from the owner. This could increase costs of storage and create conflicting uses of the subsurface. For most saline formation CO2 storage projects, securing these pore-space rights could require agreement from hundreds of landowners. Conflicting uses may also arise when the subsurface is used for oil, gas, or geothermal energy production. Moreover, no mechanisms currently exist to grant access and use to pore-space rights for CCS projects on federal or state lands. 

Some states allow forced unitization of mineral resources, which means that if some percentage of owners agree, the remaining owners can be forced to participate. This has yet to be extended to pore-space rights, but North Dakota adopted an analogous approach that allows for amalgamation of pore-space rights.

Only six states have addressed the ownership of CO2 post-injection: Montana, Wyoming, North Dakota, Texas, Oklahoma, and Louisiana. In those states, the project operator owns the CO2 until liability is transferred to the state, and the pore-space owner, if different from the operator, is not responsible for the CO2 at any time. Louisiana also allows the project operator to transfer the CO2 ownership while the CO2 is in the storage facility.

These issues would need to be resolved in California to encourage investment in and development of CCS projects. 

Pathways Forward

Although the Class VI permit approval process may raise complicated legal issues, project developers have successfully received permits before. The first permit approvals involved constant back-and-forth between project developers and the EPA to navigate and clarify the regulatory pathway, which future developers can benefit from. These past projects can provide useful insight moving forward.

Under the existing system, the long permitting process is mainly attributed to extensive discussions between project developers and the EPA so the agency could understand the technical bases for the Class VI permit application. Because the process is new, it is extremely iterative, requiring frequent exchanges of additional information as the application progresses. Communication with the regulator is therefore key to understanding and meeting the requirements under a new regulatory regime.

Alston & Bird's attorneys have substantial experience in CCS projects at the federal and state levels and would be happy to answer any questions your company may have about a CCS project.