You would be surprised how often parties get it wrong and
don't execute their contracts properly. If a document is not
properly executed as a deed then the limitation period reduces to 6
years, instead of 12 years.
If you intend to execute your building contract, sub-contracts,
appointment or any other contracts as deed make sure that you:
1 Sign the full and completed document
1.1 If you have signed a document as a deed,
but it is not complete and pages are to be appended or inserted
once complete, then you have not signed the same physical document
and according to recent case law the deed may be invalid.
1.2 Make sure all of the Contract Documents
which form part of the Contract are appended or physically
present.
1.3 When the last party has signed, then the
Contract can be completed by dating it. Do not date it before it
has been signed by all parties.
Thomas Eggar LLP is a limited liability partnership
registered in England and Wales under registered number OC326278
whose registered office is at The Corn Exchange, Baffin's Lane,
Chichester, West Sussex, PO19 1GE (VAT number 991259583). The word
'partner' refers to a member of the LLP, or an employee or
consultant with equivalent standing and qualifications. A list of
the members of the LLP is displayed at the above address, together
with a list of those non-members who are designated as partners.
Regulated by the Solicitors Regulation Authority. Lexcel and
Investors in People accredited.
Thomas Eggar LLP is not authorised by the Financial
Services Authority. However, we are included on the register
maintained by the Financial Services Authority so that we can carry
on insurance mediation activity which is broadly the advising on,
selling and administering of insurance contracts. This part of our
business, including arrangements for complaints and redress if
something goes wrong, is regulated by the Solicitors Regulation
Authority. The register can be accessed via the Financial Services
Authority website. We can also provide certain further limited
investment services to clients if those services are incidental to
the professional services we have been engaged to provide as
solicitors.
Thesis Asset Management plc, our associated financial
services company, provides a comprehensive range of investment
services and advice. Thesis is owned by members of Thomas Eggar LLP
but is independent of and separate to it. No lawyer connected with
Thomas Eggar LLP provides services through Thesis as a practicing
lawyer regulated by the Solicitors Regulation Authority. Thesis is
authorised and regulated by the Financial Services Authority.
Thesis has its own framework of investor protection and
professional indemnity cover but Thesis clients do not enjoy the
statutory protection of solicitors' clients.
The contents of this article are intended as guidelines for
clients and other readers. It is not a substitute for considered
advice on specific issues. Consequently, we cannot accept any
responsibility for this information or for any errors or
omissions.
To print this article, all you need is to be registered on Mondaq.com.
Click to Login as an existing user or Register so you can print this article.
n the English decision in West -v- Ian Finlay & Associates, the Court considered if a net contribution clause could offer any protection or limitation of liability to an architect who faced claims in relation to damages allegedly caused by a main contractor.
In the case of Aspect Contracts (Asbestos) Ltd v Higgins Construction Plc, [2013] EWHC 1322 (TCC), Mr Justice Akenhead, had to consider when, bearing in mind limitation issues, a party which is dissatisfied with the substance of an adjudicator’s decision needs to issue proceedings and seek to challenge and overturn that decision.
"Atkins Ltd v Secretary of State for Transport", a recent TCC case, gave guidance on the grounds for a "serious irregularity" challenge under section 68 of the Arbitration Act 1996.
In an increasingly challenging market, ensuring that a property is "ready for sale" has become crucial to the successful completion of transactions, helping to save clients time and money.
As the UAE matures beyond 'emerging market' status, preservation of the natural environment is becoming an increasing priority for almost every governmental and quasi-governmental authority.
Government amendments to the permitted development regime came into force today with some significant changes to how buildings can be used and the extent to which homeowners can extend their properties without requiring planning permission.
Some comments from our readers… “The articles are extremely timely and highly applicable” “I often find critical information not available elsewhere” “As in-house counsel, Mondaq’s service is of great value”