Madgwicks Lawyers has been serving clients since 1975 with reliable legal advice, clear explanations of outcomes, and practical options. Their deep expertise helps clients navigate complex matters by providing informed decision-making. The firm prioritizes developing long-term relationships with clients locally and globally, adding value beyond legal services. With over 100 staff and expertise in key practice areas, Madgwicks is an award-winning commercial firm. As part of Meritas, they are connected to a global alliance, offering business law services in 92 countries.
This Act will ensure prompt and fair payment for construction work and is a mechanism to resolve payment disputes.
Australia Real Estate and Construction

The SOPA Act

The Building and Construction Industry Security of Payment Act 2002 (the Act) is a crucial piece of legislation that governs payment issues in the building and construction industry in Victoria. The Act aims to provide a quick, cost-effective resolution mechanism for payment disputes in the industry and has significant implications for builders, contractors, and other parties involved in construction contracts in Victoria.

In reality, there can be severe and costly consequences for not properly complying with the Act.

What is the Building and Construction Industry Security of Payment Act 2002?

The Act is a Victorian legislation that applies to certain construction contracts for work carried out in Victoria. The Act seeks to ensure prompt and fair payment for construction work and provides a mechanism for resolving payment disputes in the industry. The Act applies to a wide range of parties involved in the construction process, including builders, subcontractors, and suppliers.

Important Issues to know

1. The Payment Claim
Under the Act, a builder or contractor can issue a payment claim to the party responsible for payment under the construction contract. The payment claim must identify the work that has been carried out, the amount claimed, and the due date for payment.

2. The Payment Schedule
The party who receives the payment claim must respond within ten business days by issuing a payment schedule. The payment schedule must identify the amount that will be paid, the reasons for any withholding, and the due date for payment.

3. Adjudication
If the payment dispute remains unresolved after the payment schedule has been issued, either party can refer the matter to adjudication. Adjudication is a fast, cost-effective process that aims to provide a quick resolution to payment disputes. The adjudicator will consider the evidence presented by both parties and make a determination on the amount payable.

4. Enforcement
If the adjudicator's determination is not complied with, the party owed money can seek to enforce the determination in court. The determination can be enforced as if it were a court judgment, and there are significant penalties for failing to comply with the determination.

5. Time Limits
The Act has strict time limits that apply. A payment claim must be issued within three months of the work being carried out, and an adjudication application must be made within ten business days of the payment dispute arising.